InfraLensInfraLens
IS CodesIRCToolsSORHandbookQA/QCPMCFormatsCPHEEOMapsProjectsDCRRulesAbout Join Channel
Join
IS CodesIRCToolsSORHandbookQA/QCPMCFormatsCPHEEOMapsProjectsDCRDesign RulesBIMAbout Join WhatsApp Channel
InfraLensInfraLens
IS CodesIRCToolsSORHandbookQA/QCPMCFormatsCPHEEOMapsProjectsDCRRulesAbout Join Channel
Join
IS CodesIRCToolsSORHandbookQA/QCPMCFormatsCPHEEOMapsProjectsDCRDesign RulesBIMAbout Join WhatsApp Channel

IS 1200 (Part 1) : 2000Methods of measurement of building and civil engineering works, Part 1: Earthwork

PDFGoogleCompareBIS Portal
Link points to Internet Archive / others. Not hosted by InfraLens. Details
CESMM4 · NRM 2 · POMI
CurrentFrequently UsedMethod of MeasurementBIMGeneral · Methods of Measurement of Works of Civil Engg.
PDFGoogleCompareBIS Portal
Link points to Internet Archive / others. Not hosted by InfraLens. Details
OverviewValues7InternationalEngineer's NotesTablesFAQ4Related

IS 1200:2000 (Part 1) is the Indian Standard (BIS) for methods of measurement of building and civil engineering works, part 1: earthwork. IS 1200 Part 1 establishes the standard rules and procedures for measuring earthwork quantities in civil engineering projects. It is a critical reference used by quantity surveyors, cost estimators, and civil engineers for preparing bills of quantities (BOQ), standardizing contractor billing, and avoiding measurement disputes.

Methods of measurement of building and civil engineering works, Part 1: Earthwork

Overview

Status
Current
Usage level
Frequently Used
Domain
General — Methods of Measurement of Works of Civil Engg.
Type
Method of Measurement
International equivalents
CESMM4 · ICE (UK)NRM 2 · RICS (UK)POMI · RICS (International)
Also on InfraLens for IS 1200
7Key values1Handbook topics4Knowledge articles4FAQs

BIM-relevant code. See the BIM Hub for ISO 19650, IFC, and LOD/LOIN frameworks used alongside it.

Practical Notes
! A common mistake is measuring door frames (chowkhats) in square meters or running meters; IS 1200 requires them to be measured in cubic meters (m³).
! Shutters for doors and windows must be measured in square meters (m²) separately from their frames.
! Hardware and fittings (like hinges, tower bolts, handles) are usually enumerated (measured in numbers) and billed separately unless the item description explicitly states they are included.
! Unlike standard linear measurements taken to the nearest 10 mm (0.01 m), the thickness of timber boards and scantlings is measured to the nearest 2 mm.
Frequently referenced clauses
Cl. 2General Rules for MeasurementCl. 3Measurement of Woodwork (Frames)Cl. 4Measurement of Joinery (Shutters, Partitions)Cl. 5Measurement of Architraves, Skirtings and Mouldings
Pulled from IS 1200:2000. Browse the full clause & table index below in Tables & Referenced Sections.
soilrockearth

Engineer's Notes

In Practice — Editorial Commentary
When IS 1200 Part 1 is your governing code

IS 1200 (Part 1) specifies the methods of measurement of building and civil engineering works — earthwork. The IS 1200 multi-part series is the foundational reference for measuring quantities of construction work for billing, BOQ preparation, and project cost estimation in India. Part 1 specifically covers earthwork (cut, fill, excavation, embankment).

Use IS 1200 Part 1 for: - BOQ preparation for any earthwork-heavy project (highways, dams, building basements) - Bill verification + measurement at site - Contract claim resolution (extra work, variation orders) - Tender quantity reconciliation - Standard measurement protocol for quantity surveyors

IS 1200 has multiple Parts covering different work categories: - Part 1: Earthwork (this code) - Part 2: Concrete work - Part 3: Brickwork - Part 4: Stone work - Part 5: Form-work - Part 6: Refractory work - Part 7: Hardware - Part 8: Plastering and pointing - Part 9: Roof covering - Part 10: Ceiling and lining - Part 11: Paving, floor finishing, dado, skirting - Part 12: Plumbing - Part 13: White washing, colour washing, distempering, painting of buildings - Part 14: Painting of metal works - Part 15: Painting of woodwork - Part 16-29: more specialised measurements

For public works contracts (PWD, NHAI, MoRTH, MES, Railways), the IS 1200 series is the agreed measurement standard — disputes over quantities are resolved by reference to Part X of IS 1200.

Earthwork measurement principles

General principles: - Volume by Cross-section method: average area × length of work - For long works (highway, canal): cross-sections at 100 m or per change of ground - For local works (foundation pit): direct dimension measurement - Volume in m³ (commonly cubic metre) or m² × depth

Categories of earthwork measured: - Excavation in earth (loose, ordinary, dense, hard) - Excavation in soft rock / hard rock (separate rates) - Filling (return fill from cut, borrow fill, embankment) - Spreading + dressing of excavated material - Compaction (separate item OR included in fill — per contract) - Disposal of surplus (lead distance + lift) - Dewatering (separate item if specified)

Classification of soil for excavation: - Loose / ordinary soil: sandy / gravelly soil, easy to dig with shovel - Hard / dense soil / murrum: requires pickaxe + spade - Soft rock: weathered / loose rock; can be dug with crowbar / chisel - Hard rock requiring blasting: rock that needs explosives - Hard rock not requiring blasting: rock that can be removed by chiselling, wedging

Different rates per soil class (per State SOR / contract).

Lead + lift: - Lead: horizontal distance of disposal from excavation; usually paid in 30 m / 50 m / 100 m increments - Lift: vertical distance for raising material above natural ground; paid per metre or per stage - Standard rates assume lead = 30-50 m; extra lead paid separately

Initial vs final levels: - Pre-work survey: original ground level (OGL) - Post-work survey: finished ground level (FGL) - Volume = (OGL − FGL) × area for cut; reverse for fill

Reference values you'll actually use

Earthwork measurement units:

| Item | Unit | |---|---| | Excavation in soil | m³ | | Excavation in rock | m³ | | Filling (compacted) | m³ | | Dressing of surfaces | m² | | Lead | m³ × 30 m unit (extra over 50 m) | | Lift | m³ × m vertical | | Disposal | m³ | | Dewatering | per HP × hour OR lump-sum |

Earthwork shrinkage / swell factors: - Soft / loose soil: 10-15 % shrinkage from loose to compacted (i.e., 1.15 m³ loose = 1 m³ compacted) - Cohesive (clay) soil: 15-25 % shrinkage - Rock fill: 10-20 % swell from in-situ to broken (1 m³ rock in-place = 1.15-1.25 m³ broken)

Typical bid rates (for reference, varies by region + year): - Excavation in ordinary soil: ₹150-300 per m³ - Excavation in hard rock (blasting): ₹500-1500 per m³ - Embankment fill (selected granular): ₹250-450 per m³ - Lead 50-100 m (extra): ₹50-100 per m³ - Compaction at 95-98 % MDD: ₹50-150 per m³

For highway / NHAI contracts: - MoRTH Specifications for Road and Bridge Works (5th Revision) Section 300 — earthwork specifications align with IS 1200 Part 1 for measurement - State PWD SOR — uses IS 1200 measurement methodology

Cross-section spacing: - Highway: 100 m (less in cuttings / fillings) - Canal: 50 m - Railway: 100 m - Building footprint: per pit dimensions (for rectangular)

Sample measurement record:

| Chainage | OGL (m) | FGL (m) | Cut depth (m) | Cross-section area | Length (m) | Volume (m³) | |---|---|---|---|---|---|---| | 0+000 | 102.50 | 100.00 | 2.50 | A1 = 25 m² | — | — | | 0+100 | 103.00 | 100.50 | 2.50 | A2 = 30 m² | 100 | (A1+A2)/2 × 100 = 2750 m³ | | ... | ... | ... | ... | ... | ... | ... |

Pit / footing measurement: - Length × width × depth (rectangular) - For battered sides: average between top + bottom dimensions × depth - Round columns: π × r² × depth

Companion codes (must pair with)
  • IS 1200 Part 2-29 — measurement methods for other work categories (concrete, brickwork, plaster, etc.).
  • IRC:36:2010 — earth embankment construction (defines earthwork practice).
  • IS 2720 series — soil testing methods.
  • IS 2720 Part 7 / 8 — Proctor compaction.
  • IS 1080:1985 — design of shallow foundations.
  • IS 4081 — code of safety for blasting in mines and quarries.
  • IS 1129 — recommendation for dressing of natural building stones.
  • Indian Railways General Conditions of Contract (GCC) — use IS 1200 Part 1 for earthwork measurement.
  • MoRTH Specifications for Road and Bridge Works (5th Revision).
  • NHAI Standard Bid Document — measurement per IS 1200.
  • State PWD SOR (Schedule of Rates) — built on IS 1200 measurement methodology.
  • CPWD Schedule of Rates — uses IS 1200 measurement.
  • Indian Standard Practice for Quantity Surveying (separate practice document).
Common pitfalls / what reviewers flag

1. Disagreement on soil class at site. Soil classification (loose/hard/rock) is contractor-vs-client subjective; rates differ 3-5×. Document with photo + supervisor sign-off at each soil change. 2. Lead distance over-claimed. Contractor claims long leads; client disputes. Mark spoil dump area on alignment plan; measure actual hauled distance. 3. No before-and-after surveys. Quantities computed from drawings, not actual ground; client / contractor each stake claims. Demand pre-work + post-work survey. 4. Measurement of compacted vs loose volume confused. Contractor measures loose (more); pays compacted (less). Apply shrinkage factor per soil class. 5. Disposal vs spread. Spreading on site (no disposal cost) vs disposal off-site (with lead) — confused; client disputes. Document. 6. Dewatering costs not measured separately. Contractor includes in unit rate; client argues separate. Specify in BOQ as separate item if known to be needed. 7. Rock excavation classification. 'Hard rock requiring blasting' vs 'hard rock not requiring blasting' has 30-50 % rate difference. Geological survey before excavation; document type. 8. Cross-section spacing too coarse. 200 m spacing on undulating terrain misses pockets of cut/fill; quantity wrong by 20 %. Use 100 m spacing in variable terrain. 9. No deduction for backfill within excavation. Foundation pit excavated 100 m³, backfilled 50 m³ around foundation; net 50 m³ surplus. Specify net measurement. 10. Borrow material + return fill not differentiated. Different rates apply (borrow includes haul; return fill from cut is cheaper). Specify. 11. No standard for 'extra over' rates. Lead beyond standard, vibration compaction, soil stabilisation — each needs explicit rate. Schedule of unit rates required. 12. Dispute resolution clause vague. When measurement disputed, who decides? Reference IS 1200 Part 1 + arbitration clause.

Where it sits in project measurement

Quantity surveying cascade:

1. BOQ preparation: - Designer + QS works through drawings + specifications - Quantities per IS 1200 Part 1 (earthwork) + Parts 2+ (other) - Unit rates per State SOR / project market rates - Total project cost estimate 2. Tender + award — contractor bids on quantities × rates. 3. Site execution: - Pre-work survey for OGL - Daily / weekly progress measurement (contractor + client representative joint check) - Volumes computed from cross-sections (highway / canal) OR direct (building pit) - Soil classification recorded with photo + sign-off 4. Bill submission + verification: - Contractor submits monthly bill: quantity × rate - Client QS verifies measurement against IS 1200 Part 1 - Variations from BOQ noted (extra work / less work) 5. Variation orders — for changes from original scope; rates per BOQ or new rate negotiation. 6. Final bill — total work done × agreed rates. 7. Defect-liability period — final bill held back; released after DLP.

Typical earthwork project elements: - Highway: 60-80 % of total contract value can be earthwork (especially in hilly / cut sections) - Canal / dam: 50-70 % earthwork - Building basement: 5-15 % of contract value - Foundation: 2-5 % of contract value

Given earthwork's share of contract value, accurate measurement per IS 1200 Part 1 directly affects project economics. Disputes over earthwork quantities are the #1 source of construction litigation in India.

International Equivalents

Similar International Standards
CESMM4ICE (UK)
HighCurrent
Civil Engineering Standard Method of Measurement, Fourth Edition
Defines measurement rules for civil engineering, with comprehensive coverage of earthworks.
NRM 2RICS (UK)
HighCurrent
New Rules of Measurement 2: Detailed measurement for building works
Provides detailed rules for measuring building works, including excavation and filling sections.
SMM7RICS (UK)
HighWithdrawn
Standard Method of Measurement of Building Works, Seventh Edition
Historically a direct parallel, it defined measurement principles for building works including earthworks.
POMIRICS (International)
MediumCurrent
Principles of Measurement (International) for Works of Construction
A high-level framework of principles for measurement, rather than a detailed rulebook like IS 1200.
Key Differences
≠IS 1200 specifies a standard 'lead' (horizontal transport) of 30m and 'lift' (vertical transport) of 1.5m included in the basic excavation rate. International standards like CESMM4 do not include a standard lead/lift; haulage is measured separately based on distance bands or using mass haul diagrams.
≠IS 1200 provides a detailed soil classification for payment (Soft Soil, Hard Soil, Mud, Soft Rock, Hard Rock). CESMM4 simplifies this, often measuring excavation broadly and having separate items only for 'rock' or other specified hard materials, with the definition of rock being project-specific.
≠IS 1200 provides a prescriptive allowance for 'working space' (e.g., 60 cm around foundations) which is measurable for payment. In NRM2 and CESMM4, working space is generally deemed to be included in the contractor's rates unless it is of such a magnitude that it needs to be specifically measured and described.
≠The measurement system in the USA is not nationally standardized like in India or the UK. Measurement for payment is typically governed by individual state Department of Transportation (DOT) specifications or defined per project, often referencing CSI MasterFormat for classification rather than a detailed method of measurement.
Key Similarities
≈All standards are based on the principle of measuring the net quantity of work from finished drawings. No allowance is made for the contractor's temporary works, over-excavation, or construction methods unless specifically stated.
≈The primary unit of measurement for bulk excavation, backfilling, and disposal is the cubic metre (m³) across IS 1200, CESMM4, and NRM2.
≈Measurement of filling is consistently based on the final compacted volume within the specified dimensions, not the loose volume of material transported to the site.
≈Surface treatments, such as trimming excavation faces, preparing surfaces to receive concrete, or topsoiling and turfing, are measured separately by area (in square metres, m²) in all comparable standards.
Parameter Comparison
ParameterIS ValueInternationalSource
Standard Lead in Base Rate30 metres included in excavation item.Not applicable. Haulage is measured separately from excavation.CESMM4
Standard Lift in Base Rate1.5 metres included in excavation item.Not applicable. Excavation is often measured in depth ranges (e.g., 0-2m, 2-4m).CESMM4
Bulk Excavation UnitCubic Metre (m³)Cubic Metre (m³)CESMM4 / NRM 2
Surface Dressing UnitSquare Metre (m²)Square Metre (m²)NRM 2
Deduction for Voids (e.g., pipes)No deduction for voids up to 0.1 m² in cross-section.Deductions made for voids > 0.05 m³ in volume (not cross-section).NRM 2
Measurement of ExcavationNet dimensions of the final void created.Net dimensions of the final void created.CESMM4
Measurement of FillingNet volume of the space to be filled (final compacted volume).Net volume of the space to be filled (final compacted volume).NRM 2
⚠ Verify details from original standards before use

Key Values7

Quick Reference Values
length measurement toleranceNearest 0.01 m
thickness measurement tolerance for boardsNearest 0.002 m (2 mm)
area measurement toleranceNearest 0.01 m²
volume measurement toleranceNearest 0.01 m³
woodwork frames measurement unitCubic meters (m³)
door window shutters measurement unitSquare meters (m²)
mouldings and skirting measurement unitRunning meters (m)

Tables & Referenced Sections

Key Tables
No tables data
Key Clauses
Clause 2 - General Rules for Measurement
Clause 3 - Measurement of Woodwork (Frames)
Clause 4 - Measurement of Joinery (Shutters, Partitions)
Clause 5 - Measurement of Architraves, Skirtings and Mouldings

Related Resources on InfraLens

Handbook & Design Rules
Handbook Topics
📖Excavation Rates & Quantities
→
Articles & Guides
📖Construction Cost Per Square Foot in India (2026 Guide)
→
📖Rate Analysis in Civil Engineering
→
📖Schedule of Rates India — Complete Guide
→
📖How to Read a Schedule of Rates
→
Key terms in IS 1200
📘Detailed Estimate
→
📘Abstract Estimate
→
📘Bill of Quantities (BOQ)
→
📚Full civil-engineering glossary
→
🧮
Mix Design Calculator
IS 10262 · M20–M50

Frequently Asked Questions4

How are wooden door and window frames (chowkhats) measured?+
They are measured in cubic meters (m³) by calculating the total length of the frame sections multiplied by their cross-sectional area.
What is the unit of measurement for door and window shutters?+
Shutters are measured in square meters (m²) based on their overall width and height.
How is the thickness of wooden boards measured according to this code?+
The thickness of boards and scantlings is measured to the nearest 2 mm (0.002 m).
How are wooden architraves, picture rails, and skirtings measured?+
They are measured in running meters (linear meters), stating the cross-sectional dimensions in the description.

QA/QC Inspection Templates

📋
QA/QC templates coming soon for this code.
Browse all 300 templates →