Formwork / Shuttering

Stripping time: slab 7d, beam soffit 14d, column 16-24h

Also calledformworkshutteringcenteringform removalstripping
Related on InfraLens
Definition

Formwork is the temporary mould or structure that supports concrete during placement and hardening, until the concrete is structurally adequate to support itself. Indian Standards: IS 14687:1999 (formwork specification), IS 4014:1967 (steel formwork), IS 11827:1989 (timber formwork), IS 16172 (mechanical splices). Formwork is a major construction cost element — typically 15-25% of total RCC project cost. Reusability and turnaround time directly impact project economics.

Formwork materials: (1) Timber — traditional, flexible, suitable for irregular shapes; reusable 5-10 times. (2) Plywood — common for slabs and walls; 6-mm Marine grade BWP; reusable 8-15 times. (3) Steel — reusable 50-100 times; high initial cost; common for repetitive elements (columns, walls, flat slabs). (4) Aluminium — lightweight, faster to handle; 50-200 cycles; popular for high-rise construction (Mivan system from Pune developer Eazi Mivan). (5) Plastic — emerging system; 100+ cycles; specialty applications. The selection depends on project size, repetition, schedule, and budget.

Design considerations: (a) Loads — fresh concrete pressure, equipment, workers, plus impact during pour; (b) Stiffness — formwork must not deflect more than 1/270 of span under load; (c) Stripping time — IS 456 Cl. 11 specifies minimum strip times: 16-24 hours for column sides (vertical only); 7 days for beam soffits; 14 days for slab soffits; longer for cantilevers. (d) Surface finish — formwork surface determines concrete surface; smooth shutter → smooth concrete; rough shutter → rough concrete. (e) Reuse — proper cleaning and oiling between uses extends life. Common Indian formwork issues: (a) inadequate bracing causing deflection during pour; (b) early stripping causing concrete cracking or crushing; (c) leaking joints causing slurry loss and honeycombing; (d) inadequate alignment causing dimensional defects. Pre-pour formwork inspection (verticality, alignment, bracing, surface condition) is mandatory.

Typical values
Timber formwork — reusability5-10 cycles
Plywood (Marine BWP)8-15 cycles
Steel formwork50-100 cycles
Aluminium (Mivan)50-200 cycles
Cost — timber (per m² wall)₹150-250
Cost — steel (per m²)₹300-500
Cost — aluminium₹400-700
Where used
  • All cast-in-situ RCC construction — slabs, beams, columns, footings, walls
  • Mass concrete formwork — dams, bridges, large rafts
  • Pre-cast moulds — sleepers, beams, panels
  • Tunneling and infrastructure formwork
  • Architectural concrete — exposed concrete with specific surface finish
Acceptance / threshold
Per IS 14687 + IS 456 Cl. 11: design for fresh concrete pressure + equipment + impact; deflection ≤ 1/270 of span; stripping time per Cl. 11 (column sides 24 h, beam soffits 7 days, slab soffits 14 days, cantilevers 21+ days); pre-pour inspection of bracing and alignment.
Site example
Site reality: a Bengaluru project stripped column-side formwork at 8 hours instead of the IS 456 minimum 16-24 hours. The columns showed surface laitance and minor honeycombing in 30% of locations. Repair: surface grouting + cosmetic patching. ₹3.2 lakh additional cost. Always strip formwork at the IS 456 minimum or longer; early stripping causes predictable defects.
Frequently asked
What is the minimum stripping time for formwork?
Per IS 456 Cl. 11: column sides — 16-24 hours (vertical only, no soffits); beam soffits — 7 days; slab soffits — 14 days (one-way), 21 days (two-way); cantilever soffits — 21 days minimum (often more for long cantilevers). For PCC and non-reinforced concrete: faster stripping. Cold weather may extend times. Always confirm with cube test of curing samples — minimum 70% of design strength before stripping load-carrying soffits.
What is Mivan formwork?
Mivan is an aluminium formwork system originally developed in Spain, popular in India for high-rise construction. The system uses interlocking aluminium panels for walls, columns, and slabs; assembled and removed quickly (1-2 days vs 7-15 days for conventional). Reusability 200+ cycles. Used for typical apartment buildings, where wall and floor configuration repeats per floor. Major Indian Mivan suppliers: Eazi Mivan, Goldenwall, Aluma. Faster construction reduces project schedule by 30-50%.
What is the cost of formwork?
Cost varies by material and project scale: timber (₹150-250/m² wall), plywood (₹250-350/m²), steel (₹300-500/m²), aluminium Mivan (₹400-700/m²). For high-rise repetitive construction, aluminium gives lowest per-cycle cost despite higher initial investment. Indian project budget allocation: typical 15-25% of total RCC cost on formwork.