Statutory Authority Coordination MoM

mom
PMC-MTG-MOM-011·v1.0-beta·⚠ Beta — review before use

Records coordination meetings with statutory authorities — Local Body, Municipal Corp, Pollution Control Board, Forest Dept, Labour Dept, Power Discom, etc. Critical for clearance + compliance tracking.

ReferencesFIDIC Sub-clause 1.13 (Compliance with Laws)Project-specific Statutory Clearance ListLocal Building + Town Planning Bye-laws
Download
📍 When to use this template
  • Pre-construction with authority (clearance + NOC).
  • During construction (inspections, monitoring).
  • Post-construction (occupancy + commissioning permits).
  • Issue resolution + dispute meetings.
Sections & fields
Preview of the template structure. Download Excel to fill on site.
1Meeting Details5 fields
Authority + Department
_____________
Officer-in-Charge
_____________
Project Representatives
_____________
Date + Venue
_____________
Purpose of Meeting
_____________
2Discussion Items5 fields
Item Description
_____________
Authority's Position / Requirement
_____________
Project Team's Response
_____________
Decision / Direction
_____________
Documentation Required
_____________
3Action Items5 fields
Action Required
_____________
Owner (Authority / Project)
_____________
Target Date
_____________
Required Documents
_____________
Statutory Reference
_____________
4Subsequent Steps4 fields
Next Submission Date
_____________
Next Meeting (if any)
_____________
Escalation Path (if dispute)
_____________
Cost Implications (Fees / Levies / Penalty)
_____________
💡 Sample filled excerpt
Meeting with Municipal Building Department, 14-May-2026. Issue: occupancy certificate held pending parking compliance. Resolution: revise parking layout per current bylaw + resubmit by 30-May. Action: Architect to revise within 7 days; resubmission with revised drawings.
⚖ Compliance notes
  • Per FIDIC Sub-clause 1.13, statutory compliance is contractor's obligation (within scope).
  • Authority directions in writing (even via MoM) are binding — implement promptly.
  • Disputes with authority should be escalated to legal / contract management per project procedure.
  • Bribes / facilitation payments PROHIBITED under contract + anti-corruption laws — escalate any such request.