OHSR Water Tank (5-100 kL with staging)

Cylindrical RCC overhead service reservoir per IS 3370 + IS 11682. RCC raft foundation + 4-6 staging columns + cylindrical tank with conical/flat bottom + dome roof + internal waterproofing + inlet/outlet/overflow pipes. Standard JJM Village Water Supply Scheme component. Rates: CPWD DSR Vol 1 + Vol 2 (2023).

Visual confirmation
Plan · top view · ⌀ 3.43 m tank
MH⌀ 3.43 mTank (25 kL)4 staging columns (450 × 450)
Front elevation · 25 kL × 12 m staging
25 kLOUT12 mtank 3.0 m⌀ 3.43 mNGL4 staging columns @ 450 × 450 mm
Section · ⌀ 3.43 m tank · 200 mm walls
2.7 m⌀ 3.43 mLiquidFree boardNGL━ IS 3370 internal waterproofing
Bill of Quantities15 items · CPWD DSR Vol 1 + Vol 2 (2023)
#CodeDescriptionUnitQtyRate (₹)Amount (₹)
12.8.1ExcavationEarth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, for all lift, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. — All kinds of soil.Cum43.82260.3011,406.35
24.1.8Pcc BedProviding and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : — 1:4:8 (1 Cement : 4 coarse sand (zone-III) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources)Cum2.586,812.0017,574.96
35.1.2Rcc RaftProviding and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : — 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)Cum12.179,045.751,10,086.78
45.9.1Shutter RaftCentering and shuttering including strutting, propping etc. and removal of form for — Foundations, footings, bases of columns, etc. for mass concreteSqm24.34392.159,544.93
55.2.2Rcc ColumnsReinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement : — 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)Cum9.7210,852.951,05,490.67
65.9.6Shutter ColumnsCentering and shuttering including strutting, propping etc. and removal of form for — Columns, Pillars, Piers, Abutments, Posts and StrutsSqm86.40961.3083,056.32
75.3Rcc Tank BaseReinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources).Cum2.3111,505.5026,577.71
85.9.3Shutter Tank BaseCentering and shuttering including strutting, propping etc. and removal of form for — Suspended floors, roofs, landings, balconies and access platformSqm11.54927.2510,700.46
95.2.2Rcc Tank WallsReinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement : — 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)Cum6.4710,852.9570,218.59
105.9.2Shutter Tank WallsCentering and shuttering including strutting, propping etc. and removal of form for — Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.Sqm77.67842.5065,436.98
115.5Rcc Dome RoofReinforced cement concrete work in arches, archribs, domes, vaults, shells, folded plate and roofs having slope more than 15° up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources).Cum1.5912,205.8519,407.30
125.9.9Shutter DomeCentering and shuttering including strutting, propping etc. and removal of form for — Arches, domes, vaults up to 6 m spanSqm12.702,154.3527,360.25
135.22.6SteelSteel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. — Thermo-Mechanically Treated bars of grade Fe-500D or more.Kg4,193.48107.854,52,266.82
1422.5WaterproofingProviding and laying water proofing treatment in sunken portion of WCs, bathroom etc., by applying cement slurry mixed with water proofing cement compound consisting of applying : (a) First layer of slurry of cement @ 0.488 kg/sqm mixed with water proofing cement compound @ 0.253 kg/ sqm. This layer will be allowed to air cure for 4 hours. (b) Second layer of slurry of cement @ 0.242 kg/sqm mixed with water proofing cement compound @ 0.126 kg/sqm. This layer will be allowed to air cure for 4 hours followed with water curing for 48 hours. The rate includes preparation of surface, treatment and sealing of all joints, corners, junctions of pipes and masonry with polymer mixed slurry.Sqm41.62617.0525,681.62
1519.6.2Outlet PipeProviding and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete : — 150 mm dia. R.C.C. pipeMetre17.00556.459,459.65
Your inputsTank capacity 25 kL · Staging height 12 m · Staging columns 4 columns · Column section 450 × 450 mm · Tank wall thk 200 mm · int. waterproofingTOTAL₹10,44,269
12.8.1₹11,406
Excavation
Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, for all lift, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. — All kinds of soil.
43.82 Cum× ₹260.30
24.1.8₹17,575
Pcc Bed
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : — 1:4:8 (1 Cement : 4 coarse sand (zone-III) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources)
2.58 Cum× ₹6,812.00
35.1.2₹1,10,087
Rcc Raft
Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : — 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)
12.17 Cum× ₹9,045.75
45.9.1₹9,545
Shutter Raft
Centering and shuttering including strutting, propping etc. and removal of form for — Foundations, footings, bases of columns, etc. for mass concrete
24.34 Sqm× ₹392.15
55.2.2₹1,05,491
Rcc Columns
Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement : — 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)
9.72 Cum× ₹10,852.95
65.9.6₹83,056
Shutter Columns
Centering and shuttering including strutting, propping etc. and removal of form for — Columns, Pillars, Piers, Abutments, Posts and Struts
86.40 Sqm× ₹961.30
75.3₹26,578
Rcc Tank Base
Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources).
2.31 Cum× ₹11,505.50
85.9.3₹10,700
Shutter Tank Base
Centering and shuttering including strutting, propping etc. and removal of form for — Suspended floors, roofs, landings, balconies and access platform
11.54 Sqm× ₹927.25
95.2.2₹70,219
Rcc Tank Walls
Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement : — 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)
6.47 Cum× ₹10,852.95
105.9.2₹65,437
Shutter Tank Walls
Centering and shuttering including strutting, propping etc. and removal of form for — Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.
77.67 Sqm× ₹842.50
115.5₹19,407
Rcc Dome Roof
Reinforced cement concrete work in arches, archribs, domes, vaults, shells, folded plate and roofs having slope more than 15° up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources).
1.59 Cum× ₹12,205.85
125.9.9₹27,360
Shutter Dome
Centering and shuttering including strutting, propping etc. and removal of form for — Arches, domes, vaults up to 6 m span
12.70 Sqm× ₹2,154.35
135.22.6₹4,52,267
Steel
Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. — Thermo-Mechanically Treated bars of grade Fe-500D or more.
4,193.48 Kg× ₹107.85
1422.5₹25,682
Waterproofing
Providing and laying water proofing treatment in sunken portion of WCs, bathroom etc., by applying cement slurry mixed with water proofing cement compound consisting of applying : (a) First layer of slurry of cement @ 0.488 kg/sqm mixed with water proofing cement compound @ 0.253 kg/ sqm. This layer will be allowed to air cure for 4 hours. (b) Second layer of slurry of cement @ 0.242 kg/sqm mixed with water proofing cement compound @ 0.126 kg/sqm. This layer will be allowed to air cure for 4 hours followed with water curing for 48 hours. The rate includes preparation of surface, treatment and sealing of all joints, corners, junctions of pipes and masonry with polymer mixed slurry.
41.62 Sqm× ₹617.05
1519.6.2₹9,460
Outlet Pipe
Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete : — 150 mm dia. R.C.C. pipe
17.00 Metre× ₹556.45
Tank capacity 25 kL · Staging height 12 m · Staging columns 4 columns · Column section 450 × 450 mm · Tank wall thk 200 mm · int. waterproofing
Estimated total
₹10,44,269
Notes & assumptions
  • Default 25 kL × 12 m staging = JJM Village Water Supply Scheme standard for a village of ~300-500 households. Sized at 135 lpcd × 8-hour storage capacity per CPHEEO Manual on Water Supply.
  • Tank diameter auto-derived from capacity + liquid depth. For 25 kL: dia ≈ 3.5 m × 2.7 m liquid depth. For 100 kL: dia ≈ 6.0 m × 3.5 m liquid depth.
  • Steel quantity uses 130 kg/m³ of RCC — typical for water-retaining structures per IS 3370 (higher than non-water RCC: 1.6-1.8% by volume vs 1.2% for normal slabs).
  • Tank walls are 200 mm by default — adequate for 25 kL with 2.7 m liquid depth. Bump to 250 mm for ≥ 50 kL or seismic Zone IV-V.
  • Cylindrical shuttering uses 20% extra cost per DSR 5.9.14 (built into shutter_tank_walls formula × 1.20).
  • Dome roof uses 125 mm RCC (DSR 5.5). Alternative: precast prestressed dome or flat slab — different DSR codes, not in this Builder.
  • Internal waterproofing (DSR 22.5) is the IS 3370 crack-control rule — mandatory for water tanks, prevents seepage + maintains water quality.
  • Excludes: stairs / cat-ladder to tank top (₹15-25k typical, MS angle iron); RCC column ties / horizontal bracing between staging columns (every 3 m vertical, ~10% of column volume); roof-top access manhole + ventilator; level indicator + electrode-based water-level sensor; ladder + safety cage; lightning protection rod (LPS); inlet pipe + sluice valve + non-return valve + bypass; chlorination disinfection chamber (typical at WTP, not OHSR); painting / external finish; submersible pump (separate JJM line item).

**OHSR (Overhead Service Reservoir)** is the universal water-supply structure in Indian villages + urban housing colonies — every JJM (Jal Jeevan Mission) village scheme builds one, every government housing project includes one. The IS 3370 + IS 11682 + CPHEEO Manual standard configuration: cylindrical RCC tank with conical or flat bottom + dome roof, raised on 4-6 RCC staging columns founded on a raft slab. Sizes 5-100 kL depending on user-count, with 12-18 m staging height to maintain gravity head pressure across the distribution network. This BOQ Builder generates the complete cost per CPWD DSR 2023.

JJM-standard OHSR sizing

JJM specifies **135 lpcd** (litres per capita per day) for rural household water supply. Standard sizing: tank capacity = (population × 135 lpcd × 1/3 day) = roughly **45 litres/person**. So a village of 500 people needs ≈ 25 kL tank. JJM-recommended sizes: **5 kL** for hamlet < 100 people; **10 kL** for 100-200; **25 kL** for 200-500 (the workhorse); **50 kL** for 500-1000; **100 kL** for 1000-2000. Larger settlements use multiple OHSRs or a single ground-level reservoir + boosting pumps. Staging height = 12 m default — provides ~6 m head at the farthest house with gravity flow. Increase to 15-18 m for hilly terrain or large distribution networks.

Construction sequence + special considerations for water tanks

**IS 3370 (Code for Concrete Structures for Storage of Liquids)** is the governing code. Key differences from ordinary RCC: (a) **Crack width control** — IS 3370 Part 2 limits crack widths to 0.2 mm vs 0.3 mm for ordinary RCC; this drives higher steel ratios (1.6-1.8% by volume); (b) **Cover** — minimum 40 mm clear cover to reinforcement vs 25 mm for ordinary RCC; (c) **Concrete grade** — M-25 minimum per IS 3370; M-30 preferred for ≥ 50 kL; (d) **Construction joints** — must have water-stop bands (PVC waterstops, 230 mm wide) at horizontal joints; (e) **Internal waterproofing** — cementatious crystalline coat on internal faces, mandatory per IS 3370 Part 2 Cl. 5.4; (f) **Water testing** — fill to top + observe leakage for 7 days before painting / commissioning. Failure means re-do the waterproofing layer.

Frequently asked questions
Using CPWD DSR 2023 rates for default 25 kL × 12 m staging × 4 columns × 200 mm walls + waterproofing + outlet pipe: approximately **₹10-13 lakh**. State PWD rates run 8-15% below DSR. JJM Department typically allocates ₹8-12 lakh per village OHSR depending on capacity + staging height. Add ~20% for site mobilisation + curing + commissioning in actual tender quotes.

More related

Disclaimer: Rates sourced from CPWD DSR Vol 1 + Vol 2 (2023). Indicative for estimation only — actual tender quotations are governed by market forces, locality factors and current input prices. Quantities follow IS 1200 measurement. Always verify with a local quote before finalising. © InfraLens — infralens.in