Infra
Lens
IS Codes
IRC
Tools
SOR
Handbook
QA/QC
PMC
Formats
CPHEEO
Maps
Projects
BOQ
Rules
About
Join Channel
Join
IS Codes
IRC
Tools
SOR
Handbook
QA/QC
PMC
Formats
CPHEEO
Maps
Projects
BOQ Builder
DCR
Design Rules
BIM
About
Join WhatsApp Channel
🏗
BOQ Builder
·
Auto-BOQ from dimensions, DSR rates
NEW
→
📋
BidEasy
·
Government tenders, searchable
LIVE
→
▶
InfraLens App
·
Free on Play Store, offline-ready
NEW
→
Home
›
IS Codes
›
IS 10262:2019
›
Clauses
IS 10262:2019 — Clause Reference
8 detailed clauses with interactive calculators, reference tables, and practical notes.
Cl. 4.1
Target Mean Strength
Clause 4.1 establishes the target mean compressive strength (f'ck) that the mix must be designed to achieve. The target …
Calculator
1 table
Cl. 4.2
Selection of Water-Cement Ratio
Clause 4.2 covers the selection of the free water-cement ratio. The W/C ratio is first selected based on the generalized…
2 tables
Cl. 4.3
Estimation of Water Content
Clause 4.3 provides the estimated water content required per cubic metre of concrete for the desired workability. Table …
2 tables
Cl. 4.4
Calculation of Cement Content
Clause 4.4 determines the cement content from the free water content (Clause 4.3) and the selected water-cement ratio (C…
1 table
Cl. 4.5
Proportion of Coarse Aggregate and Fine Aggregate
Clause 4.5 determines the proportion of coarse aggregate (CA) and fine aggregate (FA) in the mix. Table 3 provides the v…
2 tables
Cl. 4.6
Mix Calculations
Clause 4.6 brings together all the preceding steps into a complete mix calculation using the absolute volume method. The…
2 tables
Cl. 4.7
Trial Mixes and Adjustments
Clause 4.7 mandates that the designed mix proportions must be verified through laboratory trial mixes before use in actu…
1 table
Cl. 5
Mix Design with Mineral Admixtures
Clause 5 extends the mix design procedure of Clause 4 to incorporate mineral admixtures such as fly ash (pulverised fuel…
2 tables