Plan · QC-HVC-PLN-001
HVAC Installation ITP (Inspection and Test Plan)
18 checkpoints across 5 sections. At project kick-off for HVAC installation; used throughout execution phase
18 Checkpoints
5 Sections
Prepared once; updated if major scope changes
QC Engineer, Project Manager

Checklist Preview

S.No.CheckpointIS RequirementStatus
A. HOLD POINTS (Work Cannot Proceed Without QC Approval)
A1MATERIAL VERIFICATION AND TESTING EQUIPMENT CHECK
A2DUCT INSTALLATION COMPLETION AND VISUAL INSPECTION
A3DUCT LEAKAGE TEST COMPLETION
A4AHU INSTALLATION AND MOUNTING VERIFICATION
A5INSULATION INSTALLATION COMPLETION
B. WITNESS POINTS (QC to Observe and Document)
B1AHU STARTUP AND INITIAL OPERATION
B2SYSTEM FLOW MEASUREMENT AND BALANCING
B3TEMPERATURE CONTROL VERIFICATION
C. PHASE-WISE INSPECTION SCHEDULE
C1
C2
C3
C4
C5
Showing 13 of 18 checkpoints ·
A. HOLD POINTS (Work Cannot Proceed Without QC Approval)
A1MATERIAL VERIFICATION AND TESTING EQUIPMENT CHECK
()
A2DUCT INSTALLATION COMPLETION AND VISUAL INSPECTION
()
A3DUCT LEAKAGE TEST COMPLETION
()
A4AHU INSTALLATION AND MOUNTING VERIFICATION
()
A5INSULATION INSTALLATION COMPLETION
()
B. WITNESS POINTS (QC to Observe and Document)
B1AHU STARTUP AND INITIAL OPERATION
()
B2SYSTEM FLOW MEASUREMENT AND BALANCING
()
B3TEMPERATURE CONTROL VERIFICATION
()
C. PHASE-WISE INSPECTION SCHEDULE
C1
()
C2
()
C3
()
C4
()
C5
()
Showing 13 of 18 ·
Inspection Sign-Off
ITP APPROVED
ITP APPROVED WITH MODIFICATIONS
ITP Prepared By
Name / Sign / Date
Approved By (QC Manager)
Name / Sign / Date