HomeProjectsExpressway
EXPRESSWAYOperational

Western Peripheral Expressway

Six-lane access-controlled expressway
📍 Kundli, Manesar, Palwal · Haryana
135.6
km
LENGTH
₹6.4K
crore
COST
2018
12 yrs build
OPENED
Kundli
Haryana
LOCATION

About

135 km six-lane access-controlled expressway forming a partial ring around Delhi to the west — opened 2018, completing the Delhi bypass ring with the Eastern Peripheral.
Also known asKundli-Manesar-Palwal ExpresswayKMP ExpresswayNH-352

Western Peripheral Expressway (also known as KMP for Kundli-Manesar-Palwal) is the western half of the Delhi bypass ring road system. The 135.6 km six-lane expressway connects Kundli (north of Delhi) to Palwal (south of Delhi) via Manesar and Gurugram on the western flank, completing — together with the Eastern Peripheral Expressway (135 km, also opened 2018) — a 270 km ring around Delhi.

The project had a tortured 12-year construction history: sanctioned in 2006 with a 30-month target, it was beset by funding disputes, contractor changes (the original concessionaire KMP Expressways went bankrupt), land-acquisition delays, and political controversy. NHAI eventually took over and re-tendered the remaining work to Essar Constructions, completing the project in 2018 at ₹6,400 crore.

The expressway diverts heavy commercial traffic — particularly Punjab/Haryana trucks heading to Mumbai or Rajasthan — around Delhi. Combined with EPE, the ring carries an estimated 50,000+ trucks/day that previously transited through Delhi's saturated arteries, contributing significantly to the capital's air pollution.

Design features include: 6-lane (3+3) configuration, design speed 120 km/h, 4 toll plazas, dedicated truck lanes, integration with all major Delhi-NCR exit roads (NH-1, NH-8, NH-2, NH-44). A 2 km test track section was used by Maruti Suzuki for prototype validation before public opening.

Cross-references

14

Indian Standards, IRC codes, and InfraLens knowledge articles that bear on this project's design and execution. Each link opens the relevant reference page.

Related calculators

4

InfraLens calculators most relevant for expressway projects.

Notable features

  • Forms the western half of Delhi's complete bypass ring (with EPE)
  • Diverts ~50,000 trucks/day around Delhi — major pollution mitigation
  • Six-lane (3+3) with dedicated truck lanes
  • 12-year construction history due to funding + contractor issues
  • Integration with all major Delhi-NCR exit highways
  • 2 km test track section used by Maruti for prototype validation

Records

2
01
Together with EPE — first complete bypass ring around Delhi
02
Major contributor to Delhi air-quality improvement (pollution mitigation)

Stakeholders

3
HS
Client / Owner
Haryana State Industrial and Infrastructure Development Corporation (HSIIDC) + NHAI
HC
Contractor
HCC + KMP Expressways consortium
EC
Contractor
Essar Constructions

Engineering

Structural type
Six-lane access-controlled expressway
Deck
Foundation
Span arrangement

Related expressways