QA/QC  › Fire Safety & Fighting  › Fire Safety Installation
Plan · QC-FIR-PLN-001
Fire Safety Installation ITP (Inspection and Test Plan)
25 checkpoints across 6 sections. Prepared at project kick-off for fire safety systems; used throughout installation phase to guide QC inspections and test activities
25 Checkpoints
6 Sections
Prepared once at start; updated only if major scope changes occur
QC Engineer, QC Manager

Checklist Preview

S.No.CheckpointIS RequirementStatus
A. HOLD POINTS (Work Cannot Proceed Without QC Approval)
A1PRE-INSTALLATION SITE INSPECTION
A2MATERIAL AND EQUIPMENT VERIFICATION
A3PIPE INSTALLATION COMPLETION AND VISUAL INSPECTION
A4SYSTEM FLUSHING COMPLETION (Hydrant/Sprinkler)
A5FIRE DOOR AND FRAME INSTALLATION INSPECTION
A6SPRINKLER HEAD INSTALLATION VERIFICATION
A7FIRE ALARM DETECTOR INSTALLATION AND ADDRESSING (Addressable Systems)
A8PENETRATION SEALING AND FIRE STOPS INSTALLATION
B. WITNESS POINTS (QC to Observe and Document)
B1HYDROSTATIC PRESSURE TEST
B2SYSTEM FLOW TEST AND PRESSURE MEASUREMENT AT REMOTE OUTLETS
B3SMOKE DETECTOR RESPONSE TEST (Sample Detectors)
B4ALARM DEVICE FUNCTIONALITY TEST
B5FIRE DOOR OPERATION AND CLOSING TEST
C. INSPECTION SCHEDULE AND PHASE-WISE ACTIVITIES
C1
C2
C3
C4
Showing 17 of 25 checkpoints ·
A. HOLD POINTS (Work Cannot Proceed Without QC Approval)
A1PRE-INSTALLATION SITE INSPECTION
()
A2MATERIAL AND EQUIPMENT VERIFICATION
()
A3PIPE INSTALLATION COMPLETION AND VISUAL INSPECTION
()
A4SYSTEM FLUSHING COMPLETION (Hydrant/Sprinkler)
()
A5FIRE DOOR AND FRAME INSTALLATION INSPECTION
()
A6SPRINKLER HEAD INSTALLATION VERIFICATION
()
A7FIRE ALARM DETECTOR INSTALLATION AND ADDRESSING (Addressable Systems)
()
A8PENETRATION SEALING AND FIRE STOPS INSTALLATION
()
B. WITNESS POINTS (QC to Observe and Document)
B1HYDROSTATIC PRESSURE TEST
()
B2SYSTEM FLOW TEST AND PRESSURE MEASUREMENT AT REMOTE OUTLETS
()
B3SMOKE DETECTOR RESPONSE TEST (Sample Detectors)
()
B4ALARM DEVICE FUNCTIONALITY TEST
()
B5FIRE DOOR OPERATION AND CLOSING TEST
()
C. INSPECTION SCHEDULE AND PHASE-WISE ACTIVITIES
C1
()
C2
()
C3
()
C4
()
Showing 17 of 25 ·
Inspection Sign-Off
ITP APPROVED
ITP APPROVED WITH MODIFICATIONS
ITP UNDER REVIEW
ITP Prepared By
Name / Sign / Date
Approved By (QC Manager)
Name / Sign / Date
Contractor Acknowledgment
Name / Sign / Date