Standard daily output per skilled worker for common construction activities, based on CPWD norms used across Indian government works. Use for crew sizing, schedule planning, and cost estimation. Productivity varies Β±20β30% with site conditions, weather, supervision, and worker skill β use as a benchmark, not a guarantee.
Related π CPWD βοΈ Concrete cover π Concrete cover π Rate Analysis in Civil Engiβ¦ π§ RCC design
Concrete Work (per mason per 8-hour day)
Activity Output Unit Crew Note PCC 1:4:8 / 1:5:10 (mass) 5.0β7.0 mΒ³ per day 1 mason + 4 labourers + 1 mixer Hand mixing β half output PCC 1:3:6 (column footings) 4.0β5.0 mΒ³ per day 1 mason + 3 labourers β RCC slab (M20/M25, machine mixed) 3.0β4.0 mΒ³ per day 1 mason + 4 labourers Includes vibration & finishing RCC beam (M20/M25) 2.5β3.5 mΒ³ per day 1 mason + 4 labourers Smaller pours, more handling RCC column (M20/M25) 1.5β2.5 mΒ³ per day 1 mason + 4 labourers Vertical pour, slower Concrete pump (RMC) 30β50 mΒ³/hr (pump rate) 1 pump op + 6 labourers Far higher than manual
Brickwork (per mason per day)
Activity Output Unit Crew Note Brickwork in foundation/plinth (1:4) 1.5β2.0 mΒ³ per day 1 mason + 2 labourers β 750 bricks/day Brickwork in superstructure (1:6) 1.0β1.5 mΒ³ per day 1 mason + 2 labourers β 500 bricks/day Half-brick wall (115 mm) 8.0β10.0 mΒ² per day 1 mason + 1 labourer Partition walls AAC block work (200 mm) 5.0β7.0 mΒ³ per day 1 mason + 2 labourers Faster than brick RR (random rubble) masonry 1.0β1.5 mΒ³ per day 1 mason + 2 labourers β Coursed rubble masonry 0.8β1.2 mΒ³ per day 1 mason + 2 labourers Slower due to dressing
Plastering (per mason per day)
Activity Output Unit Crew Note Internal plaster 12 mm (1:6) 10.0β12.0 mΒ² per day 1 mason + 1 labourer Single coat External plaster 15 mm (1:5) 8.0β10.0 mΒ² per day 1 mason + 1 labourer Sand-faced finish Two-coat external plaster 20 mm 6.0β8.0 mΒ² per day 1 mason + 2 labourers Both coats Ceiling plaster 6 mm 8.0β10.0 mΒ² per day 1 mason + 1 labourer Slower β overhead work Punning (white finish 3 mm) 15.0β20.0 mΒ² per day 1 mason + 1 labourer Lime / POP Pointing (re-pointing brickwork) 8.0β10.0 mΒ² per day 1 mason + 1 labourer β
Steel & Reinforcement
Activity Output Unit Crew Note Bar bending & cutting 100β150 kg per fitter per day 1 bar bender + 1 helper Includes BBS Reinforcement fixing in slabs 300β400 kg per fitter per day 1 fitter + 2 helpers Higher for larger bars Reinforcement fixing in columns 200β300 kg per fitter per day 1 fitter + 2 helpers Slower β vertical work Reinforcement fixing in beams 250β350 kg per fitter per day 1 fitter + 2 helpers β Structural steel erection (heavy) 1.0β2.0 tonne per crew per day 1 erector + 4 fitters + crane Industrial sheds
Finishing & Other Trades
Activity Output Unit Crew Note Tile laying (300Γ300 floor) 10.0β15.0 mΒ² per day 1 mason + 1 helper Larger tiles slower Tile laying (600Γ600 floor) 8.0β12.0 mΒ² per day 1 mason + 1 helper β Wall tiling (kitchen/bath) 6.0β8.0 mΒ² per day 1 mason + 1 helper Vertical work, slower Polished kota / marble 4.0β6.0 mΒ² per day 1 mason + 1 helper Includes grinding Shuttering (column) 8.0β12.0 mΒ² per carpenter per day 1 carpenter + 1 helper β Shuttering (slab + beam) 6.0β10.0 mΒ² per carpenter per day 1 carpenter + 1 helper Including props & soffit Painting β primer 30.0β40.0 mΒ² per painter per day 1 painter + 1 helper Smooth surface Painting β emulsion (2 coats) 20.0β25.0 mΒ² per painter per day 1 painter + 1 helper β Painting β exterior textured 15.0β20.0 mΒ² per painter per day 1 painter + 1 helper β
Earthwork & Excavation
Activity Output Unit Crew Note Excavation (manual, ordinary soil) 2.5β3.5 mΒ³ per labourer per day Labourer only Loose soil, depth β€ 1.5 m Excavation (manual, hard soil) 1.5β2.0 mΒ³ per labourer per day Labourer + pickaxe Murum, weathered rock Excavation (machine, JCB 3CX) 60β100 mΒ³ per machine per day 1 operator Plus dumpers Backfilling with compaction 5.0β7.0 mΒ³ per labourer per day 1 labourer + manual rammer β
Notes
β’ These are CPWD norms β contractor productivity is often Β±30% in either direction
β’ Productivity drops ~25% in monsoon, ~15% in extreme heat (>40Β°C), ~20% in night work
β’ Always add 10β15% supervision overhead when computing crew sizes
β’ First day on a new task: expect 60β70% of normal output (learning curve)
β’ Output goes up 20β30% in repetitive work (e.g., 50+ identical floors)
β’ Don't size crews from output alone β also check the working area / front available
β’ For heavy industrial work, refer to RCD/IOC/NTPC norms β these are typically lower than CPWD
β’ Use these for offer preparation; for actuals, log site productivity weekly and recalibrate
Also useful 1 related items across IS codes, knowledge articles, design rules, maps and tools
π Related Knowledge ArticlesΒ· 1 Generated by InfraLens Β· infralens.in