QA/QC  › Drainage & Sewerage  › Drainage Works ITP
Plan · QC-DRN-PLN-001
Drainage Works ITP
7 checkpoints across 4 sections. Project start; guides drainage works activities
7 Checkpoints
4 Sections
One per project
QC Engineer, Site Engineer

Checklist Preview

S.No.CheckpointIS RequirementStatus
PHASE_1. Phase 1: Trench Preparation
1.1Trench excavation verification; depth and width per design, sand cushion prepared
Acceptance: Trench dimensions verified, sand layer in place, ready for pipe
Trench readiness
1.2WITNESS POINT: QC verifies trench condition before pipe laying authorization
Acceptance: QC sign-off obtained, documented
QC approval to proceed
PHASE_2. Phase 2: Drainage Pipe Laying
2.1Pipes laid per design, joints made with mortar, gradient verified at intervals
Acceptance: Pipe laying completed, gradient confirmed, as-laid drawing prepared
Pipe installation
PHASE_3. Phase 3: Manhole Construction
3.1Manhole pits excavated, linings constructed, benching done, step irons fitted
Acceptance: All MH constructed, watertight, accessible
Manhole construction
Showing 4 of 7 checkpoints ·
PHASE_1. Phase 1: Trench Preparation
1.1Trench excavation verification; depth and width per design, sand cushion prepared
Trench readiness (IS 4127)
Trench dimensions verified, sand layer in place, ready for pipe
1.2WITNESS POINT: QC verifies trench condition before pipe laying authorization
QC approval to proceed (IS 4127)
QC sign-off obtained, documented
PHASE_2. Phase 2: Drainage Pipe Laying
2.1Pipes laid per design, joints made with mortar, gradient verified at intervals
Pipe installation (IS 4127)
Pipe laying completed, gradient confirmed, as-laid drawing prepared
PHASE_3. Phase 3: Manhole Construction
3.1Manhole pits excavated, linings constructed, benching done, step irons fitted
Manhole construction (IS 4127)
All MH constructed, watertight, accessible
Showing 4 of 7 ·
Inspection Sign-Off
ITP APPROVED
ITP APPROVED WITH MODS
ITP REJECTED
Prepared By
Name / Sign / Date
Reviewed By (QC)
Name / Sign / Date