PMC📐 Design CoordinationClient Review Register

Client Review Register

register
PMC-DSN-REG-001·v1.0-beta·⚠ Beta — review before use

This register tracks all documents, drawings, and samples submitted to the client or their representative for review and approval. It's our master list to ensure we get timely responses and have a clear record of the entire approval cycle.

ReferencesFIDIC (1999/2017) Sub-clause 1.9FIDIC (1999/2017) Sub-clause 5.2CPWD Manual Vol II, Chapter 21ISO 9001:2015 Clause 7.5
Download
📍 When to use this template
  • Whenever a drawing, document, material sample, or method statement is formally submitted to the Client/Engineer for review.
  • Updated continuously as submissions are made and responses are received; reviewed weekly in project meetings.
  • Maintained by the PMC's Document Controller or the concerned discipline engineer (Civil, MEP, etc.).
Sections & fields
Preview of the template structure. Download Excel to fill on site.
1Header / Project Information6 fields
Project Name
_____________
Contract / Package No.
_____________
Register Title
_____________
Document No.
_____________
Revision No.
_____________
Date of Issue
_____________
2Submission Details9 fields
Sl. No.
_____________
Submission Ref. No.
_____________
Date of Submission
_____________
Submitted By (PMC/Contractor)
_____________
Document/Drawing Title
_____________
Document/Drawing No.
_____________
Revision No.
_____________
Type of Submission (e.g., Drawing, Method Statement, Material, RFI)
_____________
No. of Copies Submitted
_____________
3Client / Engineer Review Details6 fields
Date of Receipt by Client/Engineer
_____________
Date of Response from Client/Engineer
_____________
Response Ref. No.
_____________
Review Status (Code A/B/C/D, Approved, Approved with Comments, Revise & Resubmit, Rejected)
_____________
Reviewer's Name/Designation
_____________
Key Comments / Remarks
_____________
4Action & Closure6 fields
Action Required By (Discipline/Person)
_____________
Target Date for Action
_____________
Date of Resubmission (if any)
_____________
Resubmission Ref. No.
_____________
Final Closure Date
_____________
Remarks / Link to NCR/SI
_____________
5Timeline & SLA Tracking4 fields
Contractual Review Period (Days)
_____________
Actual Review Period Taken (Days)
_____________
Delay (if any, in Days)
_____________
Reason for Delay (if known)
_____________
💡 Sample filled excerpt
Sl. No: 12 | Submission Ref: ABC/TR/DWG/ARCH/023-R1 | Date: 15-Jun-2023 | Doc Title: First Floor Reflected Ceiling Plan | Review Status: Code B - Approved with Comments | Key Comments: 'Verify AHU locations with MEP drawings. Resubmit for records after incorporating.' | Action By: Architect
⚖ Compliance notes
  • Enforces contractual timelines for review, often specified in FIDIC Sub-clause 1.9 (Delayed Drawings or Instructions).
  • Provides a clear audit trail for claims related to delays caused by late approvals (EOT claims under FIDIC Sub-clause 8.5).
  • Acts as primary evidence during project review meetings (PRM) and for dispute resolution regarding design/document approval status.
  • Supports compliance with quality management systems like ISO 9001, which require control of documents and records.