QA/QC  › Piping Systems (Plastic)  › Pressure Test Prep
Checklist · QC-PIP-CHK-003
Pressure Test Prep Checklist
23 checkpoints across 6 sections. Before commencement of hydrostatic pressure testing; day of test
23 Checkpoints
6 Sections
Once per piping system before testing
QC Engineer, Test Supervisor

Checklist Preview

S.No.CheckpointIS RequirementStatus
A. SYSTEM COMPLETION & READINESS
A1All piping joints completed and cured (Minimum 24 hrs since last joint cementing)
Acceptance: Last joint completed >24 hrs prior; temperature >15°C during curing; documented
Allow adhesive to fully set before pressure
OK
NC
NA
HOLD
A2All valves, taps, and end caps installed and verified
Acceptance: End caps and blank flanges present; valves installed correctly; no open ends
Complete system sealing
OK
NC
NA
HOLD
A3Bypass or test relief valve installed for protection
Acceptance: Relief valve set to 1.5× test pressure; test pressure <1.5× working pressure
System over-pressure protection
OK
NC
NA
HOLD
A4System alignment verified (no stress from misalignment or settlement)
Acceptance: Support structure stable; no visible stress on joints; expansion loops intact
Ensure system structural integrity
OK
NC
NA
HOLD
B. EQUIPMENT & INSTRUMENTATION
B1Pressure gauge selection and calibration
Acceptance: Range 0-1.5× test pressure; calibrated within 6 months; accuracy ±1% of range
Accurate pressure measurement
OK
NC
NA
HOLD
B2Pump selection (Manual/Electric for test pressure requirement)
Acceptance: Pump capacity adequate for test duration; manual or electric available for system size
Appropriate pressurization equipment
OK
NC
NA
HOLD
B3Pressure test hose/connection to system (proper coupling, no leaks)
Acceptance: Hose rated for test pressure; connection points checked for leakage when pressurized
Reliable test setup
OK
NC
NA
HOLD
B4Data logging / Chart recorder setup (if required for documentation)
Acceptance: Data logger or chart installed if required; calibrated; recording media ready
Record pressure over test duration
OK
NC
NA
HOLD
C. SAFETY MEASURES & PRECAUTIONS
C1Area isolation and warning signs (No personnel in pressurized area)
Acceptance: Barriers around test area; warning signs posted; area cleared of personnel
Ensure worker safety
OK
NC
NA
HOLD
C2Pressure release valve / Manual relief provision
Acceptance: Relief valve or manual valve at highest point; accessible for operation
Safe system de-pressurization
OK
NC
NA
HOLD
C3Safety briefing for personnel (Test procedure, emergency response)
Acceptance: All personnel briefed; emergency shut-off procedure understood; contact person identified
Worker awareness
OK
NC
NA
HOLD
C4Emergency stop procedure and responsible personnel identified
Acceptance: Stop valve position known; operator assigned; procedure documented
Quick response to test issues
OK
NC
NA
HOLD
Showing 12 of 23 checkpoints ·
A. SYSTEM COMPLETION & READINESS
A1All piping joints completed and cured (Minimum 24 hrs since last joint cementing)
Allow adhesive to fully set before pressure (IS 4985)
Last joint completed >24 hrs prior; temperature >15°C during curing; documented
OKNCNAHOLD
A2All valves, taps, and end caps installed and verified
Complete system sealing (IS 4985)
End caps and blank flanges present; valves installed correctly; no open ends
OKNCNAHOLD
A3Bypass or test relief valve installed for protection
System over-pressure protection (IS 4985)
Relief valve set to 1.5× test pressure; test pressure <1.5× working pressure
OKNCNAHOLD
A4System alignment verified (no stress from misalignment or settlement)
Ensure system structural integrity (IS 4985)
Support structure stable; no visible stress on joints; expansion loops intact
OKNCNAHOLD
B. EQUIPMENT & INSTRUMENTATION
B1Pressure gauge selection and calibration
Accurate pressure measurement (IS 4985)
Range 0-1.5× test pressure; calibrated within 6 months; accuracy ±1% of range
OKNCNAHOLD
B2Pump selection (Manual/Electric for test pressure requirement)
Appropriate pressurization equipment (IS 4985)
Pump capacity adequate for test duration; manual or electric available for system size
OKNCNAHOLD
B3Pressure test hose/connection to system (proper coupling, no leaks)
Reliable test setup (IS 4985)
Hose rated for test pressure; connection points checked for leakage when pressurized
OKNCNAHOLD
B4Data logging / Chart recorder setup (if required for documentation)
Record pressure over test duration (IS 4985)
Data logger or chart installed if required; calibrated; recording media ready
OKNCNAHOLD
C. SAFETY MEASURES & PRECAUTIONS
C1Area isolation and warning signs (No personnel in pressurized area)
Ensure worker safety (IS 4985)
Barriers around test area; warning signs posted; area cleared of personnel
OKNCNAHOLD
C2Pressure release valve / Manual relief provision
Safe system de-pressurization (IS 4985)
Relief valve or manual valve at highest point; accessible for operation
OKNCNAHOLD
C3Safety briefing for personnel (Test procedure, emergency response)
Worker awareness (IS 4985)
All personnel briefed; emergency shut-off procedure understood; contact person identified
OKNCNAHOLD
C4Emergency stop procedure and responsible personnel identified
Quick response to test issues (IS 4985)
Stop valve position known; operator assigned; procedure documented
OKNCNAHOLD
Showing 12 of 23 ·
Inspection Sign-Off
READY FOR TEST
NOT READY - REWORK REQUIRED
CONDITIONAL
Overall Readiness Assessment
Name / Sign / Date
Items Not Ready
Name / Sign / Date
Corrective Actions Required
Name / Sign / Date
Approval for Test Start
Name / Sign / Date
Checked By
Name / Sign / Date
Approved By (Engineer-in-Charge)
Name / Sign / Date