QA/QC  › Piping Systems (Plastic)  › Hydrostatic Test Report
Test-report · QC-PIP-TST-001
Hydrostatic Test Report
18 checkpoints across 5 sections. After piping system installation and joint curing; before system commissioning
18 Checkpoints
5 Sections
Once per piping system or section
Test Supervisor, QC Engineer

Checklist Preview

S.No.CheckpointIS RequirementStatus
A. TEST PROCEDURE & EXECUTION
A1Test procedure documentation (Method, duration, acceptance criteria)
Acceptance: Procedure defined; test duration ≥2 hrs minimum; pressure drop limit ≤5% per 2 hrs
Formalized testing approach
OK
NC
NA
HOLD
A2Initial pressurization to test pressure (Gradual increase, monitor for leaks)
Acceptance: Pressure increased in increments; halted if leakage detected; recorded every 5-10 psi
Controlled pressure ramp-up
OK
NC
NA
HOLD
A3Pressure stabilization at test pressure (Hold for 30 minutes before data collection)
Acceptance: System held at test pressure for 30 mins; then measurement phase starts
Allow system to stabilize thermally
OK
NC
NA
HOLD
A4Data collection interval and frequency (Readings every 15-30 minutes)
Acceptance: Pressure and time recorded at regular intervals (15-30 min); temperature noted
Monitor pressure over test duration
OK
NC
NA
HOLD
B. PRESSURE MONITORING & LEAKAGE DETECTION
B1Initial pressure reading at start of test (Time 0, Pressure 0 min)
Acceptance: Pressure reading recorded at exact test start time; gauge zero-checked
Baseline measurement
OK
NC
NA
HOLD
B2Pressure readings at regular intervals (15/30 min intervals for ≥2 hrs)
Acceptance: Readings recorded at intervals; data sheet shows time and pressure values
Track pressure change over time
OK
NC
NA
HOLD
B3Visual leakage inspection (Walk around system, look for water seepage)
Acceptance: No visible water seepage from joints; dry connections; any wetness noted with location
Identify leak locations
OK
NC
NA
HOLD
B4Pressure drop calculation (Loss in kg/cm² over test duration)
Acceptance: Pressure drop ≤5% of test pressure over 2 hrs = PASS; >5% = FAIL
Quantify system leakage
OK
NC
NA
HOLD
C. LEAK LOCATION & REMEDIATION
C1Leak detection method (Visual, soap solution, sound detection)
Acceptance: Leaking joint identified; location marked; severity documented (drip/stream)
Identify specific leak points
OK
NC
NA
HOLD
C2Leak location documentation (Marked on system drawing with photos)
Acceptance: Location marked; photo taken; details recorded on system drawing
Record leak position for repair
OK
NC
NA
HOLD
C3Repair method & re-test approval (After repair, system re-pressurized)
Acceptance: Failed joint repaired/replaced; system re-tested; result documented
Verify repair effectiveness
OK
NC
NA
HOLD
Showing 11 of 18 checkpoints ·
A. TEST PROCEDURE & EXECUTION
A1Test procedure documentation (Method, duration, acceptance criteria)
Formalized testing approach (IS 4985)
Procedure defined; test duration ≥2 hrs minimum; pressure drop limit ≤5% per 2 hrs
OKNCNAHOLD
A2Initial pressurization to test pressure (Gradual increase, monitor for leaks)
Controlled pressure ramp-up (IS 4985)
Pressure increased in increments; halted if leakage detected; recorded every 5-10 psi
OKNCNAHOLD
A3Pressure stabilization at test pressure (Hold for 30 minutes before data collection)
Allow system to stabilize thermally (IS 4985)
System held at test pressure for 30 mins; then measurement phase starts
OKNCNAHOLD
A4Data collection interval and frequency (Readings every 15-30 minutes)
Monitor pressure over test duration (IS 4985)
Pressure and time recorded at regular intervals (15-30 min); temperature noted
OKNCNAHOLD
B. PRESSURE MONITORING & LEAKAGE DETECTION
B1Initial pressure reading at start of test (Time 0, Pressure 0 min)
Baseline measurement (IS 4985)
Pressure reading recorded at exact test start time; gauge zero-checked
OKNCNAHOLD
B2Pressure readings at regular intervals (15/30 min intervals for ≥2 hrs)
Track pressure change over time (IS 4985)
Readings recorded at intervals; data sheet shows time and pressure values
OKNCNAHOLD
B3Visual leakage inspection (Walk around system, look for water seepage)
Identify leak locations (IS 4985)
No visible water seepage from joints; dry connections; any wetness noted with location
OKNCNAHOLD
B4Pressure drop calculation (Loss in kg/cm² over test duration)
Quantify system leakage (IS 4985)
Pressure drop ≤5% of test pressure over 2 hrs = PASS; >5% = FAIL
OKNCNAHOLD
C. LEAK LOCATION & REMEDIATION
C1Leak detection method (Visual, soap solution, sound detection)
Identify specific leak points (IS 4985)
Leaking joint identified; location marked; severity documented (drip/stream)
OKNCNAHOLD
C2Leak location documentation (Marked on system drawing with photos)
Record leak position for repair (IS 4985)
Location marked; photo taken; details recorded on system drawing
OKNCNAHOLD
C3Repair method & re-test approval (After repair, system re-pressurized)
Verify repair effectiveness (IS 4985)
Failed joint repaired/replaced; system re-tested; result documented
OKNCNAHOLD
Showing 11 of 18 ·
Inspection Sign-Off
PASSED
FAILED - REWORK REQUIRED
CONDITIONAL
Test Summary
Name / Sign / Date
Initial Pressure (kg/cm²)
Name / Sign / Date
Final Pressure (kg/cm²)
Name / Sign / Date
Pressure Drop (kg/cm²)
Name / Sign / Date
Pressure Drop %
Name / Sign / Date
Acceptance Limit %
Name / Sign / Date
Leakage Observed (Y/N)
Name / Sign / Date
Final Verdict
Name / Sign / Date
Remarks
Name / Sign / Date
Test Conducted By
Name / Sign / Date
Reviewed By (QC Engineer)
Name / Sign / Date