PMC🚧 Mobilization & Project KickoffSite Mobilization Checklist

Site Mobilization Checklist

checklist
PMC-MOB-CHK-001·v1.0-beta·⚠ Beta — review before use

This is a master checklist to ensure all essential activities are completed before starting major construction work. It covers everything from getting statutory approvals and setting up the site office to deploying machinery and manpower as per the contract.

ReferencesBOCW Act, 1996BOCW (Central) Rules, 1998FIDIC Red Book (2017) Sub-Clause 8.1CPWD Works Manual, Chapter 16: Commencement of WorkContract Labour (Regulation and Abolition) Act, 1970
Download
📍 When to use this template
  • At the very beginning of a project, after the Letter of Award (LOA) is issued and before any major site work begins.
  • Triggered by the 'Notice to Proceed' or as per the contract's defined mobilization period (e.g., 15-30 days).
  • Typically filled by the Contractor's Project Manager, then jointly verified by the PMC/Client's Site Engineer.
Sections & fields
Preview of the template structure. Download Excel to fill on site.
1Header / Project Information7 fields
Project Name
_____________
Contract / Package No.
_____________
Document Number
_____________
Date of Checklist
_____________
Prepared By (Contractor)
_____________
Verified By (PMC)
_____________
Approved By (Client)
_____________
2Contractual & Statutory Compliance9 fields
Letter of Award (LOA) Received
_____________
Contract Agreement Signed
_____________
Performance Bank Guarantee (PBG) Submitted
_____________
Mobilization Advance Bank Guarantee (MABG) Submitted
_____________
BOCW Registration Certificate Application
_____________
Contract Labour License Application
_____________
EPF & ESIC Registration Codes
_____________
Pollution Control Board (PCB) Consent to Establish (CTE)
_____________
Insurance Policies (CAR, Workmen's Compensation) Submitted
_____________
3Site Establishment & Infrastructure12 fields
Site Office Setup (Porta Cabin/Building)
_____________
Labour Camp Establishment (as per BOCW norms)
_____________
Material Storage Yard / Stacking Area
_____________
Cement Godown (Raised & Waterproof)
_____________
Reinforcement Steel Yard
_____________
Site Barricading / Fencing & Gate
_____________
Project Signboard Installation (as per spec)
_____________
Temporary Power Connection (Load Sanctioned)
_____________
Temporary Water Source (Borewell/Tanker)
_____________
Site Toilets / Sanitation Facilities
_____________
First Aid Station / Ambulance Provision
_____________
Site Laboratory Setup (if applicable)
_____________
4Plant & Machinery (P&M) Mobilization7 fields
P&M Mobilization Plan Submitted
_____________
Major Equipment Deployed (e.g., Batching Plant, Tower Crane, Excavator)
_____________
Equipment Fitness Certificates / TPI Reports
_____________
Operator Licenses & Competency Certificates
_____________
Fuel Storage Area (Diesel Tank with Dyke wall)
_____________
P&M Logbooks & Maintenance Schedule
_____________
Calibration Certificates for Batching Plant & Lab Equipment
_____________
5Manpower Deployment7 fields
Key Personnel CVs Submitted & Approved (PM, QA/QC, Safety)
_____________
Organization Chart Submitted & Approved
_____________
Site Staff Induction & Training Conducted
_____________
Skilled & Unskilled Labour Mobilization
_____________
Gate Pass / ID Card System Implemented
_____________
Labour Attendance System (Biometric/Register)
_____________
Labour Welfare Officer Appointed (if applicable)
_____________
6Health, Safety & Environment (HSE)8 fields
Project Specific HSE Plan Submitted & Approved
_____________
Emergency Response Plan (ERP) & Contact List Displayed
_____________
Fire Extinguishers & Sand Buckets Installed
_____________
Personal Protective Equipment (PPE) Stock & Issue Register
_____________
HSE Induction for all personnel
_____________
Toolbox Talk Schedule Prepared
_____________
Waste Management Plan & Designated Bins
_____________
Emergency Assembly Point Demarcated
_____________
7Initial Surveys & Documentation7 fields
Initial Site Survey & Demarcation Report
_____________
Joint Level Survey with Client/PMC
_____________
Geotechnical Investigation Report Acknowledged
_____________
List of 'Good for Construction' (GFC) Drawings Received
_____________
Quality Assurance Plan (QAP) / ITP Submitted
_____________
Project Baseline Schedule (L1/L2) Submitted
_____________
Material Source Approval Requests Submitted
_____________
💡 Sample filled excerpt
Section: Site Establishment & Infrastructure | Field: Labour Camp Establishment | Status: In Progress | Remarks: Foundation work for 4 barracks completed. Water and sanitation lines being laid. Target completion: 25-May-2024. Joint inspection with Labour Officer scheduled. | Verified By: R. Singh (PMC) | Date: 18-May-2024
⚖ Compliance notes
  • Fulfills mobilization requirements as per FIDIC Conditions of Contract (e.g., Sub-Clause 8.1 Commencement of Works).
  • Essential for compliance with the Building and Other Construction Workers (BOCW) Act, 1996, for site registration (Section 7) and worker facilities (Rules 238-241).
  • Submission of PBG, MABG, and Insurance is a contractual prerequisite for payments, as per CPWD General Conditions of Contract and most private agreements.
  • Establishes a formal record for defining the 'Commencement Date' or 'Appointed Day' as per the contract agreement.