| S.No. | Field / Checkpoint | Reference | Status |
|---|---|---|---|
| A. INSTALLATION VERIFICATION | |||
| A1 | FAS panel + detectors + MCPs + sounders + cabling per drawing Acceptance: Drawing-conformity | Per NBC 2016 Part 4 | OK NC NA |
| A2 | Detector types per zone — smoke / heat / multi-criteria / aspirating Acceptance: Per design | Per occupancy + risk | OK NC NA |
| A3 | Cable type (FRLS / FRLSH) + segregation from power Acceptance: Per code | IS 2189 Cl. 9 | OK NC NA |
| A4 | Battery backup — 24 hrs standby + 30 min alarm Acceptance: Per spec | Per IS 2189 | OK NC NA |
| B. ZONE-WISE FUNCTIONAL TEST | |||
| B1 | Detector test (smoke / heat) — each zone Acceptance: Tested + logged | All detectors trigger alarm | OK NC NA |
| B2 | MCP (Manual Call Point) test — each zone Acceptance: Tested | Activation → panel + sounders | OK NC NA |
| B3 | Sounder + visual alarm test — each zone Acceptance: Sound level meter test | Audible 65 dBA at far point | OK NC NA |
| B4 | Public address voice evacuation (if integrated) Acceptance: Tested | Per spec | OK NC NA |
| C. INTERFACES + EMERGENCY ACTIONS | |||
| C1 | AHU shutdown on fire alarm (smoke control) Acceptance: Tested | Per fire strategy | OK NC NA |
| C2 | Lift recall to ground floor Acceptance: Tested | Per fire strategy | OK NC NA |
| C3 | Door release (mag locks) on fire alarm Acceptance: Tested | Per spec | OK NC NA |
| C4 | Hooter + strobe in all common areas Acceptance: Tested | Per spec | OK NC NA |