QA/QC  › Piping Systems (Plastic)  › Piping System ITP
Plan · QC-PIP-PLN-001
Piping System ITP
23 checkpoints across 5 sections. Before piping works commence; covers entire system from material to commissioning
23 Checkpoints
5 Sections
One ITP per piping system; updated if major scope changes
QC Engineer, Engineer-in-Charge

Checklist Preview

S.No.CheckpointIS RequirementStatus
A. INSPECTION HOLD POINTS
A1HOLD POINT 1: Material Receipt & Quality Verification
Acceptance: Pipes inspected; certificates verified; ISI mark checked; accepted/rejected
Verify material before storage/use
OK
NC
NA
HOLD
A2HOLD POINT 2: Storage & Environmental Conditions
Acceptance: Storage adequate; temp <40°C; UV protected; organized inventory
Verify material preservation
OK
NC
NA
HOLD
A3HOLD POINT 3: Joint Assembly Procedure Pilot (First 50 m)
Acceptance: First joints inspected; no leakage; procedure approved for continuation
Verify jointing quality before full-scale laying
OK
NC
NA
HOLD
A4HOLD POINT 4: Pipe Laying & Support Installation Completion
Acceptance: All pipes laid; joints assembled; supports installed; system ready for curing
Verify system is complete before curing/testing
OK
NC
NA
HOLD
A5HOLD POINT 5: Pressure Test Readiness Verification
Acceptance: Joint curing >24 hrs; equipment ready; personnel briefed; safety measures in place
Confirm system ready for testing
OK
NC
NA
HOLD
A6HOLD POINT 6: Final Acceptance & Handover
Acceptance: All tests passed; no rejections; documentation complete; ready for commissioning
Comprehensive final approval
OK
NC
NA
HOLD
B. TEST & INSPECTION SCHEDULE
B1Receiving Inspection (Visual, dimensional, certificate verification)
Acceptance: All deliveries inspected; defects <1% acceptable; certificates filed
Material quality at receipt
OK
NC
NA
HOLD
B2Daily Joint Inspection (Alignment, leakage, curing status)
Acceptance: Daily visual checks; joints inspected; defects logged and tracked
Ongoing QC during installation
OK
NC
NA
HOLD
B3Support Installation Check (Spacing, alignment, stability)
Acceptance: Bracket spacing per spec (1-2 m horizontal); level/plumb verified
Support system compliance
OK
NC
NA
HOLD
B4Hydrostatic Pressure Test (System leak detection, pressure hold)
Acceptance: Test pressure 1.5× working; hold 2+ hrs; pressure drop ≤5%; no visible leakage
System integrity verification
OK
NC
NA
HOLD
B5Ring Stiffness Test (If HDPE, verify structural rigidity)
Acceptance: If HDPE: ring stiffness ≥ spec minimum; batch tested 5-10%; results documented
Flexible pipe structural verification
OK
NC
NA
HOLD
C. ACCEPTANCE CRITERIA
C1Material Acceptance (Quality, certificates, defects <acceptable limit)
Acceptance: ISI mark present; test certificates valid; visual defects within grade limits
Material meets specification
OK
NC
NA
HOLD
C2Installation Acceptance (Joints leak-free, supports adequate, alignment correct)
Acceptance: Joints no leakage at normal conditions; spacing/alignment per spec
Installation meets standard
OK
NC
NA
HOLD
C3Pressure Test Acceptance (Pass pressure hold, minimal pressure drop)
Acceptance: Pressure drop ≤5% over 2 hrs at test pressure; no visible leaks
System integrity verified
OK
NC
NA
HOLD
C4Final System Acceptance (All checks passed, no outstanding issues)
Acceptance: All hold points cleared; documentation complete; approval given
Ready for commissioning
OK
NC
NA
HOLD
Showing 15 of 23 checkpoints ·
A. INSPECTION HOLD POINTS
A1HOLD POINT 1: Material Receipt & Quality Verification
Verify material before storage/use (IS 4985)
Pipes inspected; certificates verified; ISI mark checked; accepted/rejected
OKNCNAHOLD
A2HOLD POINT 2: Storage & Environmental Conditions
Verify material preservation (IS 4985)
Storage adequate; temp <40°C; UV protected; organized inventory
OKNCNAHOLD
A3HOLD POINT 3: Joint Assembly Procedure Pilot (First 50 m)
Verify jointing quality before full-scale laying (IS 4985)
First joints inspected; no leakage; procedure approved for continuation
OKNCNAHOLD
A4HOLD POINT 4: Pipe Laying & Support Installation Completion
Verify system is complete before curing/testing (IS 4985)
All pipes laid; joints assembled; supports installed; system ready for curing
OKNCNAHOLD
A5HOLD POINT 5: Pressure Test Readiness Verification
Confirm system ready for testing (IS 4985)
Joint curing >24 hrs; equipment ready; personnel briefed; safety measures in place
OKNCNAHOLD
A6HOLD POINT 6: Final Acceptance & Handover
Comprehensive final approval (IS 4985)
All tests passed; no rejections; documentation complete; ready for commissioning
OKNCNAHOLD
B. TEST & INSPECTION SCHEDULE
B1Receiving Inspection (Visual, dimensional, certificate verification)
Material quality at receipt (IS 4985)
All deliveries inspected; defects <1% acceptable; certificates filed
OKNCNAHOLD
B2Daily Joint Inspection (Alignment, leakage, curing status)
Ongoing QC during installation (IS 4985)
Daily visual checks; joints inspected; defects logged and tracked
OKNCNAHOLD
B3Support Installation Check (Spacing, alignment, stability)
Support system compliance (IS 4985)
Bracket spacing per spec (1-2 m horizontal); level/plumb verified
OKNCNAHOLD
B4Hydrostatic Pressure Test (System leak detection, pressure hold)
System integrity verification (IS 4985)
Test pressure 1.5× working; hold 2+ hrs; pressure drop ≤5%; no visible leakage
OKNCNAHOLD
B5Ring Stiffness Test (If HDPE, verify structural rigidity)
Flexible pipe structural verification (IS 14333)
If HDPE: ring stiffness ≥ spec minimum; batch tested 5-10%; results documented
OKNCNAHOLD
C. ACCEPTANCE CRITERIA
C1Material Acceptance (Quality, certificates, defects <acceptable limit)
Material meets specification (IS 4985)
ISI mark present; test certificates valid; visual defects within grade limits
OKNCNAHOLD
C2Installation Acceptance (Joints leak-free, supports adequate, alignment correct)
Installation meets standard (IS 4985)
Joints no leakage at normal conditions; spacing/alignment per spec
OKNCNAHOLD
C3Pressure Test Acceptance (Pass pressure hold, minimal pressure drop)
System integrity verified (IS 4985)
Pressure drop ≤5% over 2 hrs at test pressure; no visible leaks
OKNCNAHOLD
C4Final System Acceptance (All checks passed, no outstanding issues)
Ready for commissioning (IS 4985)
All hold points cleared; documentation complete; approval given
OKNCNAHOLD
Showing 15 of 23 ·
Inspection Sign-Off
APPROVED FOR EXECUTION
APPROVED WITH MODIFICATIONS
REJECTED
ITP Summary
Name / Sign / Date
Hold Points Overview
Name / Sign / Date
Key Testing Milestones
Name / Sign / Date
Contractor Representative
Name / Sign / Date
QC Engineer Name
Name / Sign / Date
Engineer-in-Charge
Name / Sign / Date