IS 1888:1982 is the Indian Standard (BIS) for method of load test on soils for shallow foundations. This standard covers the procedure for determining the ultimate bearing capacity, safe bearing pressure, and expected settlement of shallow foundations using an in-situ plate load test. It details the required equipment, test setup, incremental loading procedure, and the interpretation of load-settlement curves for both cohesive and cohesionless soils.
Specifies the method for conducting plate load tests on soils to determine the bearing capacity and settlement characteristics for shallow foundations.
Field plate load test for safe bearing capacity of soil. Plate sizes, loading procedure, scaling.
| Reference | Value | Clause |
|---|---|---|
| Plate type | rigid steel, square or circular | Cl. 3.1 |
| Plate sizes — standard | 300, 450, 600, 750 mm | Cl. 3.1.1 |
| Plate thickness — minimum | 25 mm | Cl. 3.1.1 |
| Test pit depth | = proposed founding depth | Cl. 4.1 |
| Test pit width | ≥ 5 × plate size | Cl. 4.1 |
| Loading method — gravity / kentledge | stacked weights on platform | Cl. 5.1 |
| Loading method — reaction (preferred) | hydraulic jack against truss / anchor | Cl. 5.2 |
| Load increment — first stage | 1/5 of estimated SBC | Cl. 6.1 |
| Load increment — subsequent stages | 1/10 of SBC | Cl. 6.1 |
| Settlement reading interval | 1, 2, 4, 8, 15, 30, 45, 60 minutes | Cl. 6.2 |
| Stage termination criterion | settlement < 0.02 mm/min for 1 hour | Cl. 6.2 |
| Test continuation | to 1.5 × estimated SBC or failure | Cl. 6.3 |
| Failure criterion — load-settlement | marked break / breakdown of slope | Cl. 7.2 |
| Settlement scaling — sandy soil | Sf = Sp × ((Bf(Bp+0.3))/(Bp(Bf+0.3)))² | Cl. 7.4 (Bowles) |
| Settlement scaling — clayey soil | Sf = Sp × (Bf / Bp) | Cl. 7.4 |
| SBC factor of safety — typical | 2.5–3.0 | (IS 6403) |
| Maximum permissible settlement (sand) | 25 mm | (IS 1904 Cl. 5) |
| Maximum permissible settlement (clay) | 40 mm | (IS 1904 Cl. 5) |
| Number of tests for site characterisation | min 3 per soil layer | Cl. 4.2 |
| Reporting — load-settlement curve + tabular | log-log + arithmetic | Cl. 8 |
IS 1888 specifies the method of load test on soils for shallow foundations — the in-situ Plate Load Test (PLT). A rigid steel plate is placed at the proposed founding level and loaded incrementally; settlement under each increment is measured. The result is the soil's bearing capacity and modulus of subgrade reaction at the test depth — direct empirical input to shallow foundation design.
Use IS 1888 PLT for: - Foundation design verification for important buildings (hospitals, schools, multi-storey > 4 storey) - Allowable bearing capacity estimation when SPT-based correlations are inadequate - Settlement estimation for sensitive structures (water tanks, machine foundations) - Subgrade modulus (k_s) for raft foundation analysis - Pavement design input — modulus of subgrade reaction for rigid pavement design (IRC:58:2015) - Pre-failure foundation forensics — when settlement is observed in completed structure - Heritage foundation assessment — non-destructive characterisation of existing footings
PLT is more accurate than SPT-based correlations for shallow founding strata (top 1-3 m below test plate); cheaper than full triaxial test programme; faster than long-term consolidation tests for granular soils. For deep foundations and pile design, use IS 2911 Part 4:1985 (pile load test) instead.
IS 1888 is referenced by: - IS 6403:1981 — bearing capacity calculation methods - IS 1080:1985 — design of shallow foundations - IS 8009 Part 1:1976 — settlement of shallow foundations - IRC:58:2015 — rigid pavement design (k_s input) - IRC:37:2018 — flexible pavement design (subgrade strength)
Equipment: - Test plate: square or circular, mild steel, 25 mm thick - Standard sizes: 300 × 300 mm, 450 × 450 mm, 600 × 600 mm, 750 × 750 mm - Larger plates more representative; smaller plates for thinner founding strata - Hydraulic jack with calibrated load cell or proving ring (capacity 100-500 kN typical) - Reaction system: kentledge dead-weight platform OR ground anchor reaction beam - Settlement gauges: 3-4 dial gauges with reference frame independent of load + reaction
Test pit: - Excavated to proposed founding depth - Pit dimensions: minimum 3-5 × plate dimension to ensure undisturbed soil under test - Square or rectangular shape; bottom carefully levelled - For deep tests (> 3 m): adequate shoring
Procedure: 1. Excavate to founding depth, level the bottom of the pit 2. Place test plate centrally 3. Apply gentle seating load (~1/10 of expected ultimate); record initial readings 4. Apply load increments — typically 1/10, 1/8, 1/6 of estimated ultimate, then doubling 5. Hold each load step until settlement rate < 0.02 mm per minute (granular) OR 0.02 mm per 5 min (cohesive) 6. Record cumulative settlement at end of each load step 7. Continue until either: - Settlement = 0.025 × plate width OR - Settlement-vs-load curve shows yielding (sudden settlement at constant load) - Test load reached limit of jack capacity 8. Unload in 4 increments, record rebound 9. Compute ultimate bearing capacity from break in load-settlement curve OR from settlement criterion
Test cycle (for cyclic test): - Load to ~50 % of expected ultimate, unload to 0 - Reload to ~75 %, unload to 0 - Reload to ultimate, unload to 0 - Yields elastic vs plastic settlement separately
Bearing capacity from PLT (Terzaghi-Peck):
Scale effect — plate to footing: - Granular soils (sand): q_u of large footing > q_u of small plate - q_u(footing) ≈ q_u(plate) × (B_footing / B_plate)^0.5 - Cohesive soils (clay): q_u practically independent of footing size - q_u(footing) ≈ q_u(plate)
Settlement scaling (granular): - s_footing / s_plate = (B_footing / B_plate × (B_plate + 0.3) / (B_footing + 0.3))^2 - Where s = settlement, B = footing width (m) - Implication: settlement of footing > settlement of plate at same pressure (footing is larger; mobilises deeper soil)
Subgrade modulus (k_s): - k_s = applied pressure / settlement (typical units: kN/m² per mm of settlement, or pci, or MN/m³) - For rigid pavement design (IRC:58:2015): k_s = 50-200 MN/m³ typical for compacted granular sub-base - For raft foundation Winkler model: k_s used directly
Test plate sizes — when to use which: - 300 × 300 mm: sand / silt; small structures; shallow founding (< 1 m) - 450 × 450 mm: granular soils; medium structures - 600 × 600 mm: cohesive soils; medium / large structures - 750 × 750 mm: deep founding; large structures; raft foundation design
Reaction loading: - Kentledge: dead weight ≥ 1.2 × max test load - Ground anchors: provide adequate reaction; spacing ≥ 3 × plate dimension from test plate
Settlement criterion (Terzaghi-Peck): - Ultimate at settlement = 0.025 × plate width (for granular) - Stricter for sensitive structures: settlement = 0.0125 × plate width
Test sample size: - 1 PLT per major founding stratum (minimum) - For project area > 1000 m²: 2-3 PLTs at characteristic locations - For variable soil: 4-5 PLTs at corners + centre
1. Test plate too small for actual footing. 300 mm plate result for 3 m wide raft = 10× scale-up; correction factor highly uncertain. Use largest practical plate; ideally 600-750 mm. 2. Reaction system interferes with test plate. Kentledge support footings load adjacent ground; their settlement bias reading. Maintain spacing. 3. Pit bottom disturbed during excavation. Remoulded soil layer at bottom; PLT measures disturbed layer, not undisturbed. Carefully level + remove disturbed soil before plate placement. 4. Test below water table without dewatering. Water entering pit destabilises soil; PLT result unreliable. Dewater + maintain dry test conditions. 5. Loading rate too fast. Soil doesn't have time to fully respond to each increment; result over-estimates capacity. Hold each step until settlement rate < 0.02 mm / 5 min. 6. Settlement reference frame supports too close. Frame supports settle along with plate; gauges read low. Reference frame supported ≥ 3-5 plate diameters away. 7. Single test interpolated for entire site. Soil heterogeneity ignored; design for weakest stratum, not characteristic. Run multiple PLTs across site. 8. Scale effect not applied for granular soil footing design. Plate result used directly for large footing; under-estimates settlement. Apply scale-up formula. 9. PLT in clay where consolidation matters. Short-term PLT shows undrained behaviour; long-term consolidation settlement not captured. For clay, PLT must be supplemented with consolidation test. 10. Settlement criterion too lax. 0.025 × B may be acceptable for warehouse but excessive for hospital / equipment foundation. Use stricter criterion for sensitive structures. 11. Calibration of jack / load cell stale. Force measured wrong by 10-20 %. Use calibrated equipment; certificate within 6 months. 12. No test at multiple founding depths. PLT at 1 m depth may give different result than at 1.5 m if stratum changes. Test at planned founding depth + check + 0.5 m below.
Foundation investigation cascade for a typical building:
1. Reconnaissance — desk study, walk-over. 2. Boring + sampling (IS 1892) — boreholes at corners + centre. 3. Index tests on every stratum: - Moisture content, gradation (IS 2720 Part 4), Atterberg limits (Part 5) - Specific gravity (Part 3) - Classification (IS 1498) 4. Strength tests: - Cohesive: UCS (Part 10), triaxial UU - Granular: SPT (IS 2131) + direct shear (Part 13) 5. In-situ tests: - Plate Load Test (this code, IS 1888) at proposed founding level - SPT continuous in borehole - Pressuremeter (advanced; less common in India) 6. Synthesis: - Allowable bearing pressure (IS 6403:1981) - Settlement (IS 8009) - Foundation type recommendation (shallow / deep) 7. Foundation design (IS 1080:1985 for shallow; IS 2911 Parts 1-4 for piles).
For minor / small projects: - SPT only, with empirical correlations to bearing capacity - PLT optional
For important / sensitive projects: - SPT + PLT + lab tests + multiple boreholes - PLT mandatory at proposed founding level - Multiple PLTs for site characterisation
For pavement (rigid): - PLT as the source of subgrade modulus k_s - Used directly in IRC:58:2015 slab thickness calculation
Typical PLT cost (2026): - ₹50,000-1,50,000 per test (depending on depth, plate size, reaction system) - Significantly cheaper than full triaxial programme + lab testing - High value-for-money for foundation design verification
| Parameter | IS Value | International | Source |
|---|---|---|---|
| Typical Test Plate Size | Square: 300 to 750 mm. Commonly 450 mm. | Circular: 152 to 762 mm (6 to 30 in.) diameter. | ASTM D1196 / D1196M-16 |
| Seating Load | 7 kN/m² (applied and removed). | Not specified; sufficient for 'snug contact'. | ASTM D1196 / D1196M-16 |
| Number of Settlement Gauges | Minimum of 2, preferably 3. | At least 3. | BS 1377-9:1990 |
| Load Increments | ≤ 100 kN/m² or 1/5 of estimated ultimate load. | ≤ 10% of estimated ultimate bearing capacity. | ASTM D1196 / D1196M-16 |
| Settlement Rate for Stability | Rate < 0.02 mm/minute. | Rate < 0.02 mm in a 5-minute interval (for fine soils). | BS 1377-9:1990 |
| Reaction Load Distance from Plate | Not less than 2.5B (for kentledge) or 3.5B (for anchors), where B is plate width. | No less than 2.4 m (8 ft). | ASTM D1196 / D1196M-16 |
| Maximum Settlement for Failure | Often taken as 25 mm, or when settlement is progressive. | Not explicitly defined; test continues until a predetermined load or settlement is reached. | ASTM D1196 / D1196M-16 |