ESTIMATION

Extension of Time (EoT)

Contractual grant of extra completion time for excusable (non-culpable) delay

Also calledextension of timeEoTtime extensioncompletion date extensiondelay extension
Definition

Extension of Time (EoT) is the contractual grant of additional time to the contractor to complete the works, moving the contractual completion date when completion is delayed by causes for which the contractor is not responsible — employer-caused delay, late information/access, variations, exceptional weather, force majeure and other 'excepted risks' defined in the contract. A properly assessed EoT keeps the time obligation realistic and, critically, preserves the employer's right to levy liquidated damages for any remaining culpable contractor delay (an unfairly refused or unassessed EoT can render the LD clause unenforceable).

EoT is one of the most contested areas of construction contracts. Assessment requires showing that the delaying event affected the critical path (using the contract programme/CPM), distinguishing excusable from culpable and concurrent delay, and following the contract's notice and substantiation procedure within the stipulated time. EoT addresses time only; whether the contractor is also entitled to additional payment (prolongation cost) is a separate question governed by the relevant cost/claim clauses.

Where used
  • Delay analysis + completion-date adjustment
  • Preserving the employer's liquidated-damages right
  • Variation, late-information + force-majeure claims
  • Concurrent-delay + critical-path assessment
  • Construction-claim, arbitration + dispute resolution
Acceptance / threshold
Granted per the contract delay clauses where an excusable event affects the critical path, with timely notice + substantiation per the contract procedure; addresses time only — prolongation cost is assessed separately under the relevant clauses.
Frequently asked
What is an extension of time in a construction contract?
A formal grant of extra time that moves the contractual completion date when the contractor is delayed by causes it is not responsible for (employer delay, variations, force majeure, exceptional weather).
Does an extension of time include extra payment?
Not automatically. EoT relieves the contractor of liquidated damages for the excused period (time), but any additional cost for prolongation is a separate entitlement assessed under the contract's cost/claim provisions.
Related terms