BOQ Builder·Auto-BOQ from dimensions, DSR ratesNEWBidEasy·Government tenders, searchableLIVE
← CAD Library

Underground Water Tank / Sump Generator

IS 3370 Part 1 & 2 + IS 456:2000 — covered / open sump
Tank Type
Internal Dimensions
Li (length, mm)
Bi (breadth, mm)
Hw (water depth, mm)
Free board (mm)
Element Thickness
Wall tw (mm)
Base raft tb (mm)
Top slab tt (mm)
Manhole (mm)
Cover to water face (mm)
Wall Reinforcement
Vertical Ø (mm)
Vertical c/c (mm)
Hoop Ø (mm)
Hoop c/c (mm)
Base Raft Mesh (each way, T & B)
Mesh Ø (mm)
Mesh c/c (mm)
Materials
Concrete (M30 min)
Steel
Computed Quantities
Net capacity30000 L
Capacity (volume)30.00
External size4400 × 3400
Total depth (int.)2700 mm
Max water pressure24.53 kN/m²
Wall moment (indic.)25.55 kN·m/m
Concrete volume13.92
Total steel782.2 kg
Live Preview — Plan + Section
PLANMANHOLEInternal 4000 × 3000 · External 4400 × 3400Wall t = 200SECTIONMANHOLEG.L.WATER LEVELHw = 2500Free board = 200HAUNCHOverall H = 3100COVERED · 30000 L (30.00 m³) · p_max 24.5 kN/m²
Preview shows live plan + section. PDF adds full sheet layout, quantities, BBS, title block, notes.
Quick Reference — IS 3370 Part 1/2 (Liquid-Retaining RCC)
Min clear cover (water face)45 mm (IS 3370 Pt 1 Cl. 8)
Min concrete gradeM30 (durability + crack control)
Permissible crack width0.2 mm (severe / very severe)
Design methodNo-crack or limit-state crack width (IS 3370 Pt 2)
Min wall thickness~150–200 mm (crack / cover)
Wall-base / corner junctionsProvide haunch ~150 × 150 mm
Construction jointsPVC water-bar mandatory
General RCC detailingIS 456:2000 (read with IS 3370)
Full code reference: IS 3370 (Part 1):2021 → · IS 3370 (Part 2):2009 → · IS 456:2000 →

About RCC underground water tanks & sumps

An underground water tank (sump) is a buried RCC liquid-retaining structure used to store municipal / borewell water at the ground level, from which water is pumped up to an overhead tank (OHT) for gravity distribution. It is also used as a fire-water sump or a flushing-water reservoir. Design is governed by IS 3370 (Part 1):2021 (general requirements) and IS 3370 (Part 2):2009 (reinforced concrete — design + reinforcement), read together with IS 456:2000 for general RCC detailing. IS 1893 (Part 2) applies for seismic design of liquid-retaining tanks.

Covered vs open sump

A typical building water system uses an underground sump at ground level (filled from the municipal main / borewell) plus a pump set that lifts water to an overhead tank; distribution is by gravity from the OHT. The sump buffers intermittent municipal supply.

IS 3370 design basis

Liquid-retaining structures are designed for serviceability (no leakage), not just strength. IS 3370 Part 2 permits two approaches: the older no-crack (working stress) method with low permissible tensile stresses in concrete, or the limit-state method with a crack-width check (permissible crack width 0.2 mm for severe / very severe exposure on the liquid face). The environment is treated as severe-to-very-severe, which drives the M30 minimum grade, the 45 mm minimum cover on the water face, and tight bar-spacing / smaller-diameter bars to control crack width.

Design steps (what the generator does)

  1. Capacity: required volume from demand (e.g. half-day to one-day storage). Net capacity = Li × Bi × Hw; shown in litres and m³.
  2. Hydrostatic pressure: triangular pressure on the wall, zero at top and maximum p = γw·Hw at the base (γw = 9.81 kN/m³).
  3. Wall design: for a buried rectangular tank the wall is analysed as a vertical cantilever (or propped between base + top slab when covered); the indicative cantilever moment M ≈ γw·H³/6 per metre run is shown for sizing.
  4. Base raft: designed as a slab on soil, with two-way mesh top + bottom; uplift / flotation governs when the tank is empty and the water table is high.
  5. Crack-width check: spacing + bar diameter limited so the calculated surface crack width ≤ 0.2 mm (IS 3370 Part 2 Appendix).
  6. Detailing: continuous vertical bars anchored into the raft, hoop (horizontal) bars on the water face, haunches at the wall-base junction, PVC water-bar at all construction joints.

Common mistakes

  1. Using M20 concrete — fails the durability / crack-control requirement of IS 3370 Part 1. Water-retaining concrete needs M30 minimum (denser, lower permeability, controls cracking).
  2. 25 mm cover on the water face — IS 3370 Part 1 requires 45 mm minimum on the liquid face. Thin cover leads to early rebar corrosion + spalling + leakage.
  3. No water-bar at construction joints — the kicker / wall-to-base and lift joints are the first to leak. A PVC water-bar (or swellable strip) is mandatory at every construction joint.
  4. No haunch at the wall-base junction — a sharp 90° internal corner is a stress concentration that cracks. Provide a 150 × 150 mm splay haunch to spread the moment.
  5. Ignoring uplift / flotation when empty — an empty buried tank in a high water table can float (buoyancy > self-weight). Check flotation with a factor of safety ≥ 1.2; thicken the raft, project the raft as an anti-flotation toe, or anchor down.
  6. No waterproofing / internal plaster — even sound RCC is not fully watertight. Provide an internal 20 mm CM 1:3 plaster (with waterproofing compound) and an external membrane / coating before backfilling.
  7. Inadequate free board — no air gap above water level leads to overflow seepage at the wall-slab junction; provide 150–300 mm free board and an overflow + scour pipe.

Related references