| S.No. | Checkpoint | IS Requirement | Status |
|---|---|---|---|
| 1. SUBGRADE & EARTHWORK INSPECTION | |||
| 1.1 | Subgrade excavation complete; profile matches design ±50mm Acceptance: Profile survey at 100m intervals; visual inspection; photographic record; inspector witness required | Cl. 401 — Excavation completion | |
| 1.2 | Subgrade compaction: Density ≥95% MDD achieved at 5 locations per km Acceptance: Core/sand replacement tests; CBR ≥2%; hold point until approved; re-compaction if failed | Cl. 401 — Compaction verification | |
| 1.3 | Subgrade approval: Formal sign-off issued; layer ready for base course placement Acceptance: Completion certificate signed by QC engineer; all tests passed; conditions noted; witness point | Cl. 401 — Approval gate | |
| 2. BASE COURSE (WBM/WMM/GSB) INSPECTION | |||
| 2.1 | Base course material: Aggregate source approved; test certs (LA, impact, grading) available Acceptance: Source audit; test certificates <12 months old; witness point for first load acceptance | Cl. 401 — Material approval | |
| 2.2 | Material spreading: Layer thickness 150-200mm; uniform distribution; no segregation Acceptance: Thickness checks at 50m intervals; visual inspection; witness point for 1st 500m; photo record | Cl. 401 — Layer control | |
| 2.3 | Base course compaction: Density ≥98% SP (WBM/WMM) or ≥95% SP (GSB); 1 test per 250m² Acceptance: Core cutter tests; hold point until density approved; 95% pass rate minimum; re-compact sections <spec | Cl. 401 — Density verification | |
| 2.4 | Base course CBR: CBR ≥30% (WBM base) or ≥20% (sub-base); 1 test per 2km Acceptance: Lab CBR test; result recorded; affects bituminous layer thickness; hold point for design approval | Cl. 401 — Bearing capacity | |
| 2.5 | Base course approval: Completion certificate issued; all tests passed; ready for bituminous overlay Acceptance: Written approval from QC engineer; dated; signed; witness point for handover to paving crew | Cl. 401 — Phase approval | |
| 3. MIX DESIGN & PLANT SETUP | |||
| 3.1 | Mix design submitted: JMF, Marshall test, trial batch results, QA plan Acceptance: JMF approved by engineer; Marshall stability ≥1800 kg, flow 2-4 mm, VIM 3-5%; hold point before production | Cl. 503 — Design submission | |
| 3.2 | Batch plant calibration: Scales certified ±2%; temperature control verified; documentation available Acceptance: Scale cert current; hot bin temps recorded; plant warm-up log; witness point for plant inspection | Cl. 503 — Equipment qualification | |
| 3.3 | Bitumen approval: Grade, penetration, softening point, ductility tests passed Acceptance: Test certs reviewed; grade confirmed; hold point until approved; first truck witnessed at plant | Cl. 501 — Binder approval | |
| 3.4 | Paver & roller inspection: Equipment certified; operators trained; trial laying on test strip Acceptance: Equipment inspection checklist; maintenance records; operator certs; 100m trial strip reviewed | Cl. 503 — Equipment readiness | |