PMC📦 Procurement & StoresReuse Log

Reuse Log

log
PMC-PRC-LOG-002·v1.0-beta·⚠ Beta — review before use

This log is used to track materials recovered from temporary works or dismantled structures for reuse in other parts of the project. It helps in controlling material costs, reducing wastage, and preparing accurate material reconciliation statements.

ReferencesCPWD Works Manual (Chapter on Stores)FIDIC Red Book 1999, Sub-clause 4.1 [Contractor's General Obligations]FIDIC Red Book 1999, Sub-clause 14.5 [Plant and Materials intended for the Works]IS 1200 (All Parts) - Basis for theoretical consumption calculations
Download
📍 When to use this template
  • When temporary structures like formwork, scaffolding, temporary site offices, or hoardings are dismantled.
  • Triggered whenever materials are salvaged from a completed activity and returned to the main store or a designated reuse yard.
  • Filled by the Contractor's Site Engineer or Stores In-charge, and must be verified by the PMC Engineer.
Sections & fields
Preview of the template structure. Download Excel to fill on site.
1Header / Project Information6 fields
Project Name
_____________
Contract Package No.
_____________
Log Reference No.
_____________
Date of Entry
_____________
Prepared By (Contractor)
_____________
Verified By (PMC)
_____________
2Material Recovery Details8 fields
Serial No.
_____________
Date of Recovery
_____________
Source Location / Structure ID (e.g., Tower A, 5th Floor Slab Formwork)
_____________
Dismantling Activity Ref. (e.g., DPR No. / Permit No.)
_____________
Recovered By (Team/Subcontractor)
_____________
Material Description
_____________
Unit of Measurement (UOM)
_____________
Total Quantity Recovered
_____________
3Condition Assessment & Segregation6 fields
Assessed By
_____________
Date of Assessment
_____________
Quantity Usable (Good Condition)
_____________
Quantity Requiring Minor Repair
_____________
Quantity Scrap / Unusable
_____________
Remarks on Condition (e.g., 'Bent flanges', 'Surface rust', 'Edges damaged')
_____________
4Storage & Inventory Update5 fields
Storage Location (e.g., Main Store Yard B, Scrap Yard)
_____________
Stack / Bin No.
_____________
Stores Ledger Folio No. / SAP Material Code
_____________
Date Entered in Stores Ledger
_____________
Store Keeper's Name & Signature
_____________
5Re-Issue for Use (If Applicable)6 fields
Re-Issue Date
_____________
Material Requisition Slip (MRS) No.
_____________
Issued To (Location / Activity)
_____________
Quantity Issued
_____________
Issuing Store Keeper's Signature
_____________
Receiver's Signature
_____________
💡 Sample filled excerpt
Date of Recovery: 15-May-2024 | Source: Tower B, 10th Floor Slab Shuttering | Material: 12mm Plywood Sheet | Qty Recovered: 50 Nos | Qty Usable: 42 Nos | Qty Scrap: 8 Nos | Stored at: Reuse Yard, Stack P-12 | Ledger Folio: PLY/12/78
⚖ Compliance notes
  • This log is critical for preparing the Material Reconciliation Statement, a contractual requirement for final bill settlement and release of retention money.
  • Provides auditable evidence of efficient material usage, justifying consumption against theoretical quantities and controlling wastage as per contract limits.
  • Supports compliance with FIDIC Sub-clause 4.1 [Contractor's General Obligations] regarding efficient management of materials.
  • For government projects, this log is essential for CPWD/PWD audits on material consumption and wastage control as per the CPWD Works Manual.