Sprinkler System Test Report
15 checkpoints across 6 sections. Post-installation commissioning and annual maintenance testing of sprinkler systems
15 Checkpoints
6 Sections
Post-construction; annual maintenance
QC Engineer, Fire Safety Consultant

Checklist Preview

S.No.CheckpointIS RequirementStatus
A. STATIC PRESSURE AND SUPPLY VERIFICATION
A1Static pressure at main inlet measured (no flow condition)
Acceptance: Pressure ≥ 2.8 bar; measured with calibrated gauge; temperature recorded; reading stable after 30 seconds
Cl. 4.1 — Supply pressure baseline
OK
NC
NA
HOLD
A2Water supply volume adequate for design demand (tank level / source capacity verified)
Acceptance: Tank volume ≥ design specification; no risk of depletion during test duration
Cl. 4.2 — Supply capacity
OK
NC
NA
HOLD
B. PRESSURE TEST (HYDRAULIC INTEGRITY)
B1System pressure test conducted at 1.5 × maximum working pressure for 1 hour minimum
Acceptance: Test pressure ≥ 4.2 bar (1.5 × 2.8); sustained 1 hour; pressure drop < 0.2 bar during test; test record signed
Cl. 5.1 — Integrity pressure test
OK
NC
NA
HOLD
B2Visual inspection during pressure test: no visible water leaks at joints, seals, or fittings
Acceptance: No leaks observed; dry cloth placed at suspicious joints shows no moisture; minor seepage < 10 drops/minute acceptable
Cl. 5.2 — Leak detection
OK
NC
NA
HOLD
B3Gauge accuracy verified (before and after test); calibration certificate dated within 12 months
Acceptance: Gauge calibration certificate attached; deviation noted if any; secondary gauge comparison performed (± 0.1 bar tolerance)
Cl. 5.3 — Test equipment calibration
OK
NC
NA
HOLD
C. FLOW TEST AND DISCHARGE VERIFICATION
C1Flow rate measured at remote test point (farthest hydrant/outlet) with outlet pressure ≥ 2.8 bar
Acceptance: Flow measured with calibrated meter; ≥ design specification (typically 10-15 l/min); pressure at outlet ≥ 2.8 bar recorded
Cl. 6.1 — Remote outlet flow
OK
NC
NA
HOLD
C2Flow rate at main supply during design flow test (all zones operating or representative load)
Acceptance: Total flow ≥ design demand (flow density × protected area); duration ≥ 15 minutes; flow stable and measurable
Cl. 6.2 — Main line flow
OK
NC
NA
HOLD
C3Pressure drop along system calculated (from inlet to remote outlet)
Acceptance: Pressure drop measured; compared against design calculations; acceptable if within ±10% of design prediction
Cl. 6.3 — Friction loss assessment
OK
NC
NA
HOLD
C4Sprinkler head discharge pattern observed during flow test (visual inspection of spray from sample heads)
Acceptance: Discharge pattern conical/uniform; no clogging evident; no deflections; multiple heads tested to confirm spray quality
Cl. 6.4 — Sprinkler discharge
OK
NC
NA
HOLD
Showing 9 of 15 checkpoints ·
A. STATIC PRESSURE AND SUPPLY VERIFICATION
A1Static pressure at main inlet measured (no flow condition)
Cl. 4.1 — Supply pressure baseline (IS 15105:2015)
Pressure ≥ 2.8 bar; measured with calibrated gauge; temperature recorded; reading stable after 30 seconds
OKNCNAHOLD
A2Water supply volume adequate for design demand (tank level / source capacity verified)
Cl. 4.2 — Supply capacity (IS 15105:2015)
Tank volume ≥ design specification; no risk of depletion during test duration
OKNCNAHOLD
B. PRESSURE TEST (HYDRAULIC INTEGRITY)
B1System pressure test conducted at 1.5 × maximum working pressure for 1 hour minimum
Cl. 5.1 — Integrity pressure test (IS 15105:2015)
Test pressure ≥ 4.2 bar (1.5 × 2.8); sustained 1 hour; pressure drop < 0.2 bar during test; test record signed
OKNCNAHOLD
B2Visual inspection during pressure test: no visible water leaks at joints, seals, or fittings
Cl. 5.2 — Leak detection (IS 15105:2015)
No leaks observed; dry cloth placed at suspicious joints shows no moisture; minor seepage < 10 drops/minute acceptable
OKNCNAHOLD
B3Gauge accuracy verified (before and after test); calibration certificate dated within 12 months
Cl. 5.3 — Test equipment calibration (IS 15105:2015)
Gauge calibration certificate attached; deviation noted if any; secondary gauge comparison performed (± 0.1 bar tolerance)
OKNCNAHOLD
C. FLOW TEST AND DISCHARGE VERIFICATION
C1Flow rate measured at remote test point (farthest hydrant/outlet) with outlet pressure ≥ 2.8 bar
Cl. 6.1 — Remote outlet flow (IS 15105:2015)
Flow measured with calibrated meter; ≥ design specification (typically 10-15 l/min); pressure at outlet ≥ 2.8 bar recorded
OKNCNAHOLD
C2Flow rate at main supply during design flow test (all zones operating or representative load)
Cl. 6.2 — Main line flow (IS 15105:2015)
Total flow ≥ design demand (flow density × protected area); duration ≥ 15 minutes; flow stable and measurable
OKNCNAHOLD
C3Pressure drop along system calculated (from inlet to remote outlet)
Cl. 6.3 — Friction loss assessment (IS 15105:2015)
Pressure drop measured; compared against design calculations; acceptable if within ±10% of design prediction
OKNCNAHOLD
C4Sprinkler head discharge pattern observed during flow test (visual inspection of spray from sample heads)
Cl. 6.4 — Sprinkler discharge (IS 15105:2015)
Discharge pattern conical/uniform; no clogging evident; no deflections; multiple heads tested to confirm spray quality
OKNCNAHOLD
Showing 9 of 15 ·
Inspection Sign-Off
PASS
FAIL
PASS WITH REMEDIATION
Test Summary
Name / Sign / Date
Any Deviations / Remediation
Name / Sign / Date
Tested By
Name / Sign / Date
Reviewed By
Name / Sign / Date