Lift Installation Method Statement
25 checkpoints across 5 sections. Submitted before site installation begins; guides entire execution
25 Checkpoints
5 Sections
One per project; reviewed and signed before commencement
Contractor, QC Manager

Checklist Preview

S.No.CheckpointIS RequirementStatus
A. INSTALLATION PHASES AND SEQUENCE
A1Phase 1: Shaft Inspection and Preparation
Acceptance: Concrete cured ≥ 28 days; plumbness verified; rail seating prepared; drawings reviewed by contractor
Cl. 4.1 — Shaft must be ready for rail installation
OK
NC
NA
HOLD
A2Phase 2: Guide Rail Installation
Acceptance: Rails mounted in sequence from bottom to top; brackets torqued; alignment verified at each stage
Cl. 6.1 — Rails installed per design
OK
NC
NA
HOLD
A3Phase 3: Car Frame and Mechanical Assembly
Acceptance: Car lowered into shaft; guide shoes fitted; ropes attached; counterweight installed
Cl. 7.1 — Car frame assembled in shaft
OK
NC
NA
HOLD
A4Phase 4: Motor and Drive System Installation
Acceptance: Motor positioned; sheave mounted; brake tested; coupling alignment verified
Cl. 13.1 — Motor mounted and aligned
OK
NC
NA
HOLD
A5Phase 5: Electrical Installation and Control System
Acceptance: Power supply verified; control panel installed; wiring tested; earthing verified
Cl. 12.1 — Electrical system installed per design
OK
NC
NA
HOLD
A6Phase 6: Safety Systems Installation
Acceptance: Governor rope set; safety gear fitted; buffers mounted; brake tested
Cl. 11.1 — Governor, gear, and buffers installed
OK
NC
NA
HOLD
A7Phase 7: Testing and Commissioning
Acceptance: No-load tests; load tests; speed tests; safety device tests completed
Cl. 15.1 — Complete functional testing
OK
NC
NA
HOLD
A8Phase 8: Handover and Documentation
Acceptance: As-built drawings; test certificates; maintenance manual; warranty provided
Cl. 2.3 — Manuals and records provided
OK
NC
NA
HOLD
B. QUALITY ASSURANCE AND CONTROL CHECKPOINTS
B1Design Review and Site Verification
Acceptance: Design drawings reviewed; site measurements confirm feasibility; changes documented
Cl. 2.1 — Design compliance verified
OK
NC
NA
HOLD
B2Material Inspection and Testing
Acceptance: Steel grade certificates; rope inspection reports; concrete test reports available
Cl. 5.1 — Materials meet standards
OK
NC
NA
HOLD
B3Installation QC Inspection Checklists
Acceptance: QC-LFT-CHK-001, 002, 003 completed; signed by QC Engineer; all items OK or HOLD resolved
Checkpoints at each phase
OK
NC
NA
HOLD
B4Performance Test Documentation
Acceptance: QC-LFT-TST-001, 002, 003 reports signed; all tests passed or conditional approval with corrective actions
Testing reports complete
OK
NC
NA
HOLD
B5Third-Party Independent Verification (if required)
Acceptance: Independent inspector visit conducted; report filed; any defects addressed
Optional external audit
OK
NC
NA
HOLD
C. RESOURCE AND EQUIPMENT PLAN
C1Installation Team Composition
Acceptance: Team lead experienced; electrician certified; mechanical fitter trained; safety officer appointed
Qualified personnel required
OK
NC
NA
HOLD
C2Tools and Testing Equipment
Acceptance: Laser level, laser tachometer, torque wrench, multimeter, insulation tester provided
Proper tools available
OK
NC
NA
HOLD
C3Safety Equipment and PPE
Acceptance: Helmets, harnesses, first aid kit provided; safety induction completed
Safety gear mandatory
OK
NC
NA
HOLD
C4Access and Logistics Plan
Acceptance: Shaft access scheduled; crane availability confirmed; material delivery plan prepared
Site access managed
OK
NC
NA
HOLD
Showing 17 of 25 checkpoints ·
A. INSTALLATION PHASES AND SEQUENCE
A1Phase 1: Shaft Inspection and Preparation
Cl. 4.1 — Shaft must be ready for rail installation (IS 14665)
Concrete cured ≥ 28 days; plumbness verified; rail seating prepared; drawings reviewed by contractor
OKNCNAHOLD
A2Phase 2: Guide Rail Installation
Cl. 6.1 — Rails installed per design (IS 14665)
Rails mounted in sequence from bottom to top; brackets torqued; alignment verified at each stage
OKNCNAHOLD
A3Phase 3: Car Frame and Mechanical Assembly
Cl. 7.1 — Car frame assembled in shaft (IS 14665)
Car lowered into shaft; guide shoes fitted; ropes attached; counterweight installed
OKNCNAHOLD
A4Phase 4: Motor and Drive System Installation
Cl. 13.1 — Motor mounted and aligned (IS 14665)
Motor positioned; sheave mounted; brake tested; coupling alignment verified
OKNCNAHOLD
A5Phase 5: Electrical Installation and Control System
Cl. 12.1 — Electrical system installed per design (IS 732)
Power supply verified; control panel installed; wiring tested; earthing verified
OKNCNAHOLD
A6Phase 6: Safety Systems Installation
Cl. 11.1 — Governor, gear, and buffers installed (IS 14665)
Governor rope set; safety gear fitted; buffers mounted; brake tested
OKNCNAHOLD
A7Phase 7: Testing and Commissioning
Cl. 15.1 — Complete functional testing (IS 14665)
No-load tests; load tests; speed tests; safety device tests completed
OKNCNAHOLD
A8Phase 8: Handover and Documentation
Cl. 2.3 — Manuals and records provided (IS 14665)
As-built drawings; test certificates; maintenance manual; warranty provided
OKNCNAHOLD
B. QUALITY ASSURANCE AND CONTROL CHECKPOINTS
B1Design Review and Site Verification
Cl. 2.1 — Design compliance verified (IS 14665)
Design drawings reviewed; site measurements confirm feasibility; changes documented
OKNCNAHOLD
B2Material Inspection and Testing
Cl. 5.1 — Materials meet standards (IS 14665)
Steel grade certificates; rope inspection reports; concrete test reports available
OKNCNAHOLD
B3Installation QC Inspection Checklists
Checkpoints at each phase (IS 14665)
QC-LFT-CHK-001, 002, 003 completed; signed by QC Engineer; all items OK or HOLD resolved
OKNCNAHOLD
B4Performance Test Documentation
Testing reports complete (IS 14665)
QC-LFT-TST-001, 002, 003 reports signed; all tests passed or conditional approval with corrective actions
OKNCNAHOLD
B5Third-Party Independent Verification (if required)
Optional external audit (IS 14665)
Independent inspector visit conducted; report filed; any defects addressed
OKNCNAHOLD
C. RESOURCE AND EQUIPMENT PLAN
C1Installation Team Composition
Qualified personnel required (IS 14665)
Team lead experienced; electrician certified; mechanical fitter trained; safety officer appointed
OKNCNAHOLD
C2Tools and Testing Equipment
Proper tools available (IS 14665)
Laser level, laser tachometer, torque wrench, multimeter, insulation tester provided
OKNCNAHOLD
C3Safety Equipment and PPE
Safety gear mandatory (IS 14665)
Helmets, harnesses, first aid kit provided; safety induction completed
OKNCNAHOLD
C4Access and Logistics Plan
Site access managed (IS 14665)
Shaft access scheduled; crane availability confirmed; material delivery plan prepared
OKNCNAHOLD
Showing 17 of 25 ·
Inspection Sign-Off
APPROVED
APPROVED WITH CONDITIONS
REJECTED
Method Statement Summary
Name / Sign / Date
Key Risks and Mitigation
Name / Sign / Date
Quality Assurance Strategy
Name / Sign / Date
Proposed By
Name / Sign / Date
Reviewed By
Name / Sign / Date
Approved By
Name / Sign / Date