QA/QC  › Structural Design & Loading  › Structural Design Review
Register · QC-STR-REG-001
Structural Design Review Register
7 checkpoints across 1 sections. Throughout design phase; updated after each design review cycle
7 Checkpoints
1 Sections
Daily/per design submission
QA Engineer, Project Manager

Checklist Preview

S.No.CheckpointIS RequirementStatus
A. REGISTER COLUMNS & DEFINITIONS
A1Column 1: Date - Date design received, reviewed, approved (DD-MM-YYYY format)
Acceptance: Sequential dates; Format consistent; No gaps
Cl. 1 — Date tracking
OK
NC
NA
HOLD
A2Column 2: Design Item - What was designed (e.g., Foundation, Columns, Beams G+3, Slabs, Connections)
Acceptance: Item clearly described; Consistent naming; Covers all structural elements
Cl. 2 — Design component identification
OK
NC
NA
HOLD
A3Column 3: Design Engineer - Name of engineer who prepared design calculations
Acceptance: Name recorded; Title/firm noted; Contact info available if needed
Cl. 3 — Responsibility tracking
OK
NC
NA
HOLD
A4Column 4: Design Status - Status at review date (Submitted, In Review, Approved, Approved with Conditions, Rejected)
Acceptance: Status clearly stated; Consistent terminology; Links to approval/NCR
Cl. 4 — Status tracking
OK
NC
NA
HOLD
A5Column 5: Review Checklist - Reference to QC checklist used (e.g., QC-STR-CHK-001)
Acceptance: Checklist ID noted; Version/revision documented; Traceability maintained
Cl. 5 — QC linkage
OK
NC
NA
HOLD
A6Column 6: Issues/Comments - Design issues, discrepancies, queries raised during review (or 'None')
Acceptance: Issues briefly described; Linked to NCR/RFI if raised; Resolution tracked
Cl. 6 — Issue documentation
OK
NC
NA
HOLD
A7Column 7: Reviewer Name & Date - QA/Consultant reviewer and review completion date
Acceptance: Reviewer name recorded; Date of review; No blank entries
Cl. 7 — Accountability
OK
NC
NA
HOLD
A. REGISTER COLUMNS & DEFINITIONS
A1Column 1: Date - Date design received, reviewed, approved (DD-MM-YYYY format)
Cl. 1 — Date tracking (IS 456)
Sequential dates; Format consistent; No gaps
OKNCNAHOLD
A2Column 2: Design Item - What was designed (e.g., Foundation, Columns, Beams G+3, Slabs, Connections)
Cl. 2 — Design component identification (IS 456)
Item clearly described; Consistent naming; Covers all structural elements
OKNCNAHOLD
A3Column 3: Design Engineer - Name of engineer who prepared design calculations
Cl. 3 — Responsibility tracking (IS 456)
Name recorded; Title/firm noted; Contact info available if needed
OKNCNAHOLD
A4Column 4: Design Status - Status at review date (Submitted, In Review, Approved, Approved with Conditions, Rejected)
Cl. 4 — Status tracking (IS 456)
Status clearly stated; Consistent terminology; Links to approval/NCR
OKNCNAHOLD
A5Column 5: Review Checklist - Reference to QC checklist used (e.g., QC-STR-CHK-001)
Cl. 5 — QC linkage (IS 456)
Checklist ID noted; Version/revision documented; Traceability maintained
OKNCNAHOLD
A6Column 6: Issues/Comments - Design issues, discrepancies, queries raised during review (or 'None')
Cl. 6 — Issue documentation (IS 456)
Issues briefly described; Linked to NCR/RFI if raised; Resolution tracked
OKNCNAHOLD
A7Column 7: Reviewer Name & Date - QA/Consultant reviewer and review completion date
Cl. 7 — Accountability (IS 456)
Reviewer name recorded; Date of review; No blank entries
OKNCNAHOLD
Inspection Sign-Off
REGISTER COMPLETE & VERIFIED
REGISTER IN PROGRESS
REGISTER SUSPENDED — ISSUES PENDING
Total Design Items Reviewed
Name / Sign / Date
Items Approved
Name / Sign / Date
Items with Conditions
Name / Sign / Date
Items Rejected (Resubmitted)
Name / Sign / Date
Total Issues Raised
Name / Sign / Date
Issues Resolved
Name / Sign / Date
Outstanding Issues
Name / Sign / Date
Remarks
Name / Sign / Date
Register Prepared By
Name / Sign / Date
Reviewed By
Name / Sign / Date