📘 Based on IS 1786·📖 Read: Rebar weight chart
Steel ToolsSection TableBeam SelectorRebar WeightPlate / Pipe Weight

TMT Rebar Weight Calculator

IS 1786 · Weight per metre for 6mm–40mm bars · D²/162.2 formula
Select Diameter (mm)
Calculator
0.889 kg/m × 12m × 1 nos =
10.7kg
0.011tonnes
Per bar: 10.67 kg · Bars per tonne: 93
Weight Chart — All Diameters
Dia (mm)Area (mm²)Wt/m (kg)Wt/12m (kg)Bars/TCommon Use
628.30.2222.66375Stirrups, ties
850.30.3954.74210Stirrups, distribution bars
1078.50.6177.40135Slabs, secondary reinforcement
12113.10.88910.6793Slabs, beams, columns
16201.11.58018.9652Beams, columns, footings
20314.22.46929.6333Beams, columns, footings
25490.93.85846.3021Heavy beams, columns, piles
28615.84.83958.0717Heavy columns, raft foundations
32804.26.32175.8513Heavy columns, piles, retaining walls
361017.97.99995.9910Piles, heavy structural members
401256.69.877118.528Piles, bridge piers
Formula
Weight (kg/m) = D² / 162.2
Where D = diameter in mm. Derived from: (π/4) × D² × 7850 / 10⁶, where 7850 kg/m³ is the density of steel. Simplified: D² × 0.00617 ≈ D² / 162.2
📐 Bar Bending Schedule
Cutting length · IS 2502
📖 Rebar Weight Article
Detailed guide · IS 1786
Generated by InfraLens · infralens.in

About this calculator

The Rebar Weight Calculator computes the unit weight (kg/m) and total weight of TMT reinforcement bars per IS 1786:2008. It uses the standard formula W = d²/162 (d in mm) which derives from steel density 7,850 kg/m³ and circular cross-section. Enter a bar diameter, length, and number of bars — get total weight in kg, plus the IS 1786 tolerance band (±3.5%).

Use it during BBS preparation, material take-off, billing reconciliation, or as a quick reference when verifying a vendor's invoice against actual delivered weight.

Methodology

The d² / 162 formula

Steel density: 7,850 kg/m³ ≈ 7.85 g/cm³. Cross-section area of round bar = π × d² / 4 (mm²) = π × d² / 4 × 10⁻⁶ m². Weight per metre = area × 1m × density = π × d² / 4 × 10⁻⁶ × 7,850 = d² × 6.165 × 10⁻³ ≈ d² / 162.16. The 162 figure is the rounded constant used universally in Indian practice — yields 0.395 kg/m for 8mm, 0.617 kg/m for 10mm, 0.888 kg/m for 12mm, and so on.

Standard nominal weights

Per IS 1786:2008 Table 1: 6mm = 0.222 kg/m, 8mm = 0.395, 10mm = 0.617, 12mm = 0.888, 16mm = 1.578, 20mm = 2.466, 25mm = 3.852, 28mm = 4.834, 32mm = 6.313, 36mm = 7.99, 40mm = 9.864. Tolerance band is ±3.5% of nominal weight (also Table 1) — actual delivered batches may run light (vendors save material) or heavy (out-of-spec mill). Always verify against weighbridge.

Wastage and lap allowances

BBS material take-off applies a wastage allowance: 3% for typical jobs (offcuts, tying, mill mistakes), up to 5% for heavily detailed members (columns with cranks, footings with multiple-direction reinforcement). Lap length per IS 456 Cl. 26.2.5: tension lap = 50d (Fe 415) / 60d (Fe 500); compression = 40d. Don't forget cranks at supports for slabs / cantilevers — adds ~0.42d × cover-to-cover height per crank.

Worked example — 1,000 kg of 12mm steel = how many metres?

12mm unit weight: 0.888 kg/m. 1,000 / 0.888 = 1,126 metres. If sold in standard 12-metre lengths, that's 1,126 / 12 = 94 bars. With 3% wastage allowance, order 97 bars (1,164 m). At ₹70/kg Fe 500D, cost = 1,000 × 70 = ₹70,000. Reverse: a 12-metre 12mm bar weighs 12 × 0.888 = 10.66 kg. A bundle of 50 bars = 533 kg.

Frequently asked questions

What is the difference between Fe 415, Fe 500, and Fe 500D?

Number is yield strength (N/mm²): Fe 415 = 415, Fe 500 = 500, Fe 550 = 550, Fe 600 = 600. Suffix D (or HCRM/HYSD) indicates high ductility. Fe 500D is the modern default for RCC — combines high yield strength with good elongation (≥ 16% per IS 1786:2008) for ductile failure under seismic load. Per IS 13920:2016, Fe 500D or Fe 415 is required in seismic zones (IV, V) for primary members.

Why is the formula d²/162 specifically?

Steel density is 7,850 kg/m³, and the constant comes from π × 7,850 / 4 / 1,000 = 162.16. Indian practice rounds to 162 for simplicity. Using 162 introduces a +0.1% error vs the exact value — within IS 1786 tolerance. ACI 318 / BS 8110 use slightly different constants because of local density assumptions and unit conventions (kg/m³ vs lb/ft³).

How much wastage should I include?

3% for routine jobs (slabs, beams, simple columns), 5% for complex detailing (heavily congested columns, foundation rafts with overlapping reinforcement), 7-8% for prestressed concrete (PT cables) due to anchor losses and cutting. Always verify against actual site wastage from past projects with your contractor — newer crews can run higher (8-10%).

What is the difference between nominal and actual weight?

Nominal weight = catalogue value per IS 1786 Table 1. Actual delivered weight may differ by ±3.5% per the tolerance band — vendors often supply slightly under nominal to save material. Always get a mill test certificate and verify against weighbridge for projects > ₹10 L. Discrepancy beyond -3.5% is grounds for rejection.

Are coupler / weld splices alternatives to laps?

Yes. Per IS 13920:2016 Cl. 5.3.1, mechanical couplers (Type 1 / Type 2 per IS 16172) or full-penetration welds can replace lap splices in seismic zones, saving steel and avoiding congestion. Couplers especially useful for #8 (25mm) and larger bars where laps become impractical (50d × 25 = 1,250 mm). Cost: coupler ₹100-180 each vs lap material; weld ₹50-90 each but needs WQT / WPS.

Related IS / IRC codes

Related articles

Related tools