All BOQ templates

Toilet Block (1 / 2 / 4-seat SBM-G)

Community or institutional toilet block per SBM-G + Swachh Vidyalaya specifications. Brick masonry shell with RCC roof slab, plaster + paint, tile flooring, Orissa-pattern WC pans, wash basins. Septic tank + soak pit downstream (separate templates). Rates: CPWD DSR Vol 1 + Vol 2 (2023).

Visual confirmation
Plan · 2-seat, 2.5 × 1.5 m
WCWCWB2.96 m1.96 mBrick wall 230 mmTile flooring
Front elevation · 2-seat block, 2.7 m height
2.96 m2.7 mNGL
Section · 1.5 m × 2.7 m
WC1.5 m2.7 mNGL
Bill of Quantities18 items · CPWD DSR Vol 1 + Vol 2 (2023)
#CodeDescriptionUnitQtyRate (₹)Amount (₹)
12.8.1ExcavationEarth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, for all lift, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. — All kinds of soil.Cum4.05260.301,054.21
24.1.10Pcc BedProviding and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : — 1:5:10 (1 cement : 5 coarse sand (zone-III) derived from natural sources : 10 graded stone aggregate 40 mm nominal size derived from natural sources)Cum0.666,518.604,302.28
36.1.2Brick FoundBrick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in foundation and plinth in: — Cement mortar 1:6 (1 cement : 6 coarse sand)Cum1.547,132.2510,983.67
44.10DpcProviding and laying damp-proof course 40 mm thick with cement concrete 1:2:4 (1 cement : 2 coarse sand (zone-III) derived from natural sources : 4 graded stone aggregate 12.5 mm nominal size derived from natural sources)Sqm2.05410.85842.24
56.4.2Brick AboveBrick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in superstructure above plinth level up to floor V level in all shapes and sizes in : — Cement mortar 1:6 (1 cement : 6 coarse sand)Cum5.549,105.9550,446.96
65.3Rcc RoofReinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources).Cum0.7311,505.508,399.02
75.9.3Shutter RoofCentering and shuttering including strutting, propping etc. and removal of form for — Suspended floors, roofs, landings, balconies and access platformSqm5.80927.255,378.05
85.22.6SteelSteel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. — Thermo-Mechanically Treated bars of grade Fe-500D or more.Kg72.52107.857,821.28
913.1.2Plaster Int12 mm cement plaster of mix : — 1:6 (1 cement: 6 fine sand)Sqm21.60333.357,200.36
1013.5.2Plaster Ext15 mm cement plaster on rough side of single or half brick wall of mix: — 1:6 (1 cement: 6 coarse sand)Sqm29.52395.3511,670.73
1113.41.1Distemper IntDistempering with 1st quality acrylic distemper (ready mixed) having VOC content less than 50 gram/litre, of approved manufacturer and of required shade and colour all complete to achieve even shade and colour : — New work (two or more coats) over and including water thinnable priming coat with cement primer having VOC content less than 50 gram/litreSqm21.60185.654,010.04
1213.46.1Paint ExtFinishing walls with Acrylic Smooth exterior paint of required shade : — New work (Two or more coat applied @ 1.67 ltr/10 sqm over and including priming coat of exterior primer applied @ 0.90 litre/10 sqm)Sqm29.52160.604,740.91
1317.1.1Wc PanProviding and fixing water closet squatting pan (Indian type W.C. pan ) with 100 mm sand cast Iron P or S trap, 10 litre low level white P.V.C. flushing cistern, including flush pipe, with manually controlled device (handle lever) conforming to IS : 7231, with all fittings and fixtures complete, including cutting and making good the walls and floors wherever required: — White Vitreous china Orissa pattern W.C. pan of size 580x440 mm with integral type foot restsEach2.006,767.4013,534.80
1417.7.4Wash BasinProviding and fixing wash basin with C.I. brackets, 15 mm C.P. brass pillar taps, 32 mm C.P. brass waste of standard pattern, including painting of fittings and brackets, cutting and making good the walls wherever require: — White Vitreous China Flat back wash basin size 550x 400 mm with single 15 mm C.P. brass pillar tapEach1.001,879.201,879.20
1519.6.1Sewer PipeProviding and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete : — 100 mm dia. R.C.C. pipeMetre6.00507.053,042.30
169.5.1.1Flush DoorsProviding and fixing panelled or panelled and glazed shutters for doors, windows and clerestory windows, fixing with butt hinges of required size with necessary screws, excluding panelling which will be paid for separately, all complete as per direction of Engineer-in-charge. (Note: Butt hinges and necessary screws shall be paid separately) — Second class teak wood — 35 mm thick shuttersSqm3.364,111.9513,816.15
1710.31Window FramesProviding and fixing angle iron frames for doors, windows and ventilators of mild steel Angle sections of size 35x35x5 mm, joints mitred and welded by angle iron 35x35x5 mm or 35x 5 mm flat pieces to the existing T-iron frame or to the wall with dash fastener, including fixing of necessary butt hinges and screws and applying a priming coat of approved steel primer, all complete as per the direction of Engineer-In-charge.Kg16.00130.502,088.00
1811.39Tile FloorProviding and laying rectified Glazed Ceramic floor tiles of size 300x300 mm or more (thickness to be specified by the manufacturer), of 1st quality conforming to IS : 15622, of approved make, in colours White, Ivory, Grey, Fume Red Brown, laid on 20 mm thick cement mortar 1:4 (1 Cement: 4 Coarse sand), jointing with grey cement slurry @ 3.3 kg/ sqm including grouting the joints with white cement and matching pigments etc., complete.Sqm3.751,330.004,987.50
Your inputsWC seats 2-seat · int. length 2.5 m · int. width 1.5 m · int. height 2.7 m · Wall thk 230 mm · Wash basin · Plaster + interior distemper + exterior paint · Flush doors per cubicle · Ventilator window per cubicle · Anti-skid ceramic tile flooringTOTAL₹1,56,198
12.8.1₹1,054
Excavation
Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, for all lift, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. — All kinds of soil.
4.05 Cum× ₹260.30
24.1.10₹4,302
Pcc Bed
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : — 1:5:10 (1 cement : 5 coarse sand (zone-III) derived from natural sources : 10 graded stone aggregate 40 mm nominal size derived from natural sources)
0.66 Cum× ₹6,518.60
36.1.2₹10,984
Brick Found
Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in foundation and plinth in: — Cement mortar 1:6 (1 cement : 6 coarse sand)
1.54 Cum× ₹7,132.25
44.10₹842
Dpc
Providing and laying damp-proof course 40 mm thick with cement concrete 1:2:4 (1 cement : 2 coarse sand (zone-III) derived from natural sources : 4 graded stone aggregate 12.5 mm nominal size derived from natural sources)
2.05 Sqm× ₹410.85
56.4.2₹50,447
Brick Above
Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in superstructure above plinth level up to floor V level in all shapes and sizes in : — Cement mortar 1:6 (1 cement : 6 coarse sand)
5.54 Cum× ₹9,105.95
65.3₹8,399
Rcc Roof
Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources).
0.73 Cum× ₹11,505.50
75.9.3₹5,378
Shutter Roof
Centering and shuttering including strutting, propping etc. and removal of form for — Suspended floors, roofs, landings, balconies and access platform
5.80 Sqm× ₹927.25
85.22.6₹7,821
Steel
Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. — Thermo-Mechanically Treated bars of grade Fe-500D or more.
72.52 Kg× ₹107.85
913.1.2₹7,200
Plaster Int
12 mm cement plaster of mix : — 1:6 (1 cement: 6 fine sand)
21.60 Sqm× ₹333.35
1013.5.2₹11,671
Plaster Ext
15 mm cement plaster on rough side of single or half brick wall of mix: — 1:6 (1 cement: 6 coarse sand)
29.52 Sqm× ₹395.35
1113.41.1₹4,010
Distemper Int
Distempering with 1st quality acrylic distemper (ready mixed) having VOC content less than 50 gram/litre, of approved manufacturer and of required shade and colour all complete to achieve even shade and colour : — New work (two or more coats) over and including water thinnable priming coat with cement primer having VOC content less than 50 gram/litre
21.60 Sqm× ₹185.65
1213.46.1₹4,741
Paint Ext
Finishing walls with Acrylic Smooth exterior paint of required shade : — New work (Two or more coat applied @ 1.67 ltr/10 sqm over and including priming coat of exterior primer applied @ 0.90 litre/10 sqm)
29.52 Sqm× ₹160.60
1317.1.1₹13,535
Wc Pan
Providing and fixing water closet squatting pan (Indian type W.C. pan ) with 100 mm sand cast Iron P or S trap, 10 litre low level white P.V.C. flushing cistern, including flush pipe, with manually controlled device (handle lever) conforming to IS : 7231, with all fittings and fixtures complete, including cutting and making good the walls and floors wherever required: — White Vitreous china Orissa pattern W.C. pan of size 580x440 mm with integral type foot rests
2.00 Each× ₹6,767.40
1417.7.4₹1,879
Wash Basin
Providing and fixing wash basin with C.I. brackets, 15 mm C.P. brass pillar taps, 32 mm C.P. brass waste of standard pattern, including painting of fittings and brackets, cutting and making good the walls wherever require: — White Vitreous China Flat back wash basin size 550x 400 mm with single 15 mm C.P. brass pillar tap
1.00 Each× ₹1,879.20
1519.6.1₹3,042
Sewer Pipe
Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete : — 100 mm dia. R.C.C. pipe
6.00 Metre× ₹507.05
169.5.1.1₹13,816
Flush Doors
Providing and fixing panelled or panelled and glazed shutters for doors, windows and clerestory windows, fixing with butt hinges of required size with necessary screws, excluding panelling which will be paid for separately, all complete as per direction of Engineer-in-charge. (Note: Butt hinges and necessary screws shall be paid separately) — Second class teak wood — 35 mm thick shutters
3.36 Sqm× ₹4,111.95
1710.31₹2,088
Window Frames
Providing and fixing angle iron frames for doors, windows and ventilators of mild steel Angle sections of size 35x35x5 mm, joints mitred and welded by angle iron 35x35x5 mm or 35x 5 mm flat pieces to the existing T-iron frame or to the wall with dash fastener, including fixing of necessary butt hinges and screws and applying a priming coat of approved steel primer, all complete as per the direction of Engineer-In-charge.
16.00 Kg× ₹130.50
1811.39₹4,988
Tile Floor
Providing and laying rectified Glazed Ceramic floor tiles of size 300x300 mm or more (thickness to be specified by the manufacturer), of 1st quality conforming to IS : 15622, of approved make, in colours White, Ivory, Grey, Fume Red Brown, laid on 20 mm thick cement mortar 1:4 (1 Cement: 4 Coarse sand), jointing with grey cement slurry @ 3.3 kg/ sqm including grouting the joints with white cement and matching pigments etc., complete.
3.75 Sqm× ₹1,330.00
WC seats 2-seat · int. length 2.5 m · int. width 1.5 m · int. height 2.7 m · Wall thk 230 mm · Wash basin · Plaster + interior distemper + exterior paint · Flush doors per cubicle · Ventilator window per cubicle · Anti-skid ceramic tile flooring
Estimated total
₹1,56,198
Notes & assumptions
  • Default internal dimensions match SBM-G + Swachh Vidyalaya layout: 1 m² floor per WC + 0.5 m circulation. For more spacious cubicles or wheelchair-accessible toilets, override dimensions manually.
  • Wash basins quantity = ceil(n_seats / 4) — one basin per 4 seats per CPWD school sanitation standard. Toggle off for very basic SBM-G individual household toilets.
  • Sewer pipe quantity = 3 m × n_seats — covers WC connection + branch + main runs from the toilet block to the septic tank inspection chamber. Use [Septic Tank](/boq/septic-tank) template downstream.
  • Roof slab is 125 mm RCC with 8 mm bars @ 150 mm c/c — adequate for spans up to 2.5 m. For larger spans, increase to 150 mm + 110 kg/m³ steel.
  • Excludes: doors (typically FRP / steel-louvred ~₹4,000 each), windows / ventilators (₹2,000-3,000 each), tile flooring with skirting (₹600-900/m² installed), partition walls between WC cubicles (~₹3,000 per cubicle), water tank on roof (PVC 500 litre ~₹4,000), electrical wiring + light fitting (~₹1,500 per cubicle), septic tank + soak pit downstream — quote those separately.

**Toilet blocks** are the universal sanitation infrastructure in India — every village under SBM-G, every government school under Swachh Vidyalaya, every PHC + Anganwadi under ICDS, every PMGSY road sees a public toilet block. The CPWD / SBM-G standard is a brick-masonry shell with RCC roof slab, internal cement plaster + distemper, exterior weatherproof paint, vitreous-china Orissa-pattern WC pans, wash basins (1 per 4 seats), and sewer pipes connected to an external septic tank + soak pit. This BOQ Builder generates the complete shell + fittings cost per CPWD DSR 2023 for 1/2/4/6/8-seat configurations.

Why a toilet block isn't just a small building — it's a *system*

A working toilet block needs FOUR components: (1) the **shell** (this BOQ — masonry + roof + plaster + paint + floor + fittings); (2) **water supply** (overhead tank + plumbing + taps); (3) **drainage** (sewer pipes + inspection chamber + septic tank + soak pit); (4) **electrical** (lighting + ventilation fan). This Builder covers the shell + WC pans + wash basins + sewer connection-pipes — typically 60-70% of total cost. The other 30-40% (water supply, drainage downstream, electrical) is quoted separately by respective trades. Most SBM-G individual household toilet tenders are for the shell only; community toilet blocks tender all four components together as a single package.

Common gotchas in toilet-block estimates

Five items routinely under-budgeted: (1) **Doors** — FRP / steel-louvred doors are ₹3,500-5,500 each installed; with 2 doors per cubicle (entrance + WC), a 4-seat block needs 8 doors = ₹35-45k. (2) **Tile flooring** — anti-skid ceramic tiles + skirting tiles cost ₹600-900/m² installed; cheaper than IPS but mandatory for SBM-G + Swachh Vidyalaya. (3) **Partition walls** between WC cubicles — half-brick partition (DSR 6.12.2 at ₹905/m²) costs ₹3,000-4,500 per cubicle in materials. (4) **Water supply** — even a basic 500-litre PVC tank with plumbing costs ₹8,000-12,000 per block. (5) **Septic tank + soak pit downstream** — almost universally needed in non-sewered locations; add ~₹40-80k for a 10-user septic + soak pit combo.

Frequently asked questions
Using CPWD DSR 2023 for the shell + 2 WC pans + 1 wash basin + sewer pipes: approximately ₹1.2-1.5 lakh. Adding doors (4 nos × ₹4,500 ≈ ₹18k), tile flooring (~₹3k for 4 m²), partition wall (~₹3,500), water supply (~₹10k), septic tank + soak pit downstream (~₹60k): full operational toilet block ≈ ₹2.6-3.0 lakh. SBM-G community toilet incentive is ₹2.1 lakh per block (12-seat); per-seat is ~₹17,500. For schools, Swachh Vidyalaya allocation is around ₹35,000-50,000 per cubicle.

More related

Disclaimer: Rates sourced from CPWD DSR Vol 1 + Vol 2 (2023). Indicative for estimation only — actual tender quotations are governed by market forces, locality factors and current input prices. Quantities follow IS 1200 measurement. Always verify with a local quote before finalising. © InfraLens — infralens.in