ESTIMATION
IRUSSOR — Indian Railways Unified Standard Schedule of Rates
Indian Railways Unified Standard Schedule of Rates
Also calledirussorirussor full formwhat is irussorirussor meaningindian railways unified standard schedule of rates
Definition
Railways' nationwide rate book — supersedes individual zonal USSORs. Used by all 18 zones of Indian Railways for civil construction, P-way, electrification, and S&T work. Updated periodically by Railway Board.
Frequently asked
What is the full form of IRUSSOR?
IRUSSOR = Indian Railways Unified Standard Schedule of Rates. Railways' nationwide rate book — supersedes individual zonal USSORs.
Related estimation terms
Construction Cost Estimation
Per sqft cost ₹1500-3500 in India
Quantity Estimation
Estimate cement, steel, sand, aggregate for given area
Material Wastage Factors
Cement 2-3%, steel 3-5%, tiles 5-10% typical
Bill of Quantities (BOQ)
Itemised list of work activities with quantities and unit rates — forms the priced contract document.
Rate Analysis
Computation of unit rate from material + labour + plant + overhead + profit. Reference: DSR, state SOR, in-house DB.
Abstract Estimate
Cost estimate at concept stage based on plinth area or per-bed/per-room rates. ±20% accuracy.
Detailed Estimate
Quantity-based estimate from drawings. Each work item × unit rate × quantity = cost. ±5% accuracy.
Contingency
Provision for unforeseen costs. CPWD: 3%. Private: 5-10%. Higher for renovation than new build.