QA/QC  › Structural Design & Loading  › Structural Works ITP
Plan · QC-STR-PLN-001
Structural Works ITP
22 checkpoints across 5 sections. Before structural construction; communicated to all stakeholders
22 Checkpoints
5 Sections
Once per project, updated if scope changes
Contractor, QC Engineer

Checklist Preview

S.No.CheckpointIS RequirementStatus
A. HOLD POINTS (Work Stop - Approval Required)
A1HP-1: Foundation Design Approval - Before excavation starts
Acceptance: Design reviewed & approved per QC-STR-CHK-001; Soil test report available; SBC confirmed
Clause 1.1 — Design verification
OK
NC
NA
HOLD
A2HP-2: Reinforcement Details Reviewed - Before casting foundation/superstructure
Acceptance: Rebar schedule reviewed; Cover requirements verified; Bending details confirmed; Drawings signed
Clause 1.2 — Detailing review
OK
NC
NA
HOLD
A3HP-3: Concrete Grade & Mix Design Approved - Before concrete delivery to site
Acceptance: Concrete grade per design; Mix design provided; Trial mixes tested; f'c confirmed
Clause 1.3 — Material qualification
OK
NC
NA
HOLD
A4HP-4: Steel/Connection Approval - Before fabrication or assembly of steel frame
Acceptance: Steel grade certs provided; Connection design reviewed; Welding qual certs available
Clause 1.4 — Steel qualification
OK
NC
NA
HOLD
A5HP-5: Seismic Detailing Review - If seismic zone III+, before reinforcement placement
Acceptance: Ductile detailing per IS 13920 reviewed; Critical zone reinforcement verified; Witness inspection done
Clause 1.5 — Ductility verification
OK
NC
NA
HOLD
B. INSPECTION POINTS (QC Inspections - Must Pass)
B1IP-1: Concrete Strength Verification - At 7 days and 28 days per batch via compression test / cube samples
Acceptance: 7-day ≥75% of f'c; 28-day ≥f'c per spec; Test certs provided; Failed cubes investigated
Clause 2.1 — Material testing
OK
NC
NA
HOLD
B2IP-2: Reinforcement Placement Inspection - Per floor/section; bar size, spacing, cover verified
Acceptance: Rebar schedule matched; Cover ±10mm; Spacing per drawings; Laps >50 dia; Photographic evidence
Clause 2.2 — Rebar QC
OK
NC
NA
HOLD
B3IP-3: Formwork Inspection - Before concrete pour; levelness, stability, support adequacy checked
Acceptance: Level ±5mm/m; Supports adequate; Deflection <L/250; Props per design; Checklist signed
Clause 2.3 — Temporary works
OK
NC
NA
HOLD
B4IP-4: Concrete Curing Verification - During curing period; moisture, temperature monitored
Acceptance: Curing 7 days minimum (14 days for low-strength); Moisture maintained; Temperature 5-35°C; Log kept
Clause 2.4 — Curing compliance
OK
NC
NA
HOLD
B5IP-5: Steel Fabrication Inspection - Connection details, welds, bolt tightness verified per shop inspection report
Acceptance: Welds per code; UT/RT tests done; Bolts torqued; Certs provided; NDT reports reviewed
Clause 2.5 — Steel QC
OK
NC
NA
HOLD
C. WITNESS POINTS (Contractor to Notify QC; QC Must Be Present)
C1WP-1: Concrete Pouring - First pour per structure type/location witnessed
Acceptance: Concrete quality checked (slump, consistency); Placement method observed; Curing started immediately
Clause 3.1 — Pour witness
OK
NC
NA
HOLD
C2WP-2: Concrete Strength Sample Collection - Cube samples made during concrete pour
Acceptance: 3 cubes minimum per batch; Proper making & curing; Labeling complete; Chain of custody maintained
Clause 3.2 — Sample integrity
OK
NC
NA
HOLD
C3WP-3: Formwork Removal - Witnessed for timing & method; member inspected post-removal for defects
Acceptance: Timing per code (7d min); Method controlled; Surface condition assessed; Cracks/spalling noted
Clause 3.3 — De-shuttering
OK
NC
NA
HOLD
C4WP-4: Steel Member Erection - First member installed; connections bolted/welded in presence of QC inspector
Acceptance: Alignment verified; Connections per design; Welds observed; Torque values checked
Clause 3.4 — Steel erection
OK
NC
NA
HOLD
C5WP-5: Load Test - Structural load test conducted per QC-STR-TST-001; deflection & behavior monitored
Acceptance: Load test report generated; Deflection ≤ allowable; No visible distress; Member performance acceptable
Clause 3.5 — Capacity verification
OK
NC
NA
HOLD
Showing 15 of 22 checkpoints ·
A. HOLD POINTS (Work Stop - Approval Required)
A1HP-1: Foundation Design Approval - Before excavation starts
Clause 1.1 — Design verification (IS 456)
Design reviewed & approved per QC-STR-CHK-001; Soil test report available; SBC confirmed
OKNCNAHOLD
A2HP-2: Reinforcement Details Reviewed - Before casting foundation/superstructure
Clause 1.2 — Detailing review (IS 456)
Rebar schedule reviewed; Cover requirements verified; Bending details confirmed; Drawings signed
OKNCNAHOLD
A3HP-3: Concrete Grade & Mix Design Approved - Before concrete delivery to site
Clause 1.3 — Material qualification (IS 456)
Concrete grade per design; Mix design provided; Trial mixes tested; f'c confirmed
OKNCNAHOLD
A4HP-4: Steel/Connection Approval - Before fabrication or assembly of steel frame
Clause 1.4 — Steel qualification (IS 800)
Steel grade certs provided; Connection design reviewed; Welding qual certs available
OKNCNAHOLD
A5HP-5: Seismic Detailing Review - If seismic zone III+, before reinforcement placement
Clause 1.5 — Ductility verification (IS 13920)
Ductile detailing per IS 13920 reviewed; Critical zone reinforcement verified; Witness inspection done
OKNCNAHOLD
B. INSPECTION POINTS (QC Inspections - Must Pass)
B1IP-1: Concrete Strength Verification - At 7 days and 28 days per batch via compression test / cube samples
Clause 2.1 — Material testing (IS 456)
7-day ≥75% of f'c; 28-day ≥f'c per spec; Test certs provided; Failed cubes investigated
OKNCNAHOLD
B2IP-2: Reinforcement Placement Inspection - Per floor/section; bar size, spacing, cover verified
Clause 2.2 — Rebar QC (IS 456)
Rebar schedule matched; Cover ±10mm; Spacing per drawings; Laps >50 dia; Photographic evidence
OKNCNAHOLD
B3IP-3: Formwork Inspection - Before concrete pour; levelness, stability, support adequacy checked
Clause 2.3 — Temporary works (IS 456)
Level ±5mm/m; Supports adequate; Deflection <L/250; Props per design; Checklist signed
OKNCNAHOLD
B4IP-4: Concrete Curing Verification - During curing period; moisture, temperature monitored
Clause 2.4 — Curing compliance (IS 456)
Curing 7 days minimum (14 days for low-strength); Moisture maintained; Temperature 5-35°C; Log kept
OKNCNAHOLD
B5IP-5: Steel Fabrication Inspection - Connection details, welds, bolt tightness verified per shop inspection report
Clause 2.5 — Steel QC (IS 800)
Welds per code; UT/RT tests done; Bolts torqued; Certs provided; NDT reports reviewed
OKNCNAHOLD
C. WITNESS POINTS (Contractor to Notify QC; QC Must Be Present)
C1WP-1: Concrete Pouring - First pour per structure type/location witnessed
Clause 3.1 — Pour witness (IS 456)
Concrete quality checked (slump, consistency); Placement method observed; Curing started immediately
OKNCNAHOLD
C2WP-2: Concrete Strength Sample Collection - Cube samples made during concrete pour
Clause 3.2 — Sample integrity (IS 456)
3 cubes minimum per batch; Proper making & curing; Labeling complete; Chain of custody maintained
OKNCNAHOLD
C3WP-3: Formwork Removal - Witnessed for timing & method; member inspected post-removal for defects
Clause 3.3 — De-shuttering (IS 456)
Timing per code (7d min); Method controlled; Surface condition assessed; Cracks/spalling noted
OKNCNAHOLD
C4WP-4: Steel Member Erection - First member installed; connections bolted/welded in presence of QC inspector
Clause 3.4 — Steel erection (IS 800)
Alignment verified; Connections per design; Welds observed; Torque values checked
OKNCNAHOLD
C5WP-5: Load Test - Structural load test conducted per QC-STR-TST-001; deflection & behavior monitored
Clause 3.5 — Capacity verification (IS 456)
Load test report generated; Deflection ≤ allowable; No visible distress; Member performance acceptable
OKNCNAHOLD
Showing 15 of 22 ·
Inspection Sign-Off
ITP APPROVED & READY
ITP APPROVED WITH MODIFICATIONS
ITP REJECTED — RESUBMIT
Remarks / Conditions
Name / Sign / Date
Prepared By (Contractor)
Name / Sign / Date
Reviewed By (QC/Consultant)
Name / Sign / Date
Approved By (Client)
Name / Sign / Date