Test-report · QC-SRV-TST-001
Cone Penetration Test Report
16 checkpoints across 5 sections. During geotechnical site investigation; foundation design phase
16 Checkpoints
5 Sections
Multiple tests per project at different locations
Geotechnical Engineer, Foundation Designer

Checklist Preview

S.No.CheckpointIS RequirementStatus
A. CPT EQUIPMENT AND CALIBRATION
A1Cone penetrometer calibration and certification
Acceptance: Equipment calibrated within 6 months; cone area verified; friction sleeve area confirmed
Cl. 3.1 — Equipment accuracy
A2Load cell verification and zero check
Acceptance: Load cells tested; zero reading verified; calibration certificate available; drift ≤ 2%
Cl. 3.2 — Measurement accuracy
A3Penetration rate and procedure
Acceptance: Rate = 20 ± 5 mm/sec per IS; continuous penetration; no pauses; recorded with time
Cl. 3.3 — Test standardization
B. CPT MEASUREMENTS AND DATA COLLECTION
B1Cone resistance (qc) measurement
Acceptance: Measured at 0.1 m intervals; averaged over 0.2 m; unit: MPa or kPa; recorded digitally
Cl. 4.1 — Tip resistance
B2Sleeve friction (fs) measurement
Acceptance: Measured continuously; unit: kPa; friction ratio (Rf) calculated; checked for anomalies
Cl. 4.2 — Shaft friction
B3Excess pore pressure (u) measurement (Piezocone)
Acceptance: Pore pressure measured at cone tip; saturated clay shows excess pressure; dissipation test if required
Cl. 4.3 — Pore pressure response
B4Data quality and signal integrity
Acceptance: Data downloaded from penetrometer; no signal loss; gaps identified; spikes checked and removed
Cl. 4.4 — Data validation
C. SOIL CLASSIFICATION AND INTERPRETATION
C1Soil type identification from CPT data
Acceptance: Soil type chart applied; classification zones identified; soil behavior type (SBT) determined
Cl. 5.1 — Classification per charts
C2Layer identification and boundaries
Acceptance: Transitions between layers marked; layer thickness measured; comparison with borehole log
Cl. 5.2 — Stratum determination
C3Relative density (for granular soils)
Acceptance: Relative density calculated from qc; loose/medium/dense ranges identified; correlated with SPT N
Cl. 5.3 — Sand density assessment
Showing 10 of 16 checkpoints ·
A. CPT EQUIPMENT AND CALIBRATION
A1Cone penetrometer calibration and certification
Cl. 3.1 — Equipment accuracy (IS 1892)
Equipment calibrated within 6 months; cone area verified; friction sleeve area confirmed
A2Load cell verification and zero check
Cl. 3.2 — Measurement accuracy (IS 1892)
Load cells tested; zero reading verified; calibration certificate available; drift ≤ 2%
A3Penetration rate and procedure
Cl. 3.3 — Test standardization (IS 1892)
Rate = 20 ± 5 mm/sec per IS; continuous penetration; no pauses; recorded with time
B. CPT MEASUREMENTS AND DATA COLLECTION
B1Cone resistance (qc) measurement
Cl. 4.1 — Tip resistance (IS 1892)
Measured at 0.1 m intervals; averaged over 0.2 m; unit: MPa or kPa; recorded digitally
B2Sleeve friction (fs) measurement
Cl. 4.2 — Shaft friction (IS 1892)
Measured continuously; unit: kPa; friction ratio (Rf) calculated; checked for anomalies
B3Excess pore pressure (u) measurement (Piezocone)
Cl. 4.3 — Pore pressure response (IS 1892)
Pore pressure measured at cone tip; saturated clay shows excess pressure; dissipation test if required
B4Data quality and signal integrity
Cl. 4.4 — Data validation (IS 1892)
Data downloaded from penetrometer; no signal loss; gaps identified; spikes checked and removed
C. SOIL CLASSIFICATION AND INTERPRETATION
C1Soil type identification from CPT data
Cl. 5.1 — Classification per charts (IS 1892)
Soil type chart applied; classification zones identified; soil behavior type (SBT) determined
C2Layer identification and boundaries
Cl. 5.2 — Stratum determination (IS 1892)
Transitions between layers marked; layer thickness measured; comparison with borehole log
C3Relative density (for granular soils)
Cl. 5.3 — Sand density assessment (IS 1892)
Relative density calculated from qc; loose/medium/dense ranges identified; correlated with SPT N
Showing 10 of 16 ·
Inspection Sign-Off
APPROVED
APPROVED WITH CONDITIONS
REJECTED
Test Summary
Name / Sign / Date
Key Findings
Name / Sign / Date
Soil Profile Description
Name / Sign / Date
Interpretation and Recommendations
Name / Sign / Date
Tested By
Name / Sign / Date
Reviewed By
Name / Sign / Date