Register · QC-LFT-REG-001
Lift Installation Register
20 checkpoints across 1 sections. Ongoing project record; updated as each lift milestone is achieved
20 Checkpoints
1 Sections
Monthly updates; final consolidation at project handover
Project Manager, QC Coordinator

Checklist Preview

S.No.CheckpointIS RequirementStatus
A. LIFT REGISTER MATRIX
A1S.No. / Lift ID
Acceptance: Sequential numbering; unique ID per shaft; alphanumeric code
Unique identification for each lift
OK
NC
NA
HOLD
A2Building / Block / Zone
Acceptance: Clear identification of building block; zone or area reference
Location tracking
OK
NC
NA
HOLD
A3Lift Type (Electric / Hydraulic / Other)
Acceptance: Type specified per IS 14665 or IS 15785; clearly documented
Classification per standard
OK
NC
NA
HOLD
A4Capacity (persons / kg)
Acceptance: Rated capacity in kg and approximate persons; matches design
Design load specification
OK
NC
NA
HOLD
A5Speed (m/s)
Acceptance: Rated speed in m/s; documented as per design
Design speed
OK
NC
NA
HOLD
A6Number of Stops / Floors Served
Acceptance: Number of landing doors; height range covered
Lift travel coverage
OK
NC
NA
HOLD
A7Lifting Height (m)
Acceptance: Clear distance from pit bottom to top floor
Vertical travel distance
OK
NC
NA
HOLD
A8Supplier / Manufacturer
Acceptance: Lift supplier name; equipment origin documented
Equipment source
OK
NC
NA
HOLD
A9Installation Start Date
Acceptance: Date of first site activity; mobilization documented
Schedule tracking
OK
NC
NA
HOLD
A10Installation Completion Date
Acceptance: Date of final installation; mechanical and electrical work completed
Milestone tracking
OK
NC
NA
HOLD
A11Commissioning Date
Acceptance: Date of acceptance testing; all tests passed
Testing and handover date
OK
NC
NA
HOLD
A12Handover Date
Acceptance: Date lift handed over to client; signed receipt
Transfer of responsibility
OK
NC
NA
HOLD
A13Shaft Construction QC Sign-off
Acceptance: Reference to QC-LFT-CHK-001 report number
Structural approval reference
OK
NC
NA
HOLD
A14Guide Rail & Car QC Sign-off
Acceptance: Reference to QC-LFT-CHK-002 report number
Mechanical approval reference
OK
NC
NA
HOLD
A15Electrical & Commissioning QC Sign-off
Acceptance: Reference to QC-LFT-CHK-003 report number
Electrical approval reference
OK
NC
NA
HOLD
A16Load Test Report (QC-LFT-TST-001)
Acceptance: Reference to test report; passed/conditional/failed status
Performance test reference
OK
NC
NA
HOLD
A17Safety Device Test Report (QC-LFT-TST-002)
Acceptance: Reference to test report; all systems passed
Safety verification reference
OK
NC
NA
HOLD
A18Speed Test Report (QC-LFT-TST-003)
Acceptance: Reference to test report; speed within tolerance
Performance measurement reference
OK
NC
NA
HOLD
A19Installation Status
Acceptance: Status: Design / Procurement / Installation / Testing / Handover / Completed
Current completion phase
OK
NC
NA
HOLD
A20Outstanding Issues / Defects
Acceptance: Snagging list if any; blank if none; reference to corrective action report
Outstanding items tracking
OK
NC
NA
HOLD
A. LIFT REGISTER MATRIX
A1S.No. / Lift ID
Unique identification for each lift (IS 14665)
Sequential numbering; unique ID per shaft; alphanumeric code
OKNCNAHOLD
A2Building / Block / Zone
Location tracking (IS 14665)
Clear identification of building block; zone or area reference
OKNCNAHOLD
A3Lift Type (Electric / Hydraulic / Other)
Classification per standard (IS 14665)
Type specified per IS 14665 or IS 15785; clearly documented
OKNCNAHOLD
A4Capacity (persons / kg)
Design load specification (IS 14665)
Rated capacity in kg and approximate persons; matches design
OKNCNAHOLD
A5Speed (m/s)
Design speed (IS 14665)
Rated speed in m/s; documented as per design
OKNCNAHOLD
A6Number of Stops / Floors Served
Lift travel coverage (IS 14665)
Number of landing doors; height range covered
OKNCNAHOLD
A7Lifting Height (m)
Vertical travel distance (IS 14665)
Clear distance from pit bottom to top floor
OKNCNAHOLD
A8Supplier / Manufacturer
Equipment source (IS 14665)
Lift supplier name; equipment origin documented
OKNCNAHOLD
A9Installation Start Date
Schedule tracking (IS 14665)
Date of first site activity; mobilization documented
OKNCNAHOLD
A10Installation Completion Date
Milestone tracking (IS 14665)
Date of final installation; mechanical and electrical work completed
OKNCNAHOLD
A11Commissioning Date
Testing and handover date (IS 14665)
Date of acceptance testing; all tests passed
OKNCNAHOLD
A12Handover Date
Transfer of responsibility (IS 14665)
Date lift handed over to client; signed receipt
OKNCNAHOLD
A13Shaft Construction QC Sign-off
Structural approval reference (IS 14665)
Reference to QC-LFT-CHK-001 report number
OKNCNAHOLD
A14Guide Rail & Car QC Sign-off
Mechanical approval reference (IS 14665)
Reference to QC-LFT-CHK-002 report number
OKNCNAHOLD
A15Electrical & Commissioning QC Sign-off
Electrical approval reference (IS 14665)
Reference to QC-LFT-CHK-003 report number
OKNCNAHOLD
A16Load Test Report (QC-LFT-TST-001)
Performance test reference (IS 14665)
Reference to test report; passed/conditional/failed status
OKNCNAHOLD
A17Safety Device Test Report (QC-LFT-TST-002)
Safety verification reference (IS 14665)
Reference to test report; all systems passed
OKNCNAHOLD
A18Speed Test Report (QC-LFT-TST-003)
Performance measurement reference (IS 14665)
Reference to test report; speed within tolerance
OKNCNAHOLD
A19Installation Status
Current completion phase (IS 14665)
Status: Design / Procurement / Installation / Testing / Handover / Completed
OKNCNAHOLD
A20Outstanding Issues / Defects
Outstanding items tracking (IS 14665)
Snagging list if any; blank if none; reference to corrective action report
OKNCNAHOLD
Inspection Sign-Off
APPROVED
APPROVED WITH CONDITIONS
REJECTED
Register Summary
Name / Sign / Date
Overall Status of All Lifts
Name / Sign / Date
Outstanding Actions
Name / Sign / Date
Compiled By
Name / Sign / Date
Reviewed By
Name / Sign / Date