HandbookFormwork Stripping Time

Formwork Stripping Time

IS 456:2000 · Clause 11 — Formwork, Table 11 — Minimum Period Before Striking Formwork
Minimum time to keep formwork in place before removal. Early stripping can cause cracking, deflection, or collapse. Times assume OPC concrete at 15°C+ — extend for PPC/PSC or cold weather.
IS 456
22 items shown
IS 456 Table 11 — Minimum Stripping Time (OPC at ≥15°C)
For PPC/PSC: add 50% more time. Below 15°C: consult engineer.
Member / StepTimeConditionNote
Walls, Columns, Vertical Faces16–24 hoursSides of beam (non-load bearing)Can strip early — not load-bearing
Soffit of Slab (props left under)3 daysProps remain in placeOnly remove side formwork
Soffit of Slab (props removed)7 daysSpan ≤ 4.5m
Soffit of Slab (props removed)14 daysSpan > 4.5mLonger spans need more time
Soffit of Beam (props left under)7 daysProps remain in place
Soffit of Beam (props removed)14 daysSpan ≤ 6.0m
Soffit of Beam (props removed)21 daysSpan > 6.0m
Cantilever Slab / Beam14 daysAll cantileversCritical — prop until 14 days
Arches (span ≤ 6m)14 days
Arches (span > 6m)21 days
Practical Stripping Sequence
Order of formwork removal to avoid damage
Member / StepTimeConditionNote
Step 1: Column sides24 hrsNon-load bearingStart curing immediately
Step 2: Beam sides24 hrsNon-load bearing
Step 3: Slab soffit (with props)3 daysKeep props at 3m spacingRemove plywood, keep props
Step 4: Beam soffit (with props)7 daysKeep props at mid-span
Step 5: Remove slab props7–14 daysDepending on spanRemove from centre outward
Step 6: Remove beam props14–21 daysDepending on spanRemove from centre outward
Step 7: Remove cantilever props14 days minimumLast to remove
Special Conditions
Member / StepTimeConditionNote
PPC / PSC CementAdd 50% to all above timesSlower strength gainPPC 3-day slab → 4.5 days
Temperature < 15°CDouble the standard timeCold weatherOr until cube reaches 2× stripping load
Temperature < 5°CDo NOT strip until cube test confirmsFrost riskProtect concrete from freezing
Rapid Hardening CementCan reduce to ⅓ of OPC timeConfirm with cube testRHC achieves 7-day strength in 3 days
High early strength concrete (admixture)Reduce per supplier recommendationWith acceleratorMust confirm by testing
Notes
NEVER strip formwork based on calendar alone — always verify concrete has gained sufficient strength
Minimum strength for stripping: 2× the stress the member will carry at that stage
After stripping soffit, immediately start curing the exposed surface
Re-propping: when stripping soffit early (with props), ensure props carry load to ground, not to slab below
In multi-storey construction, maintain props for at least 2 floors below the working floor
For post-tensioned slabs: strip only after stressing is complete
Keep written record of stripping dates for each pour/member