InfraLensGATE PrepConstruction Materials & ManagementCPM, PERT & Project Management

CPM, PERT & Project Management MCQ for GATE Civil Engineering

509 Questions5 Difficulty Levels3-5% in GATEFree Practice

This topic is part of the GATE Civil Engineering syllabus. Master it through progressive practice — starting from basic recall at Level 1 and building up to GATE-level problems at Level 5.

Difficulty Levels

L1 · Foundation · 280 Qs
L2 · Understanding · 54 Qs
L3 · Application · 112 Qs
L4 · Analysis · 61 Qs
L5 · GATE Ready · 2 Qs
GATE Exam Tip: Focus on understanding concepts first, then practice numerical problems. Most GATE questions in this topic require applying 2-3 concepts together.

Practice Questions — Try 17 Samples

Select an answer and click "Check Answer" to see the explanation. For the full set of 509+ questions with progress tracking, use the interactive practice mode.

Q1 · Level 1 · CM-PMG-1086
Critical activities are characterized by having a total float that is:
Q2 · Level 1 · CM-PMG-1022
The duration at which the direct cost of an activity stops decreasing as time increases is termed:
Q3 · Level 1 · CM-PMG-1236
What is the acceptable tolerance for measuring areas in a detailed construction estimate?
Q4 · Level 2 · CM-PMG-1221
What is the approximate daily output of cement concrete (mix ratio 1:2:4) that a single mason can achieve in building construction?
Q5 · Level 2 · CM-PMG-1298
According to construction standards, what is the minimum acceptable width for a septic tank?
Q6 · Level 2 · CM-PMG-1245
As per IS standards for building measurement, what is the prescribed sequence for recording dimensions?
Q7 · Level 3 · CM-PMG-1212
For a highway embankment with a formation width of B, embankment height of d, and side slopes of S:1, assuming no transverse slope, what is the formula for the cross-sectional area?
Q8 · Level 3 · CM-PMG-1073
Regarding the Critical Path Method (CPM) in construction planning, which of the following statements concerning Free Float are correct? 1. Free Float can exceed Total Float. 2. Free Float can exceed Independent Float. 3. Free Float can be equal to Total Float. 4. Free Float can be less than Independent Float.
Q9 · Level 3 · CM-PMG-1055
Identify the components that are integral to a derrick crane's structure from the following: (i) Mast (ii) Boom (iii) Bull wheel (iv) Jack
Q10 · Level 3 · CM-PMG-1124
For a project network where optimistic, most likely, and pessimistic time estimates are provided, and the contractual deadline is 75 units, what is the latest allowable time for event 2 to occur?
Q11 · Level 3 · CM-PMG-1301
The trapezoidal rule for volume calculation relies on which fundamental principle?
Q12 · Level 4 · CM-PMG-1198
In standard construction procedures, when an activity exhibits zero total float, it implies that:
Q13 · Level 4 · CM-PMG-1096
In the analysis of PERT, the time estimations for individual tasks and the likelihood of their completion are generally assumed to follow which probability distribution?
Q14 · Level 4 · CM-PMG-1282
The outlet pipe of a 'P trap' is typically inclined downwards from the horizontal at an angle of:
Q15 · Level 4 · CM-PMG-1214
A revised estimate for a project is required when the sanctioned budget is exceeded by a certain percentage due to fluctuations in material or labor costs. What is this threshold percentage?
Q16 · Level 5 · CM-PMG-0003
A PERT-CPM hybrid project has the following data for activity X: - Optimistic = 6, Most likely = 9, Pessimistic = 18 days - ES = 10, LS = 16 - Activity X feeds into activity Y (ES_Y = 19) and activity Z (ES_Z = 22). Calculate: (a) PERT expected time, (b) Total float, (c) Free float, (d) If the project deadline requires TF ≤ 3 days for all activities, should activity X be expedited, and by how much?
Q17 · Level 5 · CM-PMG-0008
A PERT network has two possible critical paths: Path 1: Expected duration = 40 days, Variance = 25 days² Path 2: Expected duration = 38 days, Variance = 49 days² The project deadline is 45 days. Which path is more likely to cause a delay, and what is the probability of completing the project within the deadline considering both paths?
Practice All 17+ Questions — Free, Leveled, Tracked →

More Construction Materials & Management Topics

Explore InfraLens