HDPE Distribution Network (per village)

HDPE (PE-100) water-distribution network per IS 4984 + IS 15164. Last-mile network from OHSR to households — trunk + sub-mains + lateral pipes + ferrule connections + sluice valves + air valves + house service connections. Configurable network length + HSC count. Rates: CPWD DSR Vol 1 (2023) + mjp_ssr_2024.

Visual confirmation
Visual schematics coming soon for this template.
Bill of Quantities11 items · CPWD DSR Vol 1 (2023) + mjp_ssr_2024
#CodeDescriptionUnitQtyRate (₹)Amount (₹)
12.8.1ExcavationEarth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, for all lift, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. — All kinds of soil.Cum2,640.00260.306,87,192.00
2BW.SANDBEDSand BeddingSand bedding for pipes.240.00640.001,53,600.00
3HDPE.110.PN6Hdpe Trunk 110HDPE PE-100 110mm PN-6 supply + laying.m800.00397.003,17,600.00
4HDPE.90.PN6Hdpe Submain 90HDPE 90mm PN-6 supply + laying.m1,500.00295.004,42,500.00
5HDPE.63.PN6Hdpe Lateral 63HDPE 63mm PN-6 supply + laying.m2,500.00162.004,05,000.00
6HDPE.FITT.SETFittings SetHDPE fittings set per 100 m.Set48.002,800.001,34,400.00
7HDPE.SLUICESluice ValveSluice valve 100 mm + chamber.Each8.0018,500.001,48,000.00
8HDPE.AIR.VLAir ValveAir valve 50 mm + chamber.Each4.0014,500.0058,000.00
9HDPE.HSCHouse ConnectionHSC complete with meter.Each350.003,400.0011,90,000.00
102.25BackfillFilling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 and for all lift.Cum2,160.00196.004,23,360.00
11DI.HYDROTESTHydraulic TestHydraulic test per metre.m4,800.0018.0086,400.00
Your inputsTrunk main length 800 m · Sub-mains length 1500 m · Laterals length 2500 m · House Service Connections 350 · Sluice valves 8 · Air valves 4 · Pipe cover depth 0.9 mTOTAL₹40,46,052
12.8.1₹6,87,192
Excavation
Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, for all lift, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. — All kinds of soil.
2,640.00 Cum× ₹260.30
2BW.SANDBED₹1,53,600
Sand Bedding
Sand bedding for pipes.
240.00 × ₹640.00
3HDPE.110.PN6₹3,17,600
Hdpe Trunk 110
HDPE PE-100 110mm PN-6 supply + laying.
800.00 m× ₹397.00
4HDPE.90.PN6₹4,42,500
Hdpe Submain 90
HDPE 90mm PN-6 supply + laying.
1,500.00 m× ₹295.00
5HDPE.63.PN6₹4,05,000
Hdpe Lateral 63
HDPE 63mm PN-6 supply + laying.
2,500.00 m× ₹162.00
6HDPE.FITT.SET₹1,34,400
Fittings Set
HDPE fittings set per 100 m.
48.00 Set× ₹2,800.00
7HDPE.SLUICE₹1,48,000
Sluice Valve
Sluice valve 100 mm + chamber.
8.00 Each× ₹18,500.00
8HDPE.AIR.VL₹58,000
Air Valve
Air valve 50 mm + chamber.
4.00 Each× ₹14,500.00
9HDPE.HSC₹11,90,000
House Connection
HSC complete with meter.
350.00 Each× ₹3,400.00
102.25₹4,23,360
Backfill
Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 and for all lift.
2,160.00 Cum× ₹196.00
11DI.HYDROTEST₹86,400
Hydraulic Test
Hydraulic test per metre.
4,800.00 m× ₹18.00
Trunk main length 800 m · Sub-mains length 1500 m · Laterals length 2500 m · House Service Connections 350 · Sluice valves 8 · Air valves 4 · Pipe cover depth 0.9 m
Estimated total
₹40,46,052
Notes & assumptions
  • Rates sourced from MJP SSR 2023-24 (with 2024-25 escalation column). 5 corrigenda dated up to 20-Dec-2024 exist (mjp.maharashtra.gov.in publications page) but are scanned-image PDFs in Marathi requiring manual review for tender-grade use. For cost feasibility this Builder is good as-is; for tender submission, cross-check each item against the latest corrigendum.
  • HDPE PE-100 PN-6 (rated 6 bar / 60 m head) is the JJM standard for village distribution networks. PN-10 for trunk mains where pressure exceeds 60 m head (uncommon at distribution end of network).
  • Pipe sizing rule-of-thumb: 110 mm OD trunk from OHSR for first 100-200 households, 90 mm sub-mains for branches serving 30-100 HH, 63 mm laterals for street-level pipes serving 5-30 HH per branch.
  • Cover depth 0.9 m is the CPHEEO + IS 4984 standard for distribution networks. Reduce to 0.6 m for utility-corridor protected sections; bump to 1.2 m under cultivated land + road crossings.
  • House Service Connection (HSC) is a per-household line — ferrule on the lateral, 15-25 mm MDPE service line to plot boundary, water meter chamber, connection to internal plumbing. Rate is per HSC complete.
  • Public stand-post taps were the JJM Phase-1 standard for community access; Phase-2 mandates individual HSC for every house. Public taps are still relevant for villages without internal plumbing infrastructure.
  • Fittings set = couplings + tees + reducers + end-caps. Estimated 1 set per 100 m of pipe. For tightly-meshed networks (urban + dense settlements), bump to 1 per 50 m.
  • PHED rates per state for HDPE PE-100: 63 mm: ₹70-110/m; 90 mm: ₹140-200/m; 110 mm: ₹200-300/m; rates include butt-welding + jointing. Verify locally.
  • Excludes: water meter at HSC (typically multi-jet brass, ₹500-1,500 each); zone-level master meters; SCADA / IoT telemetry (modern JJM-2 includes this — ₹5-10k per village); leak-detection devices; meter-reading software; flushing chambers at network ends; chlorine residual sensors.

The **HDPE distribution network** is the last-mile water-supply infrastructure that takes treated water from the OHSR to individual households via trunk mains + sub-mains + laterals + house service connections. Per **IS 4984 + IS 15164 + CPHEEO Manual** standard configuration: PE-100 PN-6 HDPE pipes (110 mm trunk + 90 mm sub-main + 63 mm lateral) buried 0.9 m deep with sand bedding, ferrule-connected HSC at every house, sluice valves at branch isolations, air valves at high points. This is the BIGGEST line item in JJM Village Water Supply — typically 35-50% of total village WSS cost. This Builder generates the complete cost per village — civil from CPWD DSR + HDPE pipe + fittings + valves + HSC from state PHED placeholder rates.

JJM (Jal Jeevan Mission) distribution network design rules

JJM Phase-2 mandates **Functional Household Tap Connection (FHTC)** — every house gets its own metered service connection. Designed for **55 lpcd minimum** (CPHEEO recommends 70 lpcd urban / 135 lpcd urban-municipal). Network is **looped** (not branch / tree) to ensure no dead-ends + better residual chlorine distribution. **Maximum service-area radius** from OHSR is 400-500 m for gravity flow at acceptable tail-end pressure (10 m residual head). **Pipe slope** is laid to follow ground profile with air valves at high points + scour valves at low points. **Material mandate**: HDPE PE-100 PN-6 for all sizes < 200 mm; DI K9 for ≥ 200 mm trunk mains.

House Service Connection (HSC) — what's included

Each HSC quote per JJM includes: (a) ferrule + saddle clamp on the lateral pipe; (b) 15-25 mm MDPE service line from lateral to plot boundary (typically 5-15 m); (c) water meter chamber with brick walls + CI / RCC cover; (d) multi-jet brass water meter (Class B + IS 779); (e) consumer side stop-tap + connection to internal plumbing; (f) all earthwork + reinstatement of road / footpath surface. Rate per HSC is typically ₹2,500 - 5,000 depending on state PHED + meter size. JJM provides full per-HSC funding under the FHTC scheme.

Disclaimer: Rates sourced from CPWD DSR Vol 1 (2023) + mjp_ssr_2024. Indicative for estimation only — actual tender quotations are governed by market forces, locality factors and current input prices. Quantities follow IS 1200 measurement. Always verify with a local quote before finalising. © InfraLens — infralens.in