OHSR Water Tank BOQ — Worked Example for a 25 kL J...

7 min read · BOQ · Estimation · Water Tank · OHSR · JJM · Worked Example
Home / Knowledge / OHSR Water Tank BOQ — Worked E
BOQEstimationWater TankOHSRJJMWorked Example📖 7 min · 1,732 words

OHSR Water Tank BOQ — Worked Example for a 25 kL JJM Village Reservoir

The OHSR (Overhead Service Reservoir) is the universal water-supply structure in Indian villages and urban housing colonies. Every Jal Jeevan Mission (JJM) village scheme builds one. Every government housing project includes one. The IS 3370 + IS 11682 + CPHEEO Manual standard configuration: cylindrical RCC tank with conical or flat bottom, dome roof, raised on 4-6 RCC staging columns founded on a raft slab. This article walks through a complete BOQ for the most common JJM size — 25 kL on 12 m staging — item by item.

Project Scenario

You're estimating an OHSR for a JJM village scheme serving ~350 households (1,750 persons at 5 per HH). At 135 lpcd × 8-hour gravity storage per CPHEEO Manual, you need ~25 kL. Standard 12 m staging height delivers ~1.2 bar gravity pressure at the tail-end of the distribution network.

Design specification at a glance
  • Capacity: 25 kL (25,000 litres)
  • Staging height: 12 m (ground to tank-bottom)
  • Staging columns: 4 nos, 450 × 450 mm RCC M20
  • Tank diameter: ≈ 3.43 m (derived from 25 kL / 2.7 m liquid depth)
  • Tank wall: 200 mm thick RCC M20
  • Tank base + dome roof: 200 mm + 125 mm RCC M20
  • Internal waterproofing: per IS 3370 (cement-based crystalline)
  • Steel ratio: 130 kg/m³ (water-retaining structure)

The Complete BOQ — 15 Items in CPWD DSR 2023

An OHSR has many more line items than a wall or drain because it has multiple distinct RCC components, each with its own shuttering line. The dome roof is particularly distinctive — DSR has a dedicated rate (5.5) for it.

# DSR Code Item Description Unit Quantity
12.8.1Earthwork in foundation pit, all-kinds-of-soil43.78
24.1.8PCC 1:4:8 below raft, 100 mm thick2.58
35.1.2RCC M20 in raft foundation, 500 mm thick12.15
45.9.1Centering & shuttering for raft (under-side)24.30
55.2.2RCC M20 in 4 staging columns (450 × 450 × 12 m)9.72
65.9.6Centering & shuttering for square columns86.40
75.3RCC M20 in tank base slab, 200 mm thick2.30
85.9.3Centering & shuttering for tank base (suspended slab)11.52
95.2.2RCC M20 in cylindrical tank walls (200 mm × 3 m height)6.46
105.9.2Centering & shuttering for cylindrical walls (× 1.20 for curve)77.56
115.5RCC M20 in dome roof, 125 mm thick1.59
125.9.9Centering & shuttering for dome roof12.67
135.22.6TMT Fe-500D reinforcement (cut, bent, placed)kg4,188.60
1422.5Internal cement-based crystalline waterproofing per IS 337041.56
1519.6.2GI outlet pipe with isolation valve (staging height + tank height + 2 m)m17.00

Total RCC volume = 32.22 m³ across 5 distinct components (raft + columns + tank base + tank walls + dome roof). At 130 kg/m³ that's ~4.2 tonnes of steel — significantly higher per-cubic-metre ratio than non-water RCC because IS 3370 demands 0.24 % minimum surface steel + crack-control bars on every face.

How Each Quantity Was Computed

Tank diameter (derived from capacity)

For a cylindrical tank of capacity V with liquid depth h, the diameter is D = 2√(V/πh). The BOQ Builder picks liquid depth from the capacity bracket — for 25 kL, h = 2.7 m:

D = 2 × √(25 / (π × 2.7)) = 2 × √(2.948) = 3.43 m

Tank total height = liquid depth + freeboard = 2.7 + 0.30 = 3.0 m

1 + 2. Excavation + PCC bed

Raft side = D + 1.5 m projection = 3.43 + 1.5 = 4.93 m (square)
Excavation pit = (raft side + 0.30) × (raft side + 0.30) × 1.60 m depth
= 5.23² × 1.60 = 43.78 m³
PCC width = raft side + 0.15 = 5.08 m
PCC volume = 5.08² × 0.10 = 2.58 m³

3 + 4. RCC raft foundation

500 mm thick raft, sized 4.93 × 4.93 m to spread column loads onto the soil:

Raft volume = 4.93² × 0.50 = 12.15 m³
Shutter area (under-side only) = 4.93² = 24.30 m²

5 + 6. Staging columns

4 columns at 450 × 450 mm × full 12 m staging height:

Col volume each = 0.450 × 0.450 × 12 = 2.43 m³
Total column volume = 4 × 2.43 = 9.72 m³
Shutter area = 4 cols × 4 faces × 0.45 × 12 = 86.4 m²

7 + 8. Tank base slab

Circular slab at top of staging, sized to tank diameter + 200 mm wall thickness on each side. This is a SUSPENDED slab between the four columns, so it needs full-area under-side shuttering:

Tank base radius = D/2 + wall_thk = 1.715 + 0.20 = 1.915 m
Tank base volume = π × 1.915² × 0.20 = 2.30 m³
Tank base shutter = π × 1.915² = 11.52 m²

9 + 10. Cylindrical tank walls

Circumference × wall thickness × height:

Wall volume = π × D × wall_thk × tank_height
= π × 3.43 × 0.20 × 3.00 = 6.46 m³
Shutter area = 2 × π × D × tank_height × 1.20 (× 1.20 for cylindrical-shuttering premium per DSR 5.9.14)
= 2 × π × 3.43 × 3.00 × 1.20 = 77.56 m²

11 + 12. Dome roof

125 mm thick spherical-cap RCC, sized to overall tank radius + 10 % overhang:

Dome volume = π × 1.915² × 0.125 × 1.10 = 1.59 m³
Dome shutter = π × 1.915² × 1.10 = 12.67 m²

13. Reinforcement

130 kg per m³ — typical for water-retaining structures per IS 3370 (1.6-1.8 % by volume, vs 1.2 % for normal slabs):

Total RCC = 12.15 + 9.72 + 2.30 + 6.46 + 1.59 = 32.22 m³
Steel = 32.22 × 130 = 4,188.60 kg (~4.2 tonnes)

14. Internal waterproofing

Cylinder wall surface + tank base — per IS 3370:

Wall area = π × D × tank_height = π × 3.43 × 3.00 = 32.32 m²
Base area = π × (D/2)² = π × 1.715² = 9.24 m²
Total = 41.56 m²

15. Outlet pipe

Runs from tank bottom down through staging to the distribution network at ground level + 2 m extra for distribution-tee fitting:

Outlet pipe length = 12 + 3.0 + 2 = 17 m

What This BOQ Excludes

  • Stairs / cat-ladder to tank top — typically ₹15-25k MS angle iron
  • RCC column ties / horizontal bracing between staging columns every 3 m vertical (~10 % of column volume)
  • Roof-top access manhole + ventilator
  • Level indicator + electrode-based water-level sensor
  • Ladder + safety cage for tank-top access
  • Lightning protection rod (LPS)
  • Inlet pipe + sluice valve + non-return valve + bypass arrangement
  • Chlorination dosing chamber (typically at WTP, not at OHSR)
  • External painting / weather protective finish
  • Submersible pump in the source borewell (separate JJM line item)

Sizing Notes for Different Capacities

CapacityPopulation servedTank Ø (m)Liquid depth (m)Wall thk (mm)Suggested staging
5 kL~70 HH1.782.01504 cols 300 × 300
10 kL~140 HH2.522.01504 cols 380 × 380
25 kL~350 HH (JJM default)3.432.72004 cols 450 × 450
50 kL~700 HH4.852.72006 cols 450 × 450
100 kL~1400 HH6.023.52506-8 cols 600 × 600

Common Estimation Mistakes

  • Using 100 kg/m³ steel as "RCC standard" — water-retaining structures need 130-160 kg/m³ for crack control (IS 3370 minimum 0.24 % each face). Under-steeling causes leakage and 4-6× cost in retrofitting.
  • Forgetting the 1.20× cylindrical shuttering premium — straight wall shuttering is cheaper than curved. DSR 5.9.14 explicitly adds 20 % for cylindrical work. Missing this under-estimates by ~₹15-20k on a 25 kL tank.
  • Skipping internal waterproofing — "the M20 concrete will be dense enough" is wrong. IS 3370 mandates a waterproofing membrane regardless of concrete grade. Tank life without it: 5-8 years vs 30+ with.
  • Treating the dome roof as a flat slab — wrong DSR code (use 5.5 not 5.3), wrong shutter rate, wrong steel pattern (radial + circumferential, not orthogonal). The cost difference is ~25 % per m³.
  • Under-sizing the raft — column load × 4 = 4 × (12 m × column weight + tank dead + water + dome) ≈ 70-90 tonnes total at the raft level on poor soil. The raft must be at least 1.5 m larger than tank diameter on each side. Smaller rafts crack within the first year.
  • Forgetting bracing between staging columns — every 3 m vertical interval needs a horizontal RCC tie beam to prevent column buckling under seismic / wind loads. This is ~10 % of column volume and routinely omitted.

What Changes for a Different Tank

  • Smaller tank (5-10 kL) — 4 columns 300-380 mm, 150 mm walls, lighter raft (300 mm). Steel drops to ~100 kg/m³ for the lighter structure.
  • Larger tank (50-100 kL) — 6-8 staging columns, 250 mm walls, possibly seismic-resistant base isolators in Zone IV/V.
  • Taller staging (15-18 m) — pressure head increases (good for serving higher elevations), but seismic + wind loads on the column scale with height². Heavier columns (600 × 600 mm) and full bracing system required.
  • Below-water-table foundation — add dewatering during construction + waterproof admixture in raft.
  • State-PWD SOR — switch from CPWD DSR to your state's water-supply SOR via the Builder. PHED state SORs are sometimes more current for JJM-specific work.

Get Your OHSR Cost in 30 Seconds

→ Open the OHSR Water Tank BOQ Builder

Change capacity (5-100 kL), staging height, column count + section, wall thickness, waterproofing — the Builder regenerates the BOQ + downloads Excel with formulas embedded. Customize for Your Project →

References & Companion Reading

Join InfraLens WhatsApp Channel
Get updates on new articles, tools, and IS code insights
More Articles
Clause references and parameter values are sourced from official BIS and international standards. Always refer to the original standard document for design decisions.
💬 Join the Discussion
Q: What has been your experience with this topic on site?
Q: Do you have any tips to share with fellow engineers?
Click a question to start your comment
Leave a Comment
0/500
No comments yet. Be the first to share your thoughts!