BOQ Builder·Auto-BOQ from dimensions, DSR ratesNEWBidEasy·Government tenders, searchableLIVE
← CAD Library

Overhead Water Tank / ESR Generator

IS 3370 Pt 1/2 container · IS 11682 + IS 1893 Pt 2 staging
Tank Type
Container — Internal Plan + Water
Li (int. length, mm)
Bi (int. breadth, mm)
Hw (water depth, mm)
Freeboard (mm)
Staging (G.L. → container bottom)
Clear height (mm)
No. of columns
Column size (sq, mm)
Bracing levels
Brace beam depth (mm)
Container Shell + Cover
Wall t (mm)
Base slab t (mm)
Top slab/dome t (mm)
Cover, water face (mm)
Container Wall Reinforcement
Vert. bar Ø (mm)
Vert. c/c (mm)
Hoop/horiz. Ø (mm)
Hoop/horiz. c/c (mm)
Staging Column Steel
Bars per column
Bar Ø (mm)
Materials
Concrete
Steel
Computed Quantities
Net capacity60000 L
= volume60.00
Total height (G.L.→top)15650 mm
Hydrostatic p_max29.43 kN/m²
Tank weight (full)1712 kN
Axial / column285 kN
Concrete volume44.92
Total steel2375.1 kg
Loads / weights are indicative for sizing only — not a substitute for a full IS 11682 / IS 1893 Pt 2 seismic analysis (impulsive + convective).
Live Preview — Elevation + Container Plan
ELEVATIONG.L.BRACINGOVERFLOWOUTLETINLETWATER LEVELFREEBOARDHw = 3000STAGING h=12000Container H=3650TOTAL H = 15650PLAN @ CONTAINER BASEInternal 5000 × 4000 · External 5400 × 4400RECTANGULAR ON COLUMNS · 60000 L (60.0 m³) · p_max 29.4 kN/m²
Preview shows live elevation + container plan. PDF adds full sheet layout, member section, BBS, title block, notes.
Quick Reference — IS 3370 / IS 11682 / IS 1893 Pt 2
Min concrete grade (container)M30 (water-retaining, IS 3370 Pt 1 Cl. 4)
Clear cover, water face45 mm (IS 3370 Pt 1 Cl. 8.1)
Permissible crack width≤ 0.2 mm (IS 3370 Pt 2 — limit state of cracking)
Free board150–300 mm (sloshing / overtopping margin)
Staging designIS 11682 — columns + bracing / RCC shaft
Seismic modelTwo-mass impulsive + convective (IS 1893 Pt 2)
Construction jointsPVC water-bar; haunch at wall–base
Full code references: IS 3370 Pt 1 → · IS 3370 Pt 2 → · IS 11682 → · IS 1893 Pt 2 → · IS 456 →

About overhead water tanks (ESR)

An overhead water tank — formally an Elevated Service Reservoir (ESR) — is a water-retaining container raised on an RCC staging so that gravity alone delivers the required residual pressure to the distribution network. The container is designed as a liquid-retaining structure to IS 3370 (Part 1):2021 and IS 3370 (Part 2):2021 (read with IS 456:2000); the staging is designed to IS 11682:1985 with the seismic demand from IS 1893 (Part 2):2014. This generator produces the construction-issue drawing combining both.

In a typical municipal scheme: source water collects in an underground sump, is pumped up into the ESR, and then flows by gravity through the distribution mains during demand hours. The ESR decouples pumping from consumption and provides balancing + emergency storage (typically one-third of the daily demand).

Container shapes and staging types

Why the staging is the critical element (seismic)

An ESR is a heavy mass on slender, flexible legs — structurally a classic soft-storey / inverted-pendulum system. In an earthquake the entire water + container mass swings on the staging, so the staging attracts the full base shear and overturning moment and is almost always what fails first — a repeatedly documented collapse mode (e.g. several ESRs in the 2001 Bhuj earthquake). IS 1893 (Part 2):2014 requires the contained liquid to be modelled as two masses — an impulsive mass rigidly moving with the tank and a convective (sloshing) mass on an equivalent spring — and the staging detailed for ductility (IS 13920) so it can dissipate energy without brittle failure. Treating the staging as an ordinary gravity frame is the single most dangerous mistake in ESR design.

Design steps (what the generator does)

  1. Capacity: net volume = L·B·Hw (rectangular) or π·D²/4·Hw (circular), surfaced in litres and m³ at water level, plus the required free board (150–300 mm).
  2. Container as water-retaining: walls + base + top sized per IS 3370 — M30 minimum, 45 mm cover on the water face, crack width ≤ 0.2 mm, haunch at the wall–base junction, water-bar at construction joints.
  3. Hydrostatics: max pressure at base = γw·Hw (γw = 9.81 kN/m³); indicative cantilever wall moment γw·H³/6 for preliminary sizing.
  4. Staging as a moment frame / shaft: columns + brace beams (or shaft) per IS 11682 carrying vertical + lateral (wind / seismic) loads; indicative axial per column = full tank weight ÷ number of columns.
  5. Seismic: two-mass impulsive + convective analysis per IS 1893 (Part 2), ductile detailing of the staging per IS 13920.
  6. Foundation: a raft / annular ring / individual footings + tie beams sized for the staging reactions (not detailed here — see the footing generators).

Common mistakes

  1. Using M20 / M25 for the container — fails durability and crack control for liquid retention; IS 3370 (Part 1) requires M30 minimum. Low grade leads to leakage and reinforcement corrosion within years.
  2. 25 mm cover on the water face — IS 3370 (Part 1) Cl. 8.1 needs 45 mm on the liquid face; thin cover causes early cracking and rebar attack.
  3. No haunch at the wall–base junction — the sharp re-entrant corner is a stress concentration that cracks and leaks; a 150×150 haunch is mandatory practice.
  4. Staging not ductile-detailed for seismic — designing the staging as an ordinary gravity frame; in an earthquake it fails in brittle shear and the tank collapses (a documented Bhuj-2001 failure mode). Detail per IS 13920 + IS 1893 (Part 2).
  5. No water-bar at construction joints — every horizontal / vertical construction joint in a liquid-retaining wall needs a PVC / metal water-bar; omitting it guarantees a leakage path.
  6. Freeboard omitted — filling to the wall top leaves no margin; the tank overtops on overfill and during sloshing. Provide 150–300 mm.
  7. Ignoring convective (sloshing) action — designing only for the impulsive mass underestimates the wave height and the long-period demand on a flexible tall staging; IS 1893 (Part 2) requires both impulsive and convective components.

Related references