📍 When to use this template
- Whenever any material, consumable, or equipment is delivered to the site against a Purchase Order.
- Triggered upon arrival of a delivery vehicle at the site gate.
- Filled by the Site Storekeeper, and co-signed by the QC/Site Engineer after inspection.
Sections & fields
Preview of the template structure. Download Excel to fill on site.
1Header / Project Information6 fields
Project Name
_____________
Contract / Package No.
_____________
Prepared By (Storekeeper Name & Sign)
_____________
Approved By (Project Manager / Engineer Name & Sign)
_____________
2Supplier & Delivery Details8 fields
Supplier Name
_____________
Purchase Order (PO) No.
_____________
Supplier's Delivery Challan No.
_____________
Challan Date
_____________
Driver's Name & Contact
_____________
Gate Entry No. & Date/Time
_____________
3Material Receipt Details10 fields
Material Description (as per PO)
_____________
Make / Brand
_____________
Unit of Measurement (UoM)
_____________
Quantity as per PO
_____________
Quantity as per Challan
_____________
Quantity Received (Actual)
_____________
Quantity Accepted
_____________
Quantity Rejected
_____________
Remarks (e.g., Short/Excess Supply, Damage)
_____________
4Inspection & Quality Check7 fields
Inspected By (QC Engineer)
_____________
Inspection Date
_____________
Material Inspection Report (MIR) No.
_____________
Test Certificate / MTC Received (Yes/No/NA)
_____________
Calibration Certificate Received (Yes/No/NA)
_____________
Visual Inspection Status (OK / Damaged / Not OK)
_____________
Quality Remarks
_____________
5Stores & Accounts Information5 fields
Received By (Storekeeper Signature)
_____________
Ledger Folio No. / Bin Card No.
_____________
Storage Location / Stack No.
_____________
Billable / Non-Billable Item
_____________
Date Forwarded to Accounts Dept.
_____________
💡 Sample filled excerpt
Sr. No: 1 | Material: TMT Steel Fe-500D, 12mm dia | Make: JSW Neosteel | UoM: MT | Qty Received: 10.25 | Qty Accepted: 10.25 | Remarks: MTC received. Bundle count verified.
⚖ Compliance notes
- Primary document for verifying supplier invoices for payment processing under FIDIC Sub-clause 14 or similar contract terms.
- Essential for material reconciliation statements (e.g., for cement, steel) as required by CPWD contracts and for client audits.
- Forms the basis for updating the Stores Ledger and Bin Cards, a key requirement under CPWD Manual Vol II, Chapter 16 (Stores).
- Supports quality control compliance under FIDIC Sub-clause 7 (Plant, Materials and Workmanship) by documenting receipt and initial inspection.