Formats  › Site Execution  › Weekly Progress Report
Register · FMT-SIT-017
Weekly Progress Report — Site
9 fields across 4 sections. Weekly review with client / PMC — feeds monthly progress + payment schedule.
9 Fields
4 Sections
Weekly — Monday morning
Project Manager, Planner

Format Preview

S.No.Field / CheckpointReferenceStatus
A. WEEKLY SUMMARY
A1Week ending + period
Acceptance: Reporting period clear
Standard week (Mon-Sun)
OK
NC
NA
A2Cumulative + this-week physical progress (% per WBS)
Acceptance: Variance tabled
Compare against schedule
OK
NC
NA
B. ACHIEVEMENT VS PLAN
B1Planned activities + actual activities
Acceptance: Variance analysis
From schedule
OK
NC
NA
B2Top 5 milestones achieved + delayed
Acceptance: RAG status
Critical path items
OK
NC
NA
C. RESOURCES
C1Manpower mobilised + productivity
Acceptance: Productivity index
Avg. man-days per WBS
OK
NC
NA
C2Plant utilisation %
Acceptance: Per equipment
(Working hrs / Available hrs) × 100
OK
NC
NA
C3Material stock status (critical items)
Acceptance: Days-on-hand
Cement, steel, blocks
OK
NC
NA
Showing 7 of 9 fields ·
A. WEEKLY SUMMARY
A1Week ending + period
Standard week (Mon-Sun)
Reporting period clear
OKNCNA
A2Cumulative + this-week physical progress (% per WBS)
Compare against schedule
Variance tabled
OKNCNA
B. ACHIEVEMENT VS PLAN
B1Planned activities + actual activities
From schedule
Variance analysis
OKNCNA
B2Top 5 milestones achieved + delayed
Critical path items
RAG status
OKNCNA
C. RESOURCES
C1Manpower mobilised + productivity
Avg. man-days per WBS
Productivity index
OKNCNA
C2Plant utilisation %
(Working hrs / Available hrs) × 100
Per equipment
OKNCNA
C3Material stock status (critical items)
Cement, steel, blocks
Days-on-hand
OKNCNA
Showing 7 of 9 ·
Approval / Sign-Off
APPROVED
HOLD — REVISIONS REQUIRED
REJECTED
Overall Verdict
Name / Sign / Date
Prepared By — Name / Sign
Name / Sign / Date
Reviewed By — Name / Sign
Name / Sign / Date
Approved By — Name / Sign
Name / Sign / Date
Date & Time
Name / Sign / Date
Remarks
Name / Sign / Date