Formats  › Site Execution  › Reinforcement Fixing Inspection
Checklist · FMT-SIT-023
Reinforcement Fixing Inspection
10 fields across 3 sections. Hold point inspection — concrete pour cannot proceed without sign-off on reinforcement.
10 Fields
3 Sections
Per element pour
Site Supervisor, QC Engineer

Format Preview

S.No.Field / CheckpointReferenceStatus
A. MATERIAL
A1Rebar grade Fe 500 / Fe 500D + MTC verified
Acceptance: MTC for each lot
IS 1786 Cl. 4
OK
NC
NA
A2Bar diameter (visual + weight check)
Acceptance: Weight match
Tolerance ± 2% per IS 1786 Table 3
OK
NC
NA
A3Surface condition — no loose rust / mill scale
Acceptance: < 5% loose rust
IS 456 Cl. 12.1
OK
NC
NA
B. PLACEMENT
B1Bar size + spacing per BBS / drawing
Acceptance: Counted + measured
Per GFC
OK
NC
NA
B2Cover blocks installed @ 1m spacing
Acceptance: Mortar blocks; correct height
Cover per IS 456 Cl. 26.4
OK
NC
NA
B3Laps positioned + length per IS 456 Cl. 26.2.5 (1.3 × Ld = 47d × 1.3)
Acceptance: Per design
Per code
OK
NC
NA
B4Stirrup hook 135° + 10d extension
Acceptance: Per code
IS 456 Cl. 26.2.2
OK
NC
NA
B5Chairs / spacers for top bars (slab)
Acceptance: Per design
Maintain top cover
OK
NC
NA
C. BBS TALLY
C1Site rebar matches BBS (weight tally ± 2%)
Acceptance: Reconciled
Cross-check qty + weight
OK
NC
NA
C2BOQ qty vs delivered + cut + fixed
Acceptance: Per period
Material reconciliation
OK
NC
NA
A. MATERIAL
A1Rebar grade Fe 500 / Fe 500D + MTC verified
IS 1786 Cl. 4
MTC for each lot
OKNCNA
A2Bar diameter (visual + weight check)
Tolerance ± 2% per IS 1786 Table 3
Weight match
OKNCNA
A3Surface condition — no loose rust / mill scale
IS 456 Cl. 12.1
< 5% loose rust
OKNCNA
B. PLACEMENT
B1Bar size + spacing per BBS / drawing
Per GFC
Counted + measured
OKNCNA
B2Cover blocks installed @ 1m spacing
Cover per IS 456 Cl. 26.4
Mortar blocks; correct height
OKNCNA
B3Laps positioned + length per IS 456 Cl. 26.2.5 (1.3 × Ld = 47d × 1.3)
Per code
Per design
OKNCNA
B4Stirrup hook 135° + 10d extension
IS 456 Cl. 26.2.2
Per code
OKNCNA
B5Chairs / spacers for top bars (slab)
Maintain top cover
Per design
OKNCNA
C. BBS TALLY
C1Site rebar matches BBS (weight tally ± 2%)
Cross-check qty + weight
Reconciled
OKNCNA
C2BOQ qty vs delivered + cut + fixed
Material reconciliation
Per period
OKNCNA
Approval / Sign-Off
APPROVED
HOLD — REVISIONS REQUIRED
REJECTED
Overall Verdict
Name / Sign / Date
Prepared By — Name / Sign
Name / Sign / Date
Reviewed By — Name / Sign
Name / Sign / Date
Approved By — Name / Sign
Name / Sign / Date
Date & Time
Name / Sign / Date
Remarks
Name / Sign / Date