Hume Pipe Culvert BOQ — Worked Example for an 8 m ...

7 min read · BOQ · Estimation · Culvert · Hume Pipe · PMGSY · Worked Example
Home / Knowledge / Hume Pipe Culvert BOQ — Worked
BOQEstimationCulvertHume PipePMGSYWorked Example📖 7 min · 1,687 words

Hume Pipe Culvert BOQ — Worked Example for an 8 m × 900 mm NP3 Rural Culvert

Hume pipe culverts are the single largest category of cross-drainage structure built in rural India — PMGSY road specifications mandate at least one culvert every 500-1000 m of road. The CPWD-standard configuration is a single-line NP3 or NP4 class RCC pipe (per IS 458) laid on PCC bedding with brick masonry headwalls and earth backfill. This article walks through a complete BOQ for the most common rural-road configuration — 8 m length × 900 mm internal diameter NP3 pipe with brick headwalls, wing walls and downstream apron.

Project Scenario

You're estimating a culvert under a PMGSY rural road crossing a small seasonal nallah. Carriageway is 5.5 m wide; with 1.25 m extensions on each side for the headwalls, the culvert length is 8 m total. The drainage catchment requires a 900 mm pipe (verified via Rational method against the design 25-year storm). Standard NP3 pipe is adequate — this is a rural panchayat road, not an NH/SH.

Design specification at a glance
  • Length: 8 m (carriageway width + headwall extensions)
  • Pipe diameter: 900 mm internal
  • Pipe class: NP3 (medium duty, PMGSY rural roads, ≤ IRC Class B loading)
  • Pipe-invert depth: 1.2 m below NGL
  • Headwalls: Both ends, 1.2 m above NGL, 230 mm (full-brick) F.P.S. masonry
  • Wing walls: 4 nos, 1.5 m each, 45° splay
  • Downstream apron: 2 m × 1.5 m wide stone pitching / CC slab

The Complete BOQ — 9 Items in CPWD DSR 2023

# DSR Code Item Description Unit Quantity
12.8.1Earthwork in trench, all-kinds-of-soil, lead ≤ 50 m16.20
24.1.8PCC 1:4:8 bedding + cradle haunch fill3.69
319.35.3NP3 RCC pipe 900 mm dia, supplied + laid + jointedm8.00
46.1.2F.P.S. brick masonry in cement mortar 1:6, in headwall foundation3.11
56.4.2F.P.S. brick masonry in cement mortar 1:6, in headwall above plinth4.97
62.25Backfill with excavated earth, watered + compacted in 200 mm layers9.31
76.4.2F.P.S. brick masonry in cement mortar 1:6, in 4 wing walls (45° splay)3.23
87.1.1Stone pitching / CC apron on downstream bed0.90

The live BOQ Builder evaluates these formulas in real time — change pipe diameter (450 / 600 / 900 / 1000 / 1200 mm), pipe class (NP3 / NP4), headwall height, wing wall length, or apron length, and the quantities update instantly.

How Each Quantity Was Computed

1. Excavation — Item 2.8.1

Trench width = pipe diameter + 600 mm working space (300 mm each side for bedding + jointing access):

Trench width = 0.9 + 0.6 = 1.5 m
Trench depth = depth below NGL + PCC bedding
= 1.2 + 0.15 = 1.35 m
Excavation = 8 × 1.5 × 1.35 = 16.2 m³

2. PCC bedding + cradle — Item 4.1.8

Two parts: (a) 150 mm flat PCC bed under the full trench width; (b) cradle / haunch fill — 25 % of pipe diameter for NP3, taken on 70 % of the trench width to account for the pipe occupying the centre:

Flat bed = 8 × 1.5 × 0.15 = 1.80 m³
Cradle haunch = 8 × 1.5 × (0.9 × 0.25) × 0.7 = 1.89 m³
Total PCC = 3.69 m³

For NP4 heavy-duty pipes (NH / SH carriageway), the cradle is 50 % of pipe diameter per IRC SP 13 Cl. 5.3 — substantially more PCC for the same pipe.

3. RCC pipe — Item 19.35.3

Single line of 900 mm NP3 pipe, 8 m total — DSR rate is per running metre and covers supply + laying + jointing with collar / spigot-and-socket. Use DSR code 19.35.3 for 900 mm NP3; the equivalent NP4 code is 19.36.3 (≈ 18 % more expensive).

4 + 5. Brick headwalls

Both ends, 1-brick (230 mm) full-thickness, F.P.S. class-7.5 brick. The Builder allows for headwall thickness of 0.345 m to account for a strengthening bullnose / capping detail.

Headwall length = trench width + 1.5 m extension = 1.5 + 1.5 = 3.0 m each
Headwall foundation height = 1.2 (NGL depth) + 0.15 (PCC) + 0.15 (plinth band) = 1.5 m
Headwall above-ground = 1.2 (above NGL) + 0.9 (pipe dia) + 0.30 (cap) = 2.4 m

Foundation masonry (both ends) = 2 × 3.0 × 0.345 × 1.5 = 3.11 m³
Above-ground masonry (both ends) = 2 × 3.0 × 0.345 × 2.4 = 4.97 m³

6. Backfill — Item 2.25

Excavated earth re-fills the trench above the pipe. The pipe + cradle occupy ~25 % of the trench volume; the rest needs back-fill:

Backfill = trench above pipe − pipe cross-sectional area × length
= 8 × 1.5 × 1.2 − 8 × π × 0.45²
= 14.4 − 5.09 = 9.31 m³

Backfill must be done in 200 mm layers, watered and tamped — IS 1200 Part 1 Cl. 5.4. Otherwise settlement opens the road over the pipe.

7. Wing walls — Item 6.4.2

4 wing walls (2 at each end of culvert, 45° splay outward from pipe outlet / inlet). Each 1.5 m long, 230 mm thick:

Wing wall average height = 60 % of (headwall_above + headwall_found) ≈ 2.34 m
Wing wall masonry = 4 × 1.5 × 0.23 × 2.34 = 3.23 m³

8. Downstream apron — Item 7.1.1

Stone pitching or CC slab on the downstream bed prevents pipe-outlet scour:

Apron volume = 2 (length) × 1.5 (width) × 0.30 (thickness) = 0.9 m³

NP3 vs NP4 — Which to Use

NP3 medium-duty (DSR 19.35.x) is rated for occasional vehicular loading up to IRC Class B + 1.2 m earth cover above pipe crown. Use for PMGSY rural roads, village internal roads, panchayat roads, farm-access roads, residential colony storm drains.

NP4 heavy-duty (DSR 19.36.x) is rated for IRC Class A + AA wheel loads and full 70R tracked-vehicle loading. Mandatory for NH / SH carriageway crossings, district roads, urban arterials, industrial corridors, any culvert under cover < 1 m.

Cost difference: NP4 is roughly 12-20 % more expensive than NP3 for the same diameter. Specifying NP4 unnecessarily on rural roads is a common over-design that inflates the BOQ by ~10 %. Conversely, using NP3 on NH/SH under-spec the structure and risks pipe failure under 70R loading.

Pipe Diameter Selection (Hydraulic Sizing)

Rule-of-thumb: pipe diameter = function of (catchment area × design rainfall intensity ÷ Manning hydraulic capacity). PMGSY default values:

TerrainCatchment (ha)Pipe Ø (mm)
Plain< 5600
Plain5-20900
Plain20-501200
Sloped / forested< 5900
Sloped / forested5-201200
Sloped / forested> 20Box culvert (use Box Culvert Builder)

Always verify via hydrological assessment for actual design — never rely on this table alone for tender-grade work.

What This BOQ Excludes

  • Pipe-collar / jointing material (cement mortar collar bands at each joint) — typically absorbed in DSR 19.35.3 rate, but verify with your local SOR
  • Cushion concrete on inlet/outlet bed (IRC SP 13 Cl. 8.3) — separate stone-pitching / CC item
  • Stone pitching on side slopes — DSR 7.X random rubble for embankment protection
  • Guard stones at headwall ends — to prevent vehicle from striking corner masonry
  • Reflective markers + signage — IRC 67 + IRC 67-2012 for culvert delineation
  • Road overlay on top of backfill — separate bituminous or concrete road BOQ

Common Estimation Mistakes

  • Forgetting wing walls — open-end pipes without wing walls suffer erosion at the pipe inlet/outlet from concentrated flow. 4 wing walls of 1.5 m each is a baseline; longer for high-flow drains.
  • Specifying NP4 on a rural PMGSY road — wasted ~10 % on pipe cost. NP3 is rated for the actual loading.
  • Skipping the downstream apron — over a 2-3 year cycle, scour erodes the pipe outlet bed and undermines the headwall. The 0.9 m³ apron prevents this for ~₹4-6k.
  • Backfill in single lift — must be 200 mm layers, watered + tamped. Single-lift backfill causes road settlement over the pipe within 6-12 months, leaving a pothole.
  • Under-sizing the trench width — at least 300 mm working space on each side of the pipe for cradle compaction and jointing access. Smaller trenches force the contractor to skip cradle compaction → pipe rocks → joints fail.
  • Using RCC headwall when brick suffices — for PMGSY rural roads, F.P.S. brick masonry is adequate and 30-40 % cheaper than RCC. Reserve RCC headwalls for NH/SH culverts where wheel-impact loads are likely.

What Changes for a Different Culvert

  • Larger catchment (1200 mm pipe) — switch pipe code to 19.35.5; trench width grows to 1.8 m; cradle volume scales up proportionally.
  • NH / SH carriageway — pipe class to NP4 (19.36.x), headwalls to RCC (5.2.2), apron concrete to M20 (5.3 or 5.1.2), wing walls extended to 2.5-3 m each.
  • Two-line or three-line culvert (high catchment, low cover) — duplicate the pipe + bedding cost per line, single shared headwall sized to span all lines.
  • Cover < 600 mm above pipe crown — special slab cover (mini-slab culvert) required; switch to Slab Culvert Builder.
  • State-PWD SOR — switch to your state's road-works SOR (typically more current for PMGSY work).

Get Your Culvert's Cost in 30 Seconds

→ Open the Hume Pipe Culvert BOQ Builder

Change pipe diameter, class (NP3 / NP4), length, headwall and wing-wall dimensions, apron length — the Builder regenerates the BOQ + downloads Excel with formulas embedded. Customize for Your Project →

References & Companion Reading

Join InfraLens WhatsApp Channel
Get updates on new articles, tools, and IS code insights
More Articles
Clause references and parameter values are sourced from official BIS and international standards. Always refer to the original standard document for design decisions.
💬 Join the Discussion
Q: What has been your experience with this topic on site?
Q: Do you have any tips to share with fellow engineers?
Click a question to start your comment
Leave a Comment
0/500
No comments yet. Be the first to share your thoughts!