PMC🦺 Safety & PermitsRadiography Permit

Radiography Permit

permit
PMC-SAF-PMT-007·v1.0-beta·⚠ Beta — review before use

This is a permit-to-work for conducting Radiography Testing (RT) on site. It ensures all safety precautions are taken before, during, and after using radioactive sources, as per AERB guidelines and site safety rules.

ReferencesAtomic Energy (Radiation Protection) Rules, 2004AERB Safety Code (AERB/SC/INDT)BOCW Rules, 1998 (Rule 47)IS 15048: Safe use of radioactive sources in industrial radiography
Download
📍 When to use this template
  • Before starting any Non-Destructive Testing (NDT) involving X-ray or Gamma-ray sources.
  • A new permit is required for each shift or each new location of radiography work.
  • Filled by the NDT agency's Site-in-Charge/Radiographer and approved by the PMC/Client Safety Officer.
Sections & fields
Preview of the template structure. Download Excel to fill on site.
1Header / Project Information9 fields
Project Name
_____________
Contract / Package No.
_____________
Permit No.
_____________
Date of Request
_____________
Permit Validity (From Date/Time)
_____________
Permit Validity (To Date/Time)
_____________
Location / Grid / Chainage
_____________
Prepared By (NDT Agency)
_____________
Approved By (PMC/Client Safety)
_____________
2Radiography Agency & Personnel Details7 fields
NDT Agency Name
_____________
Radiographer Name & ID
_____________
BARC RSO Level (I/II/III)
_____________
BARC Certificate No. & Validity
_____________
Assistant Radiographer Name & ID
_____________
TLD Badge Nos. (All personnel)
_____________
Medical Fitness Certificate Validity
_____________
3Radiation Source & Equipment Details8 fields
Source Type (e.g., Iridium-192, Cobalt-60, X-Ray)
_____________
Source Serial Number
_____________
Source Activity (in Curies/Bq)
_____________
AERB License No. & Validity
_____________
Survey Meter Make & Model
_____________
Survey Meter Serial No.
_____________
Survey Meter Calibration Due Date
_____________
Emergency Kit Availability (Lead shots, tongs, etc.)
_____________
4Pre-Work Safety Checklist10 fields
Area Barricaded & Caution Signs Posted?
_____________
Cordon-off Distance Calculated & Maintained?
_____________
All Unauthorised Personnel Evacuated?
_____________
Communication System Established (Walkie-talkie)?
_____________
Emergency Contact Numbers Displayed?
_____________
Wind Direction Checked (if applicable)?
_____________
Night Work Lighting Adequate?
_____________
First Aid Kit Available?
_____________
RSO & Radiographer Briefed the Team (TBT)?
_____________
Physical check of emergency source container done?
_____________
5Post-Work Checks & Clearance8 fields
Source Secured in Camera/Container?
_____________
Survey Meter Reading at Source Container Surface (mR/hr)
_____________
Survey Meter Reading at Barricade Perimeter (mR/hr)
_____________
Barricades & Signs Removed?
_____________
Area Declared Safe for Re-entry?
_____________
Time of Work Completion
_____________
Signature of Radiographer (Post-Work)
_____________
Signature of PMC Safety (Post-Work)
_____________
💡 Sample filled excerpt
Location: Pipe Rack, Grid A-B/1-2. Source: Iridium-192, Activity: 35 Ci. Cordon-off Distance: 25 meters. Survey Meter Reading (Post-Work at Container): 1.5 mR/hr. Area declared safe at 04:30 AM.
⚖ Compliance notes
  • Fulfills requirements under the Atomic Energy (Radiation Protection) Rules, 2004, governed by AERB.
  • Helps comply with BOCW (Building and Other Construction Workers) Rules, 1998, Rule 47 (Use of dangerous and harmful substances).
  • Essential documentation for safety audits and to demonstrate due diligence in case of a radiation-related incident.
  • Mandatory for any work involving ionizing radiation on construction sites, especially for pressure vessels, piping, and critical structural welds.