PMC🦺 Safety & PermitsExcavation Permit

Excavation Permit

permit
PMC-SAF-PMT-005·v1.0-beta·⚠ Beta — review before use

This is a mandatory safety permit required before starting any digging or excavation work. It ensures all safety checks are done, like checking for underground cables or pipes, and making sure the sides of the pit won't collapse.

ReferencesBOCW Act, 1996BOCW (Central) Rules, 1998 - Rule 47 (Excavation and Tunnelling)IS 3764: Safety Code for Excavation WorkCPWD Safety Code
Download
📍 When to use this template
  • Before any manual or mechanical excavation begins, regardless of depth.
  • A new permit is required for each distinct excavation location or if work stops for more than 24 hours.
  • Filled by the Contractor's Site Engineer/Supervisor, checked by the PMC/Client Safety Officer, and approved by the Project Manager.
Sections & fields
Preview of the template structure. Download Excel to fill on site.
1Header / Project Information9 fields
Project Name
_____________
Contract / Package No.
_____________
Permit No.
_____________
Date of Request
_____________
Permit Validity (From Date/Time)
_____________
Permit Validity (To Date/Time)
_____________
Location / Grid Line / Chainage
_____________
Prepared By (Contractor)
_____________
Approved By (PMC/Client)
_____________
2Excavation Details7 fields
Type of Excavation (Trench, Pit, Foundation, etc.)
_____________
Method of Excavation (Manual / Mechanical)
_____________
Excavation Dimensions (L x W x D in meters)
_____________
Soil Type (Hard Rock, Soft Rock, Murrum, Clay, Sandy)
_____________
Proposed Shoring/Sloping/Benching Method
_____________
Drawing No. for Shoring/Sloping Design (if any)
_____________
Dewatering Method (if applicable)
_____________
3Pre-Excavation Safety Checklist (Underground Utilities)7 fields
Underground Electrical Cable Clearance Obtained (Y/N)
_____________
Underground Water/Sewer Line Clearance Obtained (Y/N)
_____________
Underground Gas Pipeline Clearance Obtained (Y/N)
_____________
Underground Communication Cable (OFC) Clearance Obtained (Y/N)
_____________
Trial Pits Dug (Y/N/NA)
_____________
Utility Drawings Checked & Attached (Y/N)
_____________
Barricading Plan Approved (Y/N)
_____________
4On-Site Safety Measures Checklist8 fields
Hard Barricading with Warning Signs & Lights (Y/N)
_____________
Safe Access & Egress Provided (Ladder/Ramp) (Y/N)
_____________
Excavated Soil Kept >1.5m from Edge (Y/N)
_____________
Atmospheric Testing for Confined Space (if >1.2m deep) (Y/N)
_____________
Standby Person / Banksman Deployed (Y/N)
_____________
Adequate Lighting for Night Work (Y/N)
_____________
Availability of First Aid & Emergency Contact Numbers (Y/N)
_____________
Toolbox Talk Conducted & Record Attached (Y/N)
_____________
5Permit Authorization & Closure6 fields
Permit Issuer (Safety Officer) Name & Signature
_____________
Permit Receiver (Site Supervisor) Name & Signature
_____________
Time of Issue
_____________
Permit Closed By (Name & Signature)
_____________
Date & Time of Closure
_____________
Reason for Closure (Work Completed / Unsafe Condition)
_____________
💡 Sample filled excerpt
Location: Tower C, Foundation F-12 (Grid A/3). Dimensions: 5.0m x 4.0m x 2.5m. Soil Type: Clayey Silt. Shoring Method: Strutted Sheet Piles as per Drg No. STR/SH/04. Pre-Excavation Checks: Electrical & Water line clearance obtained from respective departments. On-Site Measures: Hard barricading installed, ladder access provided.
⚖ Compliance notes
  • Helps comply with BOCW (Building and Other Construction Workers) Rules, 1998, specifically Rule 47 (Excavation and Tunnelling).
  • Provides documented proof of due diligence for preventing accidents related to trench collapse or utility damage, crucial during safety audits.
  • Mandatory record for ISO 45001 (OH&S Management Systems) compliance and internal safety reporting.
  • Fulfills contractual obligations under General/Special Conditions of Contract regarding site safety procedures.