RCC Storm Drain BOQ — Worked Example for a 50 m Covered U-Section Drain
RCC storm drains are the backbone of urban and rural drainage. PMGSY road-network rules mandate side-drains alongside every rural road; AMRUT 2.0's stormwater component co-funds urban drain networks; every panchayat does sullage and storm drains. The CPWD-standard configuration is a U-section RCC drain — M20 reinforced concrete raft and walls, optionally covered with an RCC top slab for footpath or vehicle access. This article walks through a complete BOQ for a 50 m × 600 × 600 mm covered drain along an urban society road.
Project Scenario
You're estimating a storm drain along a 50 m frontage on an urban society's internal road. The drain runs alongside the footpath, so it needs a top slab (pedestrians walk over it). Spec: 600 × 600 mm internal section, 150 mm walls and raft, 150 mm cover slab, 200 mm of cover below ground level.
Design specification at a glance
- Length: 50 m
- Internal width: 600 mm
- Internal depth: 600 mm
- Wall thickness: 150 mm (M20 RCC)
- Raft thickness: 150 mm (M20 RCC)
- Cover slab: 150 mm (M20 RCC) — covered drain
- Depth below NGL: 200 mm (drain top is 200 mm below ground level)
- Steel ratio: 85 kg per m³ RCC (light-medium duty)
The Complete BOQ — 10 Items in CPWD DSR 2023
| # | DSR Code | Item Description | Unit | Quantity |
|---|---|---|---|---|
| 1 | 2.8.1 | Earthwork in trench, all-kinds-of-soil, lead ≤ 50 m | m³ | 72.00 |
| 2 | 4.1.8 | PCC 1:4:8 bed below drain, 100 mm thick | m³ | 5.25 |
| 3 | 5.1.2 | RCC M20 in raft slab (bottom of drain) | m³ | 6.75 |
| 4 | 5.2.2 | RCC M20 in vertical walls (both sides) | m³ | 11.25 |
| 5 | 5.3 | RCC M20 in cover slab | m³ | 6.75 |
| 6 | 5.9.1 | Centering & shuttering for raft (under-side) | m² | 45.00 |
| 7 | 5.9.2 | Centering & shuttering for walls (4 faces) | m² | 150.00 |
| 8 | 5.9.3 | Centering & shuttering for cover slab | m² | 45.00 |
| 9 | 5.22.6 | TMT Fe-500D reinforcement (cut, bent, placed) | kg | 2,103.75 |
| 10 | 2.25 | Backfill with excavated earth, watered + compacted | m³ | 3.00 |
The live BOQ Builder evaluates these formulas in real time — change internal section, depth below NGL, wall thickness, or toggle off the cover slab for an open drain, and the quantities update instantly.
How Each Quantity Was Computed
1. Earthwork — Item 2.8.1
Trench needs 150 mm working space on each side for shuttering access, plus PCC depth:
External drain width = 0.6 + 2 × 0.15 = 0.9 m
Trench width = 0.9 + 0.3 = 1.20 m
Total trench depth = depth below NGL + wall height + cover slab + PCC
= 0.20 + 0.75 + 0.15 + 0.10 = 1.20 m
Excavation volume = 50 × 1.20 × 1.20 = 72 m³
2. PCC bed — Item 4.1.8
PCC width = external drain width + 150 mm overhang = 0.9 + 0.15 = 1.05 m
PCC volume = 50 × 1.05 × 0.10 = 5.25 m³
3. RCC raft slab — Item 5.1.2
Raft volume = length × external width × raft thk
= 50 × 0.9 × 0.15 = 6.75 m³
4. RCC walls — Item 5.2.2
Two walls, each at full wall-height (internal depth + raft thickness):
Wall height = 0.6 + 0.15 = 0.75 m
Wall volume = 2 × 50 × 0.15 × 0.75 = 11.25 m³
5. RCC cover slab — Item 5.3
Slab volume = 50 × 0.9 × 0.15 = 6.75 m³
6 – 8. Centering & shuttering
- Raft (5.9.1): under-side area only = 50 × 0.9 = 45 m²
- Walls (5.9.2): 4 faces total (2 walls × 2 faces each) = 4 × 50 × 0.75 = 150 m²
- Slab (5.9.3): under-side area only = 50 × 0.9 = 45 m²
9. Reinforcement — Item 5.22.6
85 kg per m³ of RCC — typical for light-medium duty storm drains (≈ 1.1 % by volume per IS 456). For drains under vehicle-access cover slabs, revise upward to 100-120 kg/m³.
Total RCC volume = 6.75 + 11.25 + 6.75 = 24.75 m³
Steel = 24.75 × 85 = 2,103.75 kg (~2.1 tonnes)
10. Backfill — Item 2.25
The trench above the drain (200 mm below NGL) is back-filled with excavated earth:
Backfill = trench volume above drain − drain external volume above drain
= 50 × 1.20 × 0.20 − 50 × 0.9 × 0.20
= 12 − 9 = 3 m³
Open vs Covered RCC Drain — Which to Use
Open drain (no top slab) is the default for rural side-drains, garden / society storm drains, and anywhere the drain needs to be visually accessible for desilting. Costs ~30 % less than covered (no slab volume, no slab shuttering, lower steel).
Covered drain (with RCC top slab + grating openings) is used along urban footpaths, vehicle accesses, parking lots, and anywhere pedestrian traffic crosses the drain line. The top slab is 150-200 mm thick RCC with M20 grade for footpath; bump to M25 + 250 mm for regular vehicle access. Always provide manhole / inspection openings at 20-30 m intervals on covered drains for desilting — these are quoted separately (≈ ₹4,500 each for a 600 × 600 mm CI cover with frame).
For carriageway crossings, do NOT use a covered drain — use a box culvert instead. The slab in a covered drain is not designed for IRC Class A/AA wheel loads.
Cost Benchmark by Section (Open Drains)
| Internal section (mm) | Approx Delhi DSR 2023 / 50 m | ₹ per running metre |
|---|---|---|
| 300 × 300 | ~₹85,000 | ₹1,700 |
| 450 × 600 | ~₹1.7 lakh | ₹3,400 |
| 600 × 900 | ~₹3.2 lakh | ₹6,400 |
| 1200 × 1200 | ~₹8.5 lakh | ₹17,000 |
Per-metre rate scales non-linearly because larger internal sections need disproportionately more wall and raft RCC. Adding a cover slab adds ~30 %. State-PWD rates run 8-15 % below DSR; municipal corporation SORs are typically cheaper still.
What This BOQ Excludes
- Gully grating + frame — cast iron 24 × 24 inch ~ ₹3,500 each, one per 10-15 m
- Inlet / inspection chambers at intervals (typically 30 m c/c)
- Manhole covers for desilting access on covered drains
- Expansion joints every 30 m linear (asphalt-filled or PVC water stop)
- Benching / step-irons inside the drain for desilting personnel access
- Connection to existing storm-water main — open trench plus T-junction chamber
Common Estimation Mistakes
- Using 85 kg/m³ steel under a vehicular cover slab — that slab needs 110-130 kg/m³ to take 5-tonne wheel loads. Under-steeling causes cracking within 6 months of opening.
- Forgetting backfill — when the drain top is below ground, the trench above needs back-filling. Most quick-estimates skip this 3-10 m³ item.
- Treating raft + walls + slab as one RCC item — they have different DSR rates (5.1.2 raft < 5.2.2 walls < 5.3 slab in cost per m³). Lumping them under one rate under- or over-estimates the BOQ by 8-12 %.
- Centering for raft = under-side only, not walls + under-side. The raft sits directly on PCC bed; no side shuttering needed. Some estimators double-count by including 4 raft sides.
- Skipping the 100 mm PCC bed on the assumption that "the GSB is enough" — PCC provides a smooth, clean casting surface for the raft. Without it, raft underside is uneven and steel cover is unreliable.
What Changes for a Different Drain
- Open drain (no cover slab) — set "covered" parameter to false. Drops slab volume (6.75 m³), slab shuttering (45 m²), and ~15 % of steel.
- Larger section (e.g., 1200 × 1200 mm) — quadruples internal area, ~3× the RCC volume. Use 200 mm walls and 200 mm raft.
- Vehicular cover slab (parking lot, driveway crossing) — bump slab thickness to 200-250 mm, M25 grade, steel to 110-130 kg/m³, and ideally use a box-culvert-style design instead.
- Below-water-table location — add waterproof admixture to the concrete + 50 mm extra cover to steel + dewatering during construction.
- State-PWD SOR — switch from CPWD DSR to your state SOR from the same dimensions in the Builder.
Get Your Drain's Cost in 30 Seconds
Change length, internal section, depth, wall thickness, cover slab — the Builder regenerates the BOQ + downloads Excel with formulas embedded. Customize for Your Project →
References & Companion Reading
- IS 456:2000 — Plain and Reinforced Concrete (concrete grades, cover, mix proportions, water-cement ratios)
- IS 1200 Part 2:1974 — Concrete measurement
- IS 1200 Part 5:1982 — Earthwork measurement
- IS 4111 Part 1:1986 — Code of Practice for Ancillary Structures in Sewerage System (drains, manholes)
- IS 1786:2008 — TMT Fe-500D reinforcement
- CPHEEO Manual on Storm Water Drainage — sizing methodology (rational method, Manning hydraulics)
- Sister tool: Box Culvert BOQ Builder — for carriageway crossings
- CPWD DSR 2023 — full SOR with rates by item