QA/QC  › Drainage & Sewerage  › Sewer Pipe Laying
Form · QC-DRN-FRM-001
Sewer Pipe Laying Method Statement
5 checkpoints across 2 sections. Before sewer pipe laying
5 Checkpoints
2 Sections
Per phase
Site Engineer

Checklist Preview

S.No.CheckpointIS RequirementStatus
A. INSTALLATION PROCEDURE
A1Step 1: Trench excavated to design depth with sand cushion (100mm) placed
Acceptance: Trench ready, sand layer in place
Cl. 5 — Preparation
A2Step 2: Pipes laid on sand, joints made with mortar, benching in manholes
Acceptance: Pipes installed, joints completed, invert level correct
Cl. 6 — Laying
A3Step 3: Support layer (150mm sand) placed over pipes; backfill soil added in 200mm lifts
Acceptance: Support and backfill completed, compacted
Cl. 7 — Backfilling
A4Step 4: Water test (30 minutes hold) and smoke test performed; defects repaired
Acceptance: Tests passed, zero leakage, ready for service
Cl. 10-11 — Testing
B. SAFETY MEASURES
B1Work site secured, trench properly shored for depth >1.5m, PPE provided to workers
Acceptance: All safety measures in place, no incidents
Cl. 12 — Safety
A. INSTALLATION PROCEDURE
A1Step 1: Trench excavated to design depth with sand cushion (100mm) placed
Cl. 5 — Preparation (IS 4127)
Trench ready, sand layer in place
A2Step 2: Pipes laid on sand, joints made with mortar, benching in manholes
Cl. 6 — Laying (IS 4127)
Pipes installed, joints completed, invert level correct
A3Step 3: Support layer (150mm sand) placed over pipes; backfill soil added in 200mm lifts
Cl. 7 — Backfilling (IS 4127)
Support and backfill completed, compacted
A4Step 4: Water test (30 minutes hold) and smoke test performed; defects repaired
Cl. 10-11 — Testing (IS 4127)
Tests passed, zero leakage, ready for service
B. SAFETY MEASURES
B1Work site secured, trench properly shored for depth >1.5m, PPE provided to workers
Cl. 12 — Safety (IS 4127)
All safety measures in place, no incidents
Inspection Sign-Off
APPROVED
APPROVED WITH MODS
REJECTED
Approved By
Name / Sign / Date