QA/QC  › HVAC & Air Conditioning  › Testing Adjusting Balancing
Test-report · QC-HVC-TST-003
Testing Adjusting Balancing (TAB) Report
10 checkpoints across 4 sections. System commissioning; final verification before operational handover
10 Checkpoints
4 Sections
Once during commissioning
HVAC Commissioning Specialist, QC Engineer

Checklist Preview

S.No.CheckpointIS RequirementStatus
A. TESTING PHASE
A1System operation verified: AHU/FCU fan starts and runs smoothly without noise or vibration issues
Acceptance: Unit powers on; fan accelerates gradually; no unusual noise; vibration levels acceptable
Cl. 4.1 — System startup
A2Supply and return air flows measured at main points; initial readings documented
Acceptance: Flows measured in m³/s; recorded in TAB report; typically 85-95% of design on first reading
Cl. 4.2 — Baseline flow measurement
A3Room temperatures measured in representative zones; thermostat control verified
Acceptance: Room temperature within ±2°C of setpoint; thermostat responds to setpoint changes; no deadband issues
Cl. 4.3 — Temperature verification
B. ADJUSTING PHASE
B1Damper adjustments made to balance zone flows; volume control dampers gradually opened/closed
Acceptance: Dampers adjusted incrementally (≤1 turn per iteration); flows measured after each adjustment; documented
Cl. 5.1 — Damper adjustment
B2Fan speed/capacity adjusted if needed to achieve overall design flow; pressure verified
Acceptance: Fan speed adjusted gradually; power input monitored; total flow approaches design value step-by-step
Cl. 5.2 — Fan adjustment
B3Thermostat calibration verified; setpoint vs. actual room temperature difference noted and corrected if > 1°C
Acceptance: Thermostat readings vs. reference thermometer verified; calibration adjustments made if needed
Cl. 5.3 — Thermostat calibration
C. BALANCING PHASE
C1All room outlet flows measured and recorded in final balance table; zone-by-zone flow documented
Acceptance: All zones: ≥90% of design flow; deviation between zones ≤±10%; final table attached to report
Cl. 6.1 — Final flow balancing
C2Supply and return air temperatures measured in all zones; temperature uniformity verified
Acceptance: Supply temperature deviation ≤±2°C across zones; no zone overheating/overcooling by > 1°C
Cl. 6.2 — Temperature balancing
C3Pressure drops across dampers and diffusers documented; system resistance verified
Acceptance: Pressure profile acceptable per design; no excessive pressure drops indicating blockages
Cl. 6.3 — System resistance verification
Showing 9 of 10 checkpoints ·
A. TESTING PHASE
A1System operation verified: AHU/FCU fan starts and runs smoothly without noise or vibration issues
Cl. 4.1 — System startup (IS 14665:2005)
Unit powers on; fan accelerates gradually; no unusual noise; vibration levels acceptable
A2Supply and return air flows measured at main points; initial readings documented
Cl. 4.2 — Baseline flow measurement (IS 3103:2017)
Flows measured in m³/s; recorded in TAB report; typically 85-95% of design on first reading
A3Room temperatures measured in representative zones; thermostat control verified
Cl. 4.3 — Temperature verification (IS 14665:2005)
Room temperature within ±2°C of setpoint; thermostat responds to setpoint changes; no deadband issues
B. ADJUSTING PHASE
B1Damper adjustments made to balance zone flows; volume control dampers gradually opened/closed
Cl. 5.1 — Damper adjustment (IS 3103:2017)
Dampers adjusted incrementally (≤1 turn per iteration); flows measured after each adjustment; documented
B2Fan speed/capacity adjusted if needed to achieve overall design flow; pressure verified
Cl. 5.2 — Fan adjustment (IS 14665:2005)
Fan speed adjusted gradually; power input monitored; total flow approaches design value step-by-step
B3Thermostat calibration verified; setpoint vs. actual room temperature difference noted and corrected if > 1°C
Cl. 5.3 — Thermostat calibration (IS 14665:2005)
Thermostat readings vs. reference thermometer verified; calibration adjustments made if needed
C. BALANCING PHASE
C1All room outlet flows measured and recorded in final balance table; zone-by-zone flow documented
Cl. 6.1 — Final flow balancing (IS 3103:2017)
All zones: ≥90% of design flow; deviation between zones ≤±10%; final table attached to report
C2Supply and return air temperatures measured in all zones; temperature uniformity verified
Cl. 6.2 — Temperature balancing (IS 14665:2005)
Supply temperature deviation ≤±2°C across zones; no zone overheating/overcooling by > 1°C
C3Pressure drops across dampers and diffusers documented; system resistance verified
Cl. 6.3 — System resistance verification (IS 3103:2017)
Pressure profile acceptable per design; no excessive pressure drops indicating blockages
Showing 9 of 10 ·
Inspection Sign-Off
COMMISSIONING COMPLETE
COMMISSIONING IN PROGRESS
COMMISSIONING FAILED
TAB Summary
Name / Sign / Date
Commissioned By
Name / Sign / Date
Verified By (QC)
Name / Sign / Date