House Construction Cost Calculator — ₹/Sq Ft Rates for 55 Indian Cities (2026)

Indicative Standard-quality civil construction cost (RCC frame, finished to handover, excluding land & statutory fees) for 55 cities across 21 states, reviewed April 2026 against builder indices and verified user projects. Multiply the city rate by the quality multiplier and built-up area for a budget figure; apply the material and hidden-cost tables below for a full estimate. Rate ranges reflect plot, design and finish variation — refine with three contractor quotes.

Metro cities — construction cost (₹/sq ft, Standard quality, 2026)
CityStateRate (₹/sq ft)Typical range
MumbaiMaharashtra₹3,000₹2,500₹3,500
New DelhiDelhi NCR₹2,700₹2,200₹3,200
GurgaonDelhi NCR₹2,600₹2,200₹3,000
NoidaDelhi NCR₹2,500₹2,100₹2,900
PuneMaharashtra₹2,450₹2,200₹2,700
BangaloreKarnataka₹2,400₹2,000₹2,800
ChennaiTamil Nadu₹2,250₹1,900₹2,600
HyderabadTelangana₹2,100₹1,800₹2,500
KolkataWest Bengal₹2,100₹1,800₹2,400
AhmedabadGujarat₹2,050₹1,800₹2,300
All 55 cities by state — Standard-quality rate (₹/sq ft, 2026)
CityStateTierRateRange
AmaravatiAndhra PradeshTier 2₹2,000₹1,800₹2,200
VijayawadaAndhra PradeshTier 2₹1,950₹1,750₹2,150
VisakhapatnamAndhra PradeshTier 2₹2,000₹1,800₹2,200
GuwahatiAssamTier 2₹1,950₹1,700₹2,200
MuzaffarpurBiharTier 3₹1,700₹1,500₹1,900
PatnaBiharTier 2₹1,800₹1,600₹2,000
RaipurChhattisgarhTier 2₹1,850₹1,650₹2,050
FaridabadDelhi NCRTier 2₹2,150₹1,900₹2,400
GhaziabadDelhi NCRTier 2₹2,200₹1,900₹2,500
GurgaonDelhi NCRMetro₹2,600₹2,200₹3,000
New DelhiDelhi NCRMetro₹2,700₹2,200₹3,200
NoidaDelhi NCRMetro₹2,500₹2,100₹2,900
PanajiGoaTier 2₹2,600₹2,300₹2,900
AhmedabadGujaratMetro₹2,050₹1,800₹2,300
RajkotGujaratTier 2₹1,950₹1,750₹2,150
SuratGujaratTier 2₹2,050₹1,800₹2,300
VadodaraGujaratTier 2₹2,000₹1,800₹2,200
KarnalHaryanaTier 2₹2,050₹1,850₹2,250
PanipatHaryanaTier 2₹2,000₹1,800₹2,200
RanchiJharkhandTier 2₹1,850₹1,600₹2,100
BangaloreKarnatakaMetro₹2,400₹2,000₹2,800
Hubli-DharwadKarnatakaTier 2₹1,900₹1,700₹2,100
MangaloreKarnatakaTier 2₹2,100₹1,900₹2,300
MysoreKarnatakaTier 2₹2,050₹1,850₹2,250
KochiKeralaTier 2₹2,300₹2,100₹2,500
KozhikodeKeralaTier 2₹2,100₹1,900₹2,300
ThiruvananthapuramKeralaTier 2₹2,200₹1,900₹2,500
BhopalMadhya PradeshTier 2₹1,900₹1,700₹2,100
IndoreMadhya PradeshTier 2₹1,950₹1,750₹2,150
AurangabadMaharashtraTier 2₹1,900₹1,700₹2,100
MumbaiMaharashtraMetro₹3,000₹2,500₹3,500
NagpurMaharashtraTier 2₹2,000₹1,800₹2,200
NashikMaharashtraTier 2₹1,950₹1,750₹2,150
PuneMaharashtraMetro₹2,450₹2,200₹2,700
BhubaneswarOdishaTier 2₹1,900₹1,700₹2,100
AmritsarPunjabTier 2₹1,950₹1,750₹2,150
ChandigarhPunjabTier 2₹2,150₹1,900₹2,400
LudhianaPunjabTier 2₹2,000₹1,800₹2,200
JaipurRajasthanTier 2₹2,000₹1,800₹2,200
JodhpurRajasthanTier 2₹1,900₹1,700₹2,100
UdaipurRajasthanTier 2₹1,950₹1,750₹2,150
ChennaiTamil NaduMetro₹2,250₹1,900₹2,600
CoimbatoreTamil NaduTier 2₹2,050₹1,850₹2,250
MaduraiTamil NaduTier 2₹1,900₹1,700₹2,100
SalemTamil NaduTier 3₹1,800₹1,600₹2,000
HyderabadTelanganaMetro₹2,100₹1,800₹2,500
WarangalTelanganaTier 2₹1,850₹1,650₹2,050
AgraUttar PradeshTier 2₹1,900₹1,700₹2,100
KanpurUttar PradeshTier 2₹1,850₹1,600₹2,100
LucknowUttar PradeshTier 2₹1,950₹1,700₹2,200
PrayagrajUttar PradeshTier 2₹1,850₹1,600₹2,100
VaranasiUttar PradeshTier 2₹1,850₹1,600₹2,100
DehradunUttarakhandTier 2₹2,050₹1,850₹2,250
KolkataWest BengalMetro₹2,100₹1,800₹2,400
SiliguriWest BengalTier 3₹1,800₹1,600₹2,000

Per-city material prices (cement, steel, sand, aggregate, bricks) are tracked separately on the InfraLens material price pages.

Quality grade multipliers

The city rate above is the Standard baseline. Multiply by the grade factor for Basic, Premium or Luxury finishes:

Finish quality multiplier on the Standard ₹/sq ft rate
GradeMultiplierTypical ₹/sq ftWhat it covers
Basic0.78×₹1,400–1,900/sqftFunctional finish, local materials
Standard1.00×₹1,900–2,800/sqftBranded materials, good finishes
Premium1.35×₹2,800–3,500/sqftHigh-end materials, designer finishes
Luxury1.85×₹3,500–5,500+/sqftImported, smart home, architect-designed

Cost breakup by work component

Approximate share of total civil cost per work head, with the governing Indian Standard for each (structure ≈ 56%, finishing ≈ 21%, services ≈ 12%, other ≈ 16%):

Construction cost breakup (% of civil cost) & governing IS codes
CategoryWork component% of costGoverning IS code(s)
StructureExcavation & Earthwork3%IS 3764
Foundation (PCC + RCC)13%IS 456, IS 1904
Columns & Beams12%IS 456, IS 13920
Slab / Roof8%IS 456, IS 10262
Brickwork / Blockwork10%IS 1077, IS 2185
Plastering5%IS 1661
FinishingFlooring & Tiling8%IS 15622
Doors & Windows7%IS 4021
Painting4%IS 5411
Waterproofing2%IS 3067
ServicesPlumbing & Sanitary6%IS 4985
Electrical Wiring6%IS 694
OtherContingency6%
Contractor Margin10%

Material requirement by construction type

Per-sq-ft cement (50 kg bags) and TMT steel for the main structural systems — multiply by built-up area for a 1,000 sq ft house etc. (add wastage: cement ~5%, steel ~3%):

Cement & steel per sq ft, and per 1,000 sq ft, by structural system
SystemCement (bags/sq ft)Steel (kg/sq ft)Per 1,000 sq ftIS code
Load Bearing0.320.381.52320380 bags · 1,5002,000 kgIS 1905
RCC Frame0.40.483.54.5400480 bags · 3,5004,500 kgIS 456
Steel + RCC0.280.3557280350 bags · 5,0007,000 kgIS 800
Prefab / Precast0.220.2823220280 bags · 2,0003,000 kgIS 15916

Rebar weights follow IS 1786 (Fe 500D); mix proportions IS 10262; measurement IS 1200.

Labour rates & daily wages (2026)

Stage-wise labour (₹/sq ft) and skilled daily wages (2026)
Work stageLabour ₹/sq ftTradeDaily wage (₹)
Excavation & Foundation6090Mason (Mistri)₹700–₹1,200 (Kerala ₹1,500+)
RCC Structure140220Bar Bender₹700–₹1,000
Brickwork / Masonry70120Carpenter₹700–₹1,200
Plastering4070Plumber₹600–₹1,000
Flooring & Tiling2560Electrician₹600–₹1,000
Plumbing & Sanitary2540Painter₹500–₹800
Electrical Wiring1830Helper / Unskilled₹400–₹600
Painting & Finishing3060

Hidden / commonly-missed costs & professional fees

Budget another 15–25% over the per-sq-ft figure for these — the leading cause of cost overruns:

Commonly-missed costs and professional fees (2026)
ItemCostIS code
Soil Testing₹8,000–15,000IS 1892
Temporary Electricity₹5,000–10,000
Water Tankers (est.)₹20,000–40,000
Debris Removal₹15,000–25,000
Anti-Termite Treatment₹5–8/sqftIS 6313
Architect Drawings₹15–25/sqft
Structural Engineer₹8–15/sqft
Municipal Approvals₹5K–50K

Typical construction timeline

Phase-wise timeline & cost flow (single-house, Standard)
PhaseWhen% of costActivities
FoundationMonth 1–216%Excavation, PCC, RCC foundation, plinth
StructureMonth 2–433%Columns, beams, slabs, staircase
Brickwork & PlasterMonth 4–619%Walls, plastering (internal + external)
Rough ServicesMonth 5–612%Electrical conduits, plumbing rough-in
FinishingMonth 6–816%Flooring, tiling, painting, doors, windows
Final TouchesMonth 8–94%Fixtures, cleaning, handover

Estimates are indicative budgeting baselines (±10–15%), not quotations. Rates reviewed April 2026; cross-checked against published builder data and verified InfraLens user projects.

About this calculator

The InfraLens Construction Cost Calculator estimates per-square-foot building cost for over 60 Indian cities, broken down by quality grade (Basic, Standard, Premium, Luxury), floor count, soil type and roof type. Rates are reviewed monthly against published builder data, NoBroker / Houseyog / Housewise medians, and verified subscriber projects.

Use it to size a budget before approaching architects or contractors, to sanity-check a quotation you've received, or to compare two cities head-to-head. The calculator also outputs material quantities (cement bags, TMT steel weight, brick count, RMC volume) per IS 1200 measurement conventions, plus labour-day estimates aligned to CPWD productivity norms.

Methodology

How the per-sqft rate is computed

Each city has a base Standard-quality rate (₹/sqft) derived from a weighted blend of three sources: published broker indices (NoBroker, Houseyog, Housewise), MoUD city-wise CPWD multipliers, and direct submissions from InfraLens users. Quality multipliers — Basic 0.78×, Standard 1.00×, Premium 1.35×, Luxury 1.85× — apply per a survey of finishes (tile grade, plumbing fixtures, joinery class, paint type). Floor count adds 4-7% per additional storey to cover formwork hire and lift / staircase construction. Soil type modifies the foundation cost band: hard-rock −3%, sandy-loam baseline, soft-clay +5-8% to reflect deeper footings or rafts.

What's included

Civil RCC frame, brickwork, plaster, flooring, doors and windows, sanitary fittings, electrical wiring, basic painting, and overheads. Excludes: land cost, soil testing (₹8K-15K), architect fees (₹15-25/sqft), municipal approvals (₹5K-50K), anti-termite treatment (₹5-8/sqft), septic tank (₹30K-60K), boundary wall, landscaping, and luxury imports. Add 15-25% for the commonly missed cost band per the calculator's smart-tips panel.

Material quantity model

Per IS 456:2000 RCC frame standards, quantities are computed at: cement 0.40-0.48 bags/sqft (OPC 43 / IS 8112 or PPC / IS 1489), TMT steel Fe500D 3.5-4.5 kg/sqft (IS 1786), bricks 8-12 per sqft of wall (red clay or fly-ash per IS 12894), aggregate ratio 1:1.5:3 for M20 nominal mix. Wastage allowance: cement 5%, steel 3%, bricks 8%, sand/aggregate 10%. Calculations cross-check against IS 10262:2019 mix-design proportions for the chosen grade.

Worked example — 1,200 sqft G+1 in Bangalore (Standard)

Standard rate for Bangalore: ₹2,300/sqft. Two floors with 7% G+1 uplift on second-floor cost: 1,200 × ₹2,300 × 1.035 = ₹28.6 L base. Add 18% professional fees + missed-cost reserve: ₹5.15 L. Total estimate: ₹33.7 L. Material breakdown: 504 cement bags (₹1.94 L at ₹385 / bag PPC), 4,800 kg TMT steel (₹3.36 L at ₹70/kg Fe500D), 12,000 bricks (₹84,000 at ₹7 each fly-ash), 80 m³ RMC M25 (₹4.0 L at ₹5,000/m³). Labour: 380 mason-days, 760 helper-days at prevailing Bangalore rates. Timeline: 9-11 months for Standard finish.

Frequently asked questions

How accurate is the construction cost calculator?

The calculator targets ±10-12% accuracy on the per-sqft figure for Standard quality, and ±15% on quantities. Real projects deviate from this band most often due to (a) plot constraints requiring deeper foundation, (b) finish upgrades during construction, (c) compliance costs (fire NOC, parking podium) not in the base estimate. Use the output as a budgeting baseline, then refine with three contractor quotes.

Which IS codes does the calculator reference?

IS 456:2000 (RCC design), IS 875:1987 (loads), IS 1893:2016 (seismic), IS 1786:2008 (steel reinforcement), IS 12894:2002 (fly-ash bricks), IS 8112:2013 (OPC 43), IS 1489:2015 (PPC), IS 10262:2019 (concrete mix design), IS 1200 series (measurement conventions). Each material rate links to the relevant IS code page on InfraLens.

How do I estimate cost for a 2BHK / 3BHK?

Typical 2BHK built-up area is 900-1,100 sqft; 3BHK is 1,400-1,700 sqft. Multiply by the city's Standard rate, add 7% per additional floor, then add 18-22% for fees and missed costs. A 1,000 sqft 2BHK in a Tier-2 city (₹1,800 base) lands around ₹22-26 L all-in for Standard finish.

What's the difference between Basic, Standard, Premium, and Luxury?

Basic (0.78×): ceramic tile flooring, single-brand sanitary, plywood doors, distemper paint — load-bearing or RCC frame. Standard (1.00×): vitrified tile, branded CP, flush doors, emulsion paint, RCC frame mandatory. Premium (1.35×): granite + marble, premium CP, teak / engineered-wood doors, designer lighting. Luxury (1.85×): imported stone, Kohler / Grohe fixtures, Italian marble, smart-home wiring, false ceiling throughout.

Are the city rates updated?

Rates are reviewed monthly. Last review date is shown beside each city's rate in the calculator output. Tier-1 cities (Mumbai, Delhi NCR, Bangalore, Chennai, Hyderabad, Pune, Kolkata) update faster than Tier-3 cities where data is sparser. If you have on-ground rate info that contradicts our number, please write to us — we adjust based on user submissions.

What costs are NOT in the per-sqft figure?

Land cost, soil testing, architect fees (15-25/sqft), structural consultant (5-8/sqft), municipal plan approvals (5K-50K), water and electricity connection deposits (10K-30K each), anti-termite treatment (5-8/sqft), septic tank construction (30K-60K), boundary wall, gate, compound paving, landscaping, interior fit-out, modular kitchen, and luxury appliances. Budget another 15-25% over the calculator output for these.