HandbookMaterial Quantities per Unit of Work

Material Quantities per Unit of Work

IS 2185, IS 1077, IS 10262 · Standard practice — derived from nominal mix ratios and material properties
Ready-reckoner for material quantities in common construction activities. Includes dry volume conversion factor (1.52–1.54) for concrete, mortar consumption for masonry and plastering.
IS 2185Try Material Estimator
29 items shown
Concrete — per m³ (wet volume)
Dry volume = 1.52 × wet volume. 1 bag cement = 50 kg = 0.035 m³
Work ItemCementSandAggregateOther
M10 (1:3:6) — PCC4.2 bags (210 kg)0.44 m³ (680 kg)0.88 m³ (1410 kg)
M15 (1:2:4) — PCC/Lean RCC6.3 bags (315 kg)0.44 m³ (680 kg)0.88 m³ (1410 kg)
M20 (1:1.5:3) — RCC8.0 bags (400 kg)0.42 m³ (650 kg)0.84 m³ (1340 kg)
M25 (1:1:2) — RCC10.8 bags (540 kg)0.38 m³ (590 kg)0.76 m³ (1220 kg)
Brickwork — per m³
Standard brick: 230×115×75mm. With 10mm mortar joints.
Work ItemCementSandAggregateOther
Brick masonry (CM 1:6)1.3 bags (63 kg)0.27 m³500 bricks
Brick masonry (CM 1:4)1.8 bags (90 kg)0.25 m³500 bricks
Brick masonry (CM 1:3)2.2 bags (110 kg)0.23 m³500 bricks
Half-brick wall per m² (115mm thick)0.6 bags (30 kg)0.02 m³58 bricks
One-brick wall per m² (230mm thick)1.2 bags (60 kg)0.04 m³117 bricks
Plastering — per m² (single coat)
Dry volume factor = 1.33 for mortar.
Work ItemCementSandAggregateOther
12mm thick (CM 1:6) — interior0.16 bags (8 kg)0.012 m³
12mm thick (CM 1:4) — exterior0.22 bags (11 kg)0.011 m³
15mm thick (CM 1:6) — ceiling0.20 bags (10 kg)0.015 m³
20mm thick (CM 1:4) — exterior0.36 bags (18 kg)0.018 m³
Two-coat: 12mm base + 8mm neat0.35 bags (17 kg)0.012 m³
Flooring — per m²
Work ItemCementSandAggregateOther
PCC bed 75mm (1:2:4)0.47 bags (24 kg)0.033 m³0.066 m³
PCC bed 100mm (1:2:4)0.63 bags (32 kg)0.044 m³0.088 m³
Tile fixing (CM 1:4, 20mm bed)0.30 bags (15 kg)0.015 m³
IPS Flooring 40mm (1:2:4)0.26 bags (13 kg)0.018 m³0.035 m³
Painting — per 100 m²
Two coats unless noted otherwise.
Work ItemCementSandAggregateOther
Wall putty (2 coats)100–140 kg putty
Cement primer (1 coat)10–12 L primer
Emulsion paint (2 coats)12–15 L paint
Enamel paint (2 coats — wood/metal)8–10 L paint
Whitewash (3 coats)5 kg lime
Thumb Rules — For a 1000 sqft (93 m²) House
Approximate values for G+1 residential construction.
Work ItemCementSandAggregateOther
Cement400–450 bags20–22.5 tonnes
Steel3.5–4.5 tonnes (3.5–4.5 kg/sqft)
Sand (river/M-sand)38–45 m³~2.5 truck loads
Aggregate (20mm)28–35 m³~2 truck loads
Bricks15,000–18,000 nos
WaterFor construction only
← Previous
Safe Bearing Capacity of Soils
Next →
Reinforcement Limits & Detailing Rules
Generated by InfraLens · infralens.in